Message ID: 2782     Entry time: Thu Jun 9 10:27:01 2022
Author: Radhika 
Type: DailyProgress 
Category: 2um Photodiodes 
Subject: PD testing plan in CAML lab 

[Aidan, Radhika]

On Tuesday 6/7 we met to discuss next steps for getting PD testing up and running in CAML (cryo auxiliary mariner lab). Here is a rough 2-month plan:

Step 0 [1 week]: Get CAML workstation running and confirm connection to EPICS/CDS. 

    - Organize BNC cables coming in from QIL and connect to the PD testing table. 

Step 1 [1 week]: Outline desired measurements and sketch diagram of electronics/components.

    - Decide how we want these component organized; i.e. how many boxes, number of inputs/outputs per box. 

Step 2 [2 weeks]: Implement desired setup.

Step 3 [2 weeks]: Replicate QE measurements on JPL PDs

    - Tweak setup as necessary

Step 4 [2 weeks]: Test MCT detectors

 