[Aidan, Radhika]
On Tuesday 6/7 we met to discuss next steps for getting PD testing up and running in CAML (cryo auxiliary mariner lab). Here is a rough 2-month plan:
Step 0 [1 week]: Get CAML workstation running and confirm connection to EPICS/CDS.
- Organize BNC cables coming in from QIL and connect to the PD testing table.
Step 1 [1 week]: Outline desired measurements and sketch diagram of electronics/components.
- Decide how we want these component organized; i.e. how many boxes, number of inputs/outputs per box.
Step 2 [2 weeks]: Implement desired setup.
Step 3 [2 weeks]: Replicate QE measurements on JPL PDs
- Tweak setup as necessary
Step 4 [2 weeks]: Test MCT detectors
|