40m QIL Cryo_Lab CTN SUS_Lab TCS_Lab OMC_Lab CRIME_Lab FEA ENG_Labs OptContFac Mariner WBEEShop
  ATF eLog  Not logged in ELOG logo
Message ID: 1249     Entry time: Thu Jan 20 12:50:43 2011
Author: Zach 
Type: Lab Infrastructure 
Category: Computing 
Subject: fb0 put back into rack, moved to a better location 

 [Alastair, Zach]

We moved fb0 from its limbo on the floor back into the rack. Instead of putting it in its inane previous location (wedged into the very bottom and not fitting in all the way), we put it a little higher up and properly mounted it in. We didn't want to support the back with cable ties, so we found some random Bosch parts that served as pretty good supports. We should look into getting little supports that can screw into the backside of the rack to hold up the longer modules.

We also did some other reasonable things like screwing the lid back on the big blue ADC/DAC module so that the heavy power supply that someone put on top of it didn't crash through it when it was brushed against.

Picture:

fb0.png

ELOG V3.1.3-