Entry  Tue Jul 31 21:33:17 2012, Koji, General, General, Plan Update: August [!] 
Completed work of the previous months: [Jul] [Aug] [Sep] [Oct] [Nov] [Dec]

Facility/Supplies

    Work done
    
        Floor
Entry  Tue Jul 31 21:29:43 2012, Koji, General, General, Work completed in July [!] 

    Completed Work: Facility/Supplies
    
        Plug a big hole on the wall [ELOG]
        Purchasing work benches
Entry  Tue Jul 24 11:41:29 2012, Koji, General, General, Useful references 
Nicolas Smith,
LIGO Document T0900383-v1 
3mm Photodiode Characterization for Enhanced LIGO
Entry  Fri Jun 29 11:26:04 2012, Zach, Optics, Characterization, RoC measurement setup RoC_measurement_setup.pngRoC_measurement_setup.graffle.zip
Here is the proposed RoC measurement setup. Koji tells me that this is referred to as "Anderson's method".
We would like to use a linear cavity to measure the RoC of the curved mirrors independently (before forming the ring cavity), since the degeneracy
of HOMs will make the fitting easier.
    Reply  Sun Jul 22 15:56:53 2012, Zach, Optics, Characterization, RoC measurement setup detailed_RoC_setup.pngdetailed_RoC_setup.graffle.zip
Here is a more detailed version of the setup, so that we can gather the parts we will need.
Entry  Wed Jul 18 23:20:13 2012, Koji, Optics, Characterization, Mode scan results of ELIGO 
Nic Smith sent me a bunch of elog lists where the results of the mode scan can be found.
From Nic:
There have been many mode scan analyses done at LLO:
Entry  Sat Jul 14 02:16:07 2012, Koji, General, General, Plan Update: July P7071878.jpg
Facility/Supplies

    Work in progress     
    
        Floor cleaning
        Plug slits on the roof of the HEPA booth - blanking panels have been ordered 
Entry  Thu Jun 21 03:07:27 2012, Zach, Optics, Configuration, Parameter selection / mode definition geom_bowtie.pnggeom_non-bowtie.png
EDIT 2 (ZK): As with the previous post, all plots and calculations
here are done with my MATLAB cavity modeling utility, 
Entry  Wed Jun 20 20:37:45 2012, Zach, Optics, Configuration, Topology / parameter selection 8x
EDIT (ZK): All the plots here were generated using my MATLAB
cavity modeling tool, ArbCav
Entry  Wed Jun 20 00:10:53 2012, Koji, Facility, General, Hole on the wall was patched P6191706.jpg
 
Entry  Sat Jun 16 08:53:09 2012, Koji, General, General, To Do List 
Facility

    Work
    
        Replacing wooden work benches
        
    
       W60" x H28-34" x D30" 
Entry  Fri Jun 15 15:45:49 2012, Koji, General, General, OMC Plan 
LIGO Document G1200683-v1: 
aLIGO OMC fabrication and testing plan
aLIGO OMC wiki