313
|
Sat Jan 12 22:49:11 2019 |
Koji | Optics | Characterization | PM-SM patch cable mode cleaning effect | Mode
cleaning capability of an optical fiber was
measured. The conclusion |
|
103
|
Mon Apr 8 20:56:52 2013 |
Koji | Optics | Configuration | PZT & Curverd Mirror arrangement | Assembly #1:
Mounting Prism #16
PZT #26 |
|
149
|
Fri Aug 9 10:09:56 2013 |
Koji | General | General | PZT Assembly #3/#4 | Yesterday, Jeff and I bonded the PZT assemblies
(#3/#4).
The attached is the arrangement of |
|
150
|
Mon Aug 12 20:22:19 2013 |
Koji | General | General | PZT Assembly #5/#6 | PZT Assembly #5/#6 were glued on Fri Aug
9th
They are removed from the fixture |
|
148
|
Sat Jul 6 17:10:07 2013 |
Koji | Mechanics | Characterization | PZT Response analysis | Analysis of the PZT scan / TF data taken
on May 31st and Jun 1st.
[DC scan] |
 |
374
|
Thu Sep 5 15:40:42 2019 |
shruti | Optics | Configuration | PZT Sub-Assembly | Aim: To find the combinations
of mounting prism+PZT+curved mirror to build
two PZT sub-assemblies that best minimises |
  |
102
|
Mon Apr 8 11:49:18 2013 |
Koji | Mechanics | Characterization | PZT actuator tested at LLO | Test result of the PZTs by Valera and Ryan
PZT Length Angle
#
[nm/V] [urad/um]
11 14.5 17.6
|
|
104
|
Mon Apr 8 21:11:14 2013 |
Koji | Optics | General | PZT assembly gluing | [Jeff, Zach, Koji]
PZT assembly gluing
Glue gun -> to be returned to |
|
106
|
Tue Apr 9 13:56:09 2013 |
Koji | Optics | General | PZT assembly post gluing / pre baking pictures |
|
|
77
|
Sat Mar 23 13:34:14 2013 |
Koji | Optics | General | PZT assembly prototype glued |
Prototype
PZT assembly |
   |
202
|
Tue Jul 8 18:54:54 2014 |
Koji | Mechanics | Characterization | PZT characterization | Each PZT was swept with 0-150V 11Hz triangular
wave.
Time series data for 0.2sec was recorded |
 |
314
|
Fri Feb 1 12:52:12 2019 |
Koji | Mechanics | General | PZT deformation simulation | A simple COMSOL simulation was run to see
how the PZT deforms as the voltage applied.
Use the geometry of the ring PZT |
|
156
|
Thu Aug 22 15:40:15 2013 |
Koji | Electronics | Configuration | PZT endurance test | [Koji, Jeff]
Background
In response to the failure of one |
   |
157
|
Fri Aug 23 19:24:32 2013 |
Koji | Electronics | Configuration | PZT endurance test (II) | The
PZT tests were finished with the conclusion
that the PZT won't be damaged with our expected |
|
328
|
Thu Apr 11 12:15:31 2019 |
Koji | Mechanics | Configuration | PZT sub assy mirror orientations | |
 |
312
|
Thu Jan 10 20:45:00 2019 |
Koji | Optics | Characterization | PZT test cable | As OMC SN002 already has the PZTs connected
to the Mighty-Mouse connector, a test cable
with a female mighty-mouse connector was |
|
203
|
Thu Jul 10 01:39:38 2014 |
Koji | Electronics | General | PZT wire | Rich came to the OMC lab. Pins for the
mighty mouse connector were crimped on the
4 PZT wires. |
|
5
|
Thu Jun 21 03:07:27 2012 |
Zach | Optics | Configuration | Parameter selection / mode definition | EDIT 2 (ZK): As with the |
 |
17
|
Mon Aug 13 17:01:35 2012 |
Koji | Clean | General | Particle Counts | Aug 13, 2012 / 0.5um 1000~2000/(0.1 cu
ft) / 0.7um 400-600/(0.1 cu ft)
by ATF particle counter (MET ONE 227A) |
|
20
|
Tue Sep 25 14:18:14 2012 |
Koji | Clean | General | Particle Counts | Particle counts
Before the prefilter is installed:
0.5um 1191cnts, 0.7um 346cnts |
|
21
|
Mon Oct 1 16:06:55 2012 |
Koji | Clean | General | Particle Counts | 1. It turned out that the particle
counter MET ONE 227A at ATF shows
(particle count)/(0.1 ft^3) |
|
398
|
Fri Oct 23 19:09:54 2020 |
Koji | General | General | Particle counter transfered to Radhika | See this entry: https://nodus.ligo.caltech.edu:8081/40m/15642 |
|
63
|
Thu Feb 21 18:44:18 2013 |
Koji | Optics | Configuration | Perpendicularity test | Perpendicularity test of the mounting
prisms:
The perpendicularity of the prism |
 |
246
|
Tue Dec 15 13:39:13 2015 |
Koji | Electronics | Characterization | Phase noise measurement of aLIGO EOM drivers | This measurement has been done on Dec 1st,
2015.
The phase noise added by |
 |
13
|
Tue Jul 31 21:33:17 2012 |
Koji | General | General | Plan Update: August [!] | Completed work of the previous months:
[Jul]
[Aug] [Sep] [Oct] [Nov] [Dec] |
|
7
|
Sat Jul 14 02:16:07 2012 |
Koji | General | General | Plan Update: July | Facility/Supplies
Work in progress |
|
34
|
Wed Nov 7 20:44:11 2012 |
Koji | General | General | Plan Update: November [!] | Completed work of the previous months:
[Jul]
[Aug] |
|
29
|
Tue Oct 16 15:51:01 2012 |
Koji | General | General | Plan Update: October [!] | Completed work of the previous months:
[Jul]
[Aug] |
|
136
|
Mon Jun 3 21:19:03 2013 |
Koji | General | General | Planning | Monday - Evening
(Koji)
[done] - DCPD alignment |
|
395
|
Thu Oct 8 19:55:22 2020 |
Koji | General | Characterization | Power Measurement of Mephisto 800NE 1166A | The output of Mephisto 800NE (former TNI
laser) was measured.
The output power was measured with |
|
227
|
Wed Jul 22 09:43:01 2015 |
Koji | Electronics | AM Stabilized EOM Driver | Power supply test of the EOM/AOM Driver | Serial Number of the unit: S1500117
Tester: Koji Arai |
|
399
|
Fri Nov 6 18:38:00 2020 |
Koji | General | General | Powermeter lent from OMC Lab to 2um ECDL | Thorlabs' powermeter controler +
S401C head was lent from OMC Lab. Returned
to OMC Jul 15, 2022 KA |
|
290
|
Thu Nov 30 12:18:41 2017 |
Stephen | General | General | Preparation for Modal Testing on 4 December | Norna Robertson, Stephen Appert ||
29 Nov 2017, 2 pm to 4 pm ||
227 Downs, CIT |
|
288
|
Fri Sep 8 15:14:05 2017 |
Koji | Facility | General | Preparation for the plumbing work | [Steve, Aaron, Koji]
We've finished the preparation
for the forthcoming plumbing work on (nominally) |
7x |
264
|
Mon Aug 15 10:09:10 2016 |
Koji | General | General | Prev H1 OMC shipped to CIT | Previous H1 OMC shipped from LHO to CIT
https://ics-redux.ligo-la.caltech.edu/JIRA/browse/Shipment-8196 |
|
44
|
Tue Dec 18 20:04:40 2012 |
Koji | Optics | Characterization | Prism Thickness Measurement | The thicknesses of the prism mirrors (A1-A5)
were measured with micrometer thickness gauge.
Since the thickness of the thinner |
|
274
|
Thu Jan 19 20:57:53 2017 |
Koji | Supply | General | Purchase | Ordered:
Office Depot
v AA battery Qty. 24 |
|
275
|
Thu Feb 16 17:23:12 2017 |
Koji | Supply | General | Purchase |
BNC Patch Panel
8x
Amphenol Connex 112443 / Isolated BNC FEMALE
TO FEMALE BULKHEAD ISOLATED ADAPTER - 50 |
|
321
|
Thu Apr 4 20:07:39 2019 |
Koji | Supply | General | Purchase | == Office Depot ==
Really
Useful Box 9L x 6 (delivered) |
|
258
|
Tue Apr 5 18:14:55 2016 |
Koji | General | Loan / Lending | QPD Lending Crackle | Xiaoyue
QPD head
X-Z stage |
|
132
|
Thu May 30 15:00:28 2013 |
Koji | Optics | General | QPD alignment | The QPD alignment was adjusted using
the aligned beam to the cavity and the 4ch
transimpedance amplifier. |
|
133
|
Fri May 31 05:46:54 2013 |
Koji | Optics | General | QPD alignment | Peter F suggested to check the bottom surface
of the PD housings if there is any protrusion/interference/whatever.
And that was true! It was found that |
  |
171
|
Tue Oct 15 18:50:08 2013 |
Koji | Optics | Characterization | QPD alignment | 1) Deburr the bottom surfaces of the QPD
housings
2) Aligned the QPDs |
|
115
|
Wed Apr 17 07:30:04 2013 |
Koji | Optics | General | QPD path glued | Yesterday,
all of the glass components for the QPD path
were glued. |
|
231
|
Mon Aug 10 02:11:47 2015 |
Koji | Electronics | AM Stabilized EOM Driver | RF AM Measurement Unit E1500151 | This is an entry for the work on Aug 3rd.
LIGO
DCC E1500151 |
  |
232
|
Mon Aug 10 11:39:40 2015 |
Koji | Electronics | AM Stabilized EOM Driver | RF AM Measurement Unit E1500151 | Entry for Aug 6th, 2015
I faced with difficulties to operate
the RF AM detectors. |
|
233
|
Mon Aug 10 11:57:17 2015 |
Koji | Electronics | AM Stabilized EOM Driver | RF AM Measurement Unit E1500151 | Spending some days to figure out how to
program CPLD (Xilinx CoolRunner II XC2C384).
I learned that the JTAG cable which |
|
234
|
Mon Aug 10 12:09:49 2015 |
Koji | Electronics | AM Stabilized EOM Driver | RF AM Measurement Unit E1500151 | Still suffering from a power supply
issue!
I have been tracking the issues |
|
238
|
Fri Aug 28 02:14:53 2015 |
Koji | Electronics | AM Stabilized EOM Driver | RF AM Measurement Unit E1500151 ~ 37MHz OCXO AM measurement | In order to check the noise level
of the RFAM detector, the power and cross
spectra for the same signal source |
|
240
|
Tue Sep 8 10:55:31 2015 |
Koji | Electronics | AM Stabilized EOM Driver | RF AM Measurement Unit E1500151 ~ 37MHz OCXO AM measurement | Test sheet: https://dcc.ligo.org/LIGO-E1400445
Test Result (S1500114): https://dcc.ligo.org/S1500114 |
|