  616   Wed Aug 23 07:48:14 2023 Camille Makarem, TejasOpticsCharacterizationFSR and TMS measuarement of A+ build

[Camille, Thejas]
22 August 2023

We used the network analyzer to measure the FSR of the cavity using the method described in section 3.2.1 of T1500060. We locked the OMC cavity and maximized transmission the TEM00 mode. (REFL PD signal was ~45-50mV and REFL CCD looked the same as in 610). We adjusted to input offset on the servo module (REFL PD signal ~95mV) and recorded the transfer function between the modulation signal (channel R) and the transmission PD signal (channel A). (See attached picture of transfer function and phase.) We fit the FSR data to the code to get a value of 264.658982 MHz.

We also recorded the TMS of the cavity (with 0V to the PZTs). We measured the horizontal and vertical mode spacing separately. After maximizing transmission of TEM00, we then used the fiber coupler to misalign in the vertical direction first (REFL PD signal ~100). Using the network analyzer, we observed the peak at ~58 MHz. We then misaligned the mirror that steers the transmited beam to the PD. We clipped the transmitted beam so as to maximize the peak at ~58 MHz. (See attached spectrum.)
We recoved vertical alignment and then repeated this process for the horizontal direction. (See attached spectrum.)

Analysis in the next elog entry. 

File names:
test_22-08-2023_160812 --> FSR
test_22-08-2022_165728 --> TMS vertical
test_22-08-2022_170543 --> TMS horizontal
https://gla-my.sharepoint.com/personal/t_seetharamu_1_research_gla_ac_uk/_layouts/15/onedrive.aspx?id=%2Fpersonal%2Ft%5Fseetharamu%5F1%5Fresearch%5Fgla%5Fac%5Fuk%2FDocuments%2FA%2B%20OMC%20%231%2F22%5F08%5F2023&view=0

Attachment 1: test_22-08-2023_165728.pdf
test_22-08-2023_165728.pdf
Attachment 2: test_22-08-2023_170543.pdf
test_22-08-2023_170543.pdf
Attachment 3: FSR_CavityLength.PNG
FSR_CavityLength.PNG
  617   Thu Aug 24 12:30:58 2023 Camille Makarem, Thejas OpticsCharacterizationFSR and TMS analysis

Attached are the analysis results from the measurements in 616.
FSR: 264.657354 +/- 0.003444 MHz

Pitch TMS: 58.45691858660249 MHz

Yaw TMS: 58.55821902092523 MHz

The attached plot shows the HOM spectrum with their sidebands. We see that there is overlap between TEM00 and one of the 9th-order modes which means this higher order mode will resonate with the TEM00 carrier.
We estimate that by increasing the FSR to ~266.7 MHz, we will avoid this as shown in the next attached plot (HOM_scan.pdf).
This will require us to decrease the cavity length by 16mm (4 mm each mirror). We plan begin adjusting the micrometers this afternoon.

Attachment 1: TMS.PNG
TMS.PNG
Attachment 2: HOM_scan.pdf
HOM_scan.pdf
Attachment 3: FSR_Scan_FitFSR_TF_22-08-2023_160812.pdf
FSR_Scan_FitFSR_TF_22-08-2023_160812.pdf
  618   Thu Aug 24 16:09:46 2023 Camille MakaremOpticsGeneralPZT length-to-angle coupling

[Camille, Thejas]

We checked the length-to-angle coupling of each PZT by monitoring the position of the transmitted beam on the CCD camera. The CCD camera was placed behind the steering mirror that guides the transmitted beam to the PD. We used a ThorLabs piezo controller to actuate the PZT.

We first tested PZT2. We increased the voltage to PZT2 in 50V increments from 0V to 150V. We did not observe any change in the position of the transmitted beam. We monitored the signal of the TRANS PD on the scope and did not see any change. (The signal was between 191-195V.) We monitored the REFL CCD and did see changes in the beamshape, which was expected (see pictures). The REFL PD signal also increased slightly with PZT actuation (see attachment).

We repeated this process for PZT1, which showed similar results (see attachment). We did not observe any movement in the position of the transmitted beam. Increasing PZT voltage shows increasing pitch misalignment in the REFL CCD and increasing REFL PD signal.

Attachment 1: PZT2.jpg
PZT2.jpg
Attachment 2: PZT1.jpg
PZT1.jpg
  621   Wed Aug 30 12:38:52 2023 Thejas OpticsGeneralA+ OMC #1: HOM spectrum

Examination into bonding template confimred the limitation of space available to change cavity length by at least 10 mm to improve the cavity HOM spectrum. Here's an anlysis of HOM spectrum for various possible ROCs and corresponding required cavity length change for optimum HOM spectrum. 

Assume: Astigmatism: Rx-Ry = 8mm

Current cavity length: 1.132 m

Ry = measured, Desired Cavity length: <1.12476 m

Ry = 2.5 m, Desired cav length: >1.13876 m

Ry = 2.55 m, “: No change 

Ry = 2.6 m, “:<1.12

So travel range of ~ (1.138 - 1.12) / 4 = 5 mm on each CM is required. WIth a safety factor for alignemnt say we require 30 mm/4 ~ 7 mm on each curved mirror.

  623   Mon Sep 18 15:08:26 2023 Thejas OpticsGeneralOMC HEPA enclosure filter fan speed

I went in lab today and turned the HEPA filter (clsoe to the entrance) to high since we are not doing any measurements at the moment. 

 

 

  624   Mon Sep 18 15:09:55 2023 Thejas OpticsCAvity BondingPiezo inertial micromaters

New piezo actuated micrometers from thorlabs arrived last week. 

4 x MPIA10

1 x KPS201

1 x KIM101 

 

One of the micrometers' fucntioning was checked (SN..229). The micrometer was checked in jogging mode and velocity control mode using the software. 

 

  52   Sun Jan 6 23:22:21 2013 KojiMechanicsGeneralSolidWorks model of the OMC suspension

D0900295_AdvLIGO_SUS_Output_Mode_Cleaner_Overall_Assembly.png

Attachment 2: D0900295_AdvLIGO_SUS_Output_Mode_Cleaner_Overall_Assembly.easm
  58   Tue Jan 22 17:56:32 2013 KojiMechanicsGeneralRotary stage selection

Newport UTR80

Newport 481-A (SELECTED)

  • Sensitivity: 15 arcsec
  • Graduations: 1 deg
  • Vernier: 5 arcmin
  • Fine travel range: 5 deg
  • With Micrometer

Newport RS40

  • Sensitivity: 16 arcsec
  • Graduations: 2 deg
  • Vernier: 12 arcmin
  • Fine travel range: 10 deg
  • Micrometer BM11.5

Newport RS65

  • Sensitivity: 11 arcsec
  • Graduations: 2 deg
  • Vernier: 12 arcmin
  • Fine travel range: 10 deg
  • Micrometer SM-06 to be bought separately

Elliot science MDE282-20G

  • Sensitivity: 5 arcsec
  • Graduations: 2 deg
  • Vernier: 10 arcmin
  • Fine travel range: 10 deg
  • Micrometer 2 arcmin/1div
  • Metric

Suruga precision B43-110N

Thorlabs precision B43-110N

  69   Thu Mar 7 15:53:47 2013 KojiMechanicsGeneralOMC Transportation fixture, OMC PD/QPD mounts

P3073218.JPG 

P3073219.JPG

P3073223.JPG

P3073225.JPG

P3073227.JPG

  70   Thu Mar 14 17:06:21 2013 KojiMechanicsGeneralOMC SUS work @LLO

EDIT (ZK): All photos on Picasa. Also, I discovered that since Picasa was migrated to Google+ only,
you no longer have the option to embed a slideshow like you used to. Lame, Google.

Photos sent from Zach

(3D VIEW)

2013-03-14_16.04.07.jpg2013-03-14_16.03.40.jpg

  90   Mon Apr 1 10:28:03 2013 KojiMechanicsGeneralAdditional UV blast for the top surface

[Koji, Lisa, Jeff, Zach]

Jeffs concern after talking with the glue company (EMI) was that the UV blast for the top side was not enough.

First we wanted to confirm if too much blasting is any harmful for the glue joint.

We took a test joint of FS-FS with the UV epoxy. We blasted the UV for 1min with ~15mm distance from the joint.
After the observation of the joint, we continued to blast more.
In total, we gave additional 5min exposure. No obvious change was found on the joint.

P3283483.JPG

Then proceed to blast the OMC top again. We gave 1 min additional blast on each glue joint.

 P3283459.jpg P3283473.JPG

  92   Wed Apr 3 17:39:38 2013 KojiMechanicsCharacterizationCalibration of the test PZTs before the glue test

We want to make sure the responses of the PZT actuator does not change after the EP30-2 gluing.

A shadow sensor set up was quickly set-up at the fiber output. It turned out the ring PZTs are something really not-so-straightforward.
If the PZT was free or just was loosely attached on a plane by double-sided tape, the actuation response was quite low (30% of the spec).
After some struggle, I reached the conclusion that the PZT deformation is not pure longitudinal but some 3-dimensional, and you need to
use a "sandwitch" with two flat surfaces with some pressue.

I turned the setup for horizontal scans to the vertical one, and put the PZT between quarter-inch spacers.
Then two more spacers are placed on the stack so that the weight applies the vertical pressure on the PZT.
This is also use ful to adjust the height of the shadow.

P4033491.JPG

The calibration plot is attached. It gives us ~21k V/m.
Voltage swing of 150V results the output voltage change of ~50mV.  This is pretty close to what is expected from the spec (16nm/V).
The PZT#3 (which had the mirror glued on) showed significantly large response.

Test PZT #1: 17.4nm/V
Test PZT #2: 17.2nm/V
Test PZT #3: 30.6nm/V
UHV PZT #24: 17.6nm/V

These numbers will be checked after the heat cure of EP30-2

Attachment 2: shadow_sensor_calib.pdf
shadow_sensor_calib.pdf
  98   Fri Apr 5 14:39:26 2013 KojiMechanicsCharacterizationCalibration of the test PZTs after the heat cure

We attached fused silica windows on the test PZTs. http://nodus.ligo.caltech.edu:8080/OMC_Lab/93

The glued assemblies were brought to Bob's bake lab for the heat cure. There they are exposed to 94degC heat for two hours (excluding ramp up/down time).

After the heat cure, we made the visual inspection.
The photos are available here.

Pre-bake
Test PZT #1: 17.4nm/V
Test PZT #2: 17.2nm/V
Test PZT #3: 30.6nm/V

Post-bake
Test PZT #1: 27.2 nm/V
Test PZT #2: 26.9 nm/V
Test PZT #3: 21.4 nm/V

Measurement precision is ~+/-20%
Spec is 14nm/V

Attachment 1: shadow_sensor_calib_after_bake.pdf
shadow_sensor_calib_after_bake.pdf
Attachment 2: PZTresponse.pdf
PZTresponse.pdf
  102   Mon Apr 8 11:49:18 2013 KojiMechanicsCharacterizationPZT actuator tested at LLO

Test result of the PZTs by Valera and Ryan

PZT  Length Angle
 #   [nm/V] [urad/um]
 11  14.5   17.6
 12  13.8   17.8
 13  11.2   25.0
 14  14.5    6.6
 15  12.5   10.6

 21  14.5    9.7
 22  13.8   28.8
 23  14.5    6.8  ==> Assembly #2
 24  18.5   51.7  ==> Used for prototyping
 25  17.1   13.8
 26  14.5    6.6  ==> Assembly #1
  124   Mon May 13 14:49:35 2013 KojiMechanicsCharacterizationMounting Glass Bracket still broke with tightenin stress

[Koji / Jeff]

This is the elog about the work on May 9th.

We made two glass brackets glue on the junk 2" mirrors with the UV glue a while ago when we used the UV bonding last time.

On May 7th:

We applied EP30-2 to the glass brackets and glued invar shims on them. These test pieces were left untouched for the night
and brought to Bob for heat curing at 94degC for two hours.

On May 9th:

We received the test pieces from Bob.

First, a DCPD mount was attached on one of the test pieces. The fasteners were screwed at the torque of 4 inch lb.
It looked very sturdy and Jeff applied lateral force to break it. It got broken at once side of the bracket.

We also attached the DCPD mount to the other piece. This time we heard cracking sound at 2 inch lb.
We found that the bracket got cracked at around the holes. As the glass is not directly stressed by the screws
we don't understand the mechanism of the failure.

After talking to PeterF and Dennis, we decided to continue to follow the original plan: glue the invar shims to the brackets.

We need to limit the fastening torque to 2 inch lb.

  125   Mon May 13 14:59:16 2013 KojiMechanicsGeneralInvar shim gluing

The invar reinforcement shims were glued on the glass brackets on the breadboard.
We worked on the light side on May 10th and did on the dark side on May 13rd.

U-shaped holding pieces are used to prevent each invar shim to be slipped from the right place.

We are going to bring the OMC breadboard to the bake oven tomorrow to cure the epoxies and promote the outgasing.

  130   Thu May 23 23:41:48 2013 KojiMechanicsGeneralDCPD/QPD Mount

DCPD mounts and QPD mounts were attached on the breadboard. They are not aligned yet and loosely fastened.

DCPD (mounting 4-40x5/16 BHCS Qty4)

Face plates fatsened by 4-40x5/16 BHCS (24 out of 40)

Housing   Face plate Destination  PD
002       002        L1OMC DCPD1  #10
003       003        L1OMC DCPD2  #11
004
       004        H1OMC DCPD1
008
       005        H1OMC DCPD2
009
       006        I1OMC DCPD1
010
       007        I1OMC DCPD2

QPD (mounting 4-40x5/16 BHCS Qty4)

Face plates fatsened by 4-40x1/4 BHCS (24 out of 80)

Housing   Face plate Destination QPD
002       002        L1OMC QPD1  #38 #43 swapped on 29th May.
003       003
        L1OMC QPD2  #43 #38 swapped on 29th May.
004
       004        H1OMC QPD1
005
      005        H1OMC QPD2
006
      006        I1OMC QPD1
007
      007        I1OMC QPD2

* 4-40x5/16 BHCS Qty 8 left
* 4-40x5/16 BHCS Qty 56 left

Cut the diode legs by 3mm

 

  148   Sat Jul 6 17:10:07 2013 KojiMechanicsCharacterizationPZT Response analysis

Analysis of the PZT scan / TF data taken on May 31st and Jun 1st.

[DC scan]

Each PZT was shaken with 10Vpp 1Hz triangular voltage to the thorlabs amp.
The amp gain was x15. Abut 4 TEM00 peaks were seen on a sweep between 0 and 10V.

The input voltage where the peaks were seen was marked. Each peak was mapped on the
corresponding fringe among four. Then the each slope (up and down) was fitted by a iiner slope.
Of course, the PZTs show hystersis. Therefore the result is only an approximation.

PZT1: PZT #26, Mirror C6 (CM1)
PZT2: PZT #23, Mirror C5 (CM2)

PZT arrangement [ELOG Entry]

PZT1:
Ramp Up        13.21nm/V
Ramp Down   13.25nm/V
Ramp Up        13.23nm/V
Ramp Down   13.29nm/V

=> 13.24+/-0.02 nm/V

PZT2:
Ramp Up        13.27nm/V
Ramp Down   12.94nm/V
Ramp Up        12.67nm/V
Ramp Down   12.82nm/V

=> 12.9+/-0.1 nm/V

[AC scan]

The OMC cavity was locked with the fast laser actuation. Each PZT was shaken with a FFT analyzer for transfer function measurments.
(No bias voltage was given)

The displacement data was readout from the laser fast feedback. Since the UGF of the control was above 30kHz, the data was
valid at least up to 30kHz. The over all calibration of the each curve was adjusted so that it agrees with the DC response of the PZTs (as shown above).

The response is pretty similar for these two PZTs. The first series resonance is seen at 10kHz. It is fairly high Q (~30).

Attachment 1: PZT_Scan.pdf
PZT_Scan.pdf
Attachment 2: L1OMC_PZT_Response.pdf
L1OMC_PZT_Response.pdf
  158   Tue Aug 27 17:02:31 2013 KojiMechanicsCharacterizationSpot position measurement on the diode mounts

After the PZT test, the curved mirrors were aligned to the cavity again.

In order to check the height of the cavity beam, the test DCPD mount was assembled with 2mm shim (D1201467-3)
The spot position was checked with a CCD camera.

According to the analysis of the picture, the spot height is about 0.71mm lower than the center of the mount.

Attachment 1: DCPD1.png
DCPD1.png
  160   Thu Aug 29 18:55:36 2013 KojiMechanicsGeneralI1 OMC top side gluing (UV)

The glass components for the I1 OMC top side were glued by the UV glue.

Breadboard SN#4
Wire bracket SN#5/6/7/8

  202   Tue Jul 8 18:54:54 2014 KojiMechanicsCharacterizationPZT characterization

Each PZT was swept with 0-150V 11Hz triangular wave.
Time series data for 0.2sec was recorded for each PZT.

The swept voltage at the resonances were extracted and the fringe number was counted.
Some hysteresis is seen as usual.

The upward/downward slopes are fitted by a linear line.

The average displacement is 11.3nm/V for PZT1 and 12.7nm/V.

The PZT response was measured with a FFT analyzer. The DC calibration was adjusted by the above numbers.

Attachment 1: PZT_Scan.pdf
PZT_Scan.pdf
Attachment 2: I1OMC_PZT_Response.pdf
I1OMC_PZT_Response.pdf
  210   Thu Jul 17 02:19:20 2014 KojiMechanicsCharacterizationI1OMC vibration test

Summary

- The breadboard has a resonance at 1.2kHz. The resonant freq may be chagned depending on the additional mass and the boundary condition.

- There is no forest of resonances at around 1kHz. A couple of resonances It mainly starts at 5kHz.

- The PZT mirrors (CM1/CM2) have the resonance at 10kHz as I saw in the past PZT test.


Motivation

- Zach's LLO OMC characterization revealed that the OMC length signals have forest of spikes at 400-500Hz and 1kHz regions.

- He tried to excite these peaks assuming they were coming from mechanical systems. It was hard to excite with the OMC PZT,
but actuating the OMCS slightly excited them. (This entry)

Because the OMC length control loop can't suppress these peaks due to their high frequency and high amplitude, they limit
the OMC residual RMS motion. This may cause the coupling of the OMC length noise into the intensity of the transmitted light.
We want to eventually suppress or eliminate these peaks.

By this vibration test we want to:

- confirm whether the peaks are coming from the OMC or not.
- identify what is causing the peaks if they are originated from the OMC
- correct experimental data for comparison with FEA

Method

- Place a NOLIAC PZT on the object to be excited.
- Look at the actuation signal for the OMC locking to find the excited peaks.

Results

Breadboard

- This configuration excited the modes between 800-1.2kHz most (red curve). As well as the others, the structures above 5kHz are also excited.

- The mode at 1.2kHz was suspected to be the bending mode of the breadboard. To confirm it, metal blocks (QPD housing and a 4" pedestal rod)
  were added on the breadboard to change the load. This actually moved (or damped) the mode (red curve).

- Note that the four corners of the breadboard were held with a PEEK pieces on the transport fixture.
  In addition, the installed OMC has additional counter balance mass on it.
  This means that the actual resonant frequency can be different from the one seen in this experiment. This should be confirmed with an FEA model.
  The breadboard should also exhibit higher Q on the OMCS due to its cleaner boundary condition. 

 

I1OMC_vibration_test_Breadboard.png

DCPD / QPD

- Vibration on the DCPDs and QPDs mainly excited the modes above 3kHz. The resonances between 3 to 5kHz are observed in addition to the ubiquitous peaks above 5kHz.
  So are these coming from the housing? This also can be confirmed with an FEA model.

- Some excitation of the breadboard mode at 1.2kHz is also seen.

 

I1OMC_vibration_test_DCPD.pngI1OMC_vibration_test_QPD.png

CM1/CM2 (PZT mirrors)

- It is very obvious that there is a resonance at 10kHz. This was also seen in the past PZT test. This can be concluded that the serial resonance of the PZT and the curved mirror.
- There is another unknown mode at around 5~6kHz.

- Some excitation of the breadboard mode at 1.2kHz is also seen.

I1OMC_vibration_test_CM.png

FM1/FM2 and Peripheral prism mirrors (BSs and SMs)

- They are all prism mirrors with the same bonding method.

- The excitation is concentrated above 5kHz. Small excitation of the breadboard mode at 1.2kHz is also seen. Some bump ~1.4kHz is also seen in some cases.

I1OMC_vibration_test_FM.png I1OMC_vibration_test_Prism.png

Beam dumps

- The excitation is quite similar to the case of the peripheral mirrors. Some bump at 1.3kHz.

I1OMC_vibration_test_BD.png


Other tapping test of the non-OMC object on the table

- Transport fixture: long side 700Hz, short side 3k. This 3K is often seen in the above PZT excitation

- Fiber coupler: 200Hz and 350Hz.

- The beam splitter for the back scattering test: 900Hz

  211   Sun Jul 20 17:19:50 2014 KojiMechanicsCharacterizationI1OMC vibration test ~ 2nd round

Improved vibration measurement of the OMC

Improvement

- Added some vibration isolation. Four 1/2" rubber legs were added between the OMC bread board and the transport fixture (via Al foils).
  In order to keep the beam height same, 1/2" pedestal legs were removed.

- The HEPA filter at the OMC side was stopped to reduce the excitation of the breadboard. It was confirmed that the particle level for 0.3um
  was still zero only with the other HEPA filter.


Method

- Same measurement method as the previous entry was used.

Results

Breadboard

- In this new setup, we could expect that the resonant frequency of the body modes were close to the free resonances, and thus the Q is higher.
  Noise is much more reduced and it is clear that the resonance seen 1.1kHz is definitely associated with the body mode of the breadboard (red curve).

  As a confirmation, some metal objects were placed on the breadboard as tried before. This indeed reduced the resonant frequency (blue curve).

I1OMC_vibration_test_Breadboard.pngI1OMC_vibration_test_Breadboard_HiRes.png

DCPD / QPD

- Vibration on the DCPDs and QPDs mainly excited the modes above 2~3kHz.
  In order to check if they are coming from the housing, we should run FEA models.

- Some excitation of the breadboard mode at 1.1kHz was also seen.

I1OMC_vibration_test_DCPD.pngI1OMC_vibration_test_QPD.png

CM1/CM2 (PZT mirrors)

- Baseically excitation was dominated by the PZT mode at 10kHz. Some spourious resonances are seen at 4~5kHz but I believe this is associated with the weight placed on the excitation PZT.

I1OMC_vibration_test_CM.png

FM1/FM2 and peripheral prism mirrors (BSs and SMs)

- The modes of the FMs are seen ~8k or 12kHz. I believe they are lowered by the weight for the measurement. In any case, the mode frequency is quite high compared to our frequency region of interest.

- As the prism resonance is quite high, the excitation is directly transmitted to the breadboard. Therefore the excitation of the non-cavity caused similar effect to the excitation on the breadboard.
  In fact what we can see from the plot is excitation of the 1.1kHz body mode and many high frequency resonances.

I1OMC_vibration_test_FM.pngI1OMC_vibration_test_Prism.png

Beam dumps

- This is also similar to the case of the peripheral mirrors.

I1OMC_vibration_test_BD.png

Attachment 1: I1OMC_vibration_test.pdf
I1OMC_vibration_test.pdf I1OMC_vibration_test.pdf I1OMC_vibration_test.pdf I1OMC_vibration_test.pdf I1OMC_vibration_test.pdf I1OMC_vibration_test.pdf I1OMC_vibration_test.pdf I1OMC_vibration_test.pdf
  213   Mon Jul 21 01:02:43 2014 KojiMechanicsCharacterizationSome structual mode analysis

Prisms

Fundamental: 12.3kHz Secondary: 16.9kHz

PRISM_12_3kHz.png PRISM_16_9kHz.png

DCPDs

Fundamental: 2.9kHz Secondary: 4.1kHz

DCPD_2_9kHz.png DCPD_4_1kHz.png

QPDs

Fundamental: 5.6kHz Secondary: 8.2kHz

QPD_6_0kHz.png QPD_8_2kHz.png

  218   Tue Sep 9 20:59:19 2014 KojiMechanicsCharacterizationStructural mode analysis for the PZT mirror

Structural analysis of the PZT mirror with COMSOL.

Inline figures: Eigenmodes which involves large motion of the tombstone. In deed 10kHz mode is not the resonance of the PZT-mirror joint, but the resonance of the tombstone.

Attached PDF: Simulated transfer function of the PZT actuation. In order to simulate the PZT motion, boundary loads on the two sides of the PZT were applied with opposite signs.
10kHz peak appears as the resonance of the tombstone dominates the mirror motion. At 12kHz, the PZT extension and the backaction of the tombstone cancells each other and
the net displacement of the mirror becomes zero.

PZT_10.0kHz.png PZT_14.6kHz.png PZT_18.0kHz.png

PZT_22.5kHz.png PZT_29.7kHz.png

Attachment 1: PZT_response_FEA.pdf
PZT_response_FEA.pdf
  296   Wed May 30 16:40:38 2018 KojiMechanicsCharacterizationEOM mount stability test

https://awiki.ligo-wa.caltech.edu/wiki/EOM_Mount_Stability

  314   Fri Feb 1 12:52:12 2019 KojiMechanicsGeneralPZT deformation simulation

A simple COMSOL simulation was run to see how the PZT deforms as the voltage applied.

Use the geometry of the ring PZT which is used in the OMCs -  NAC2124 (OD 15mm, ID 9mm, H 2mm)
The material is PZT-5H (https://bostonpiezooptics.com/ceramic-materials-pzt) which is predefined in COMSOL and somewhat similar to the one used in NAC2124 (NCE51F - http://www.noliac.com/products/materials/nce51f/)
The bottom surface of the ring was electrically grounded (0V), and mechanically fixed.
Applied 100V between the top and bottom.

 

Attachment 1: pzt.png
pzt.png
  320   Thu Mar 28 16:36:52 2019 KojiMechanicsCharacterizationOMC(002) PZT characterization

As performed in the ELOG 202, the PZTs of the OMC 002 were tested.

DC response was measured by sweeping each PZT with 0-150V triangular voltage at 11Hz. Acquire 0.2sec of the tie series using an oscilloscope to get the PDH error, cavity transmission, and the sweep signal.

The voltage where the tranmission peaks were observed were fitted were recorded. One fringe corresponds to the displacement of 532nm. So the displacement and the applied volatagewere fitted witha linear function.

This gave the PZT response for PZT1 and PZT2 to be 14.9nm/V and 14.4nm/V.

 

AC response was measured with SR785. The PZT was shaken with 1~50mVpp signal with the DC offset of 5V while the OMC was locked with the feedback to the laser fast PZT. The transfer function from the applied PZT voltage to the servo output were measured. The closed loop TF was also measured to remove the effect of the servo control.  The DC levels of the responses were calibrated using the values above.

Attachment 1: PZT_Scan.pdf
PZT_Scan.pdf
Attachment 2: OMC_PZT_Response.pdf
OMC_PZT_Response.pdf
  328   Thu Apr 11 12:15:31 2019 KojiMechanicsConfigurationPZT sub assy mirror orientations
Attachment 1: PZT_subassy.png
PZT_subassy.png
Attachment 2: PZT_subassy.pdf
PZT_subassy.pdf PZT_subassy.pdf PZT_subassy.pdf PZT_subassy.pdf
  329   Thu Apr 11 21:22:26 2019 KojiMechanicsGeneralOMC(004): PZT sub-assembly gluing

[Koji Stephen]

The four PZT sub-assemblies were glued in the gluing fixtures. There were two original gluing fixtures and two additional modified fixtures for the in-situ bonding at the repair of OMC(002).

- Firstly, we checked the fitting and arrangements of the components without glue. The component combinations are described in ELOG 329.
- Turned on the oven toaster for the cure test (200F).
- Then prepared EP30-2 mixture (7g EP30-2 + 0.35g glass sphere).
- The test specimen of EP30-2 was baked in the toaster oven. (The result shows perfect curing (no stickyness, no finger print, crisp fracture when bent)
- Applied the bond to the subassemblies.
- FInally the fixtures were put in airbake Oven A. We needed to raise one of the tray with four HSTS balance weights (Attachment 2).

Attachment 1: IMG_7561.jpg
IMG_7561.jpg
Attachment 2: IMG_7567.jpg
IMG_7567.jpg
  358   Thu May 9 16:07:18 2019 StephenMechanicsGeneralImprovements to OMC Bonding Fixture

[Stephen, Koji]

As mentioned in eLOG 331, either increased thermal cycling or apparent improvements in cured EP30-2 strength led to fracture of curved mirrors at unintended locations of bonding to the PEEK fixture parts.

The issue and intended resolution is summarized in the attached images (2 different visualizations of the same item).

Redline has been posted to D1600336-v3.

Drawing update will be processed shortly, and parts will be modified to D1600336-v4.

 

Attachment 1: image_of_issue_with_OMC_PZT_bonding_fixture_from_D16003336-v3.png
image_of_issue_with_OMC_PZT_bonding_fixture_from_D16003336-v3.png
Attachment 2: image_02_of_issue_with_OMC_PZT_bonding_fixture_from_D16003336-v3.PNG
image_02_of_issue_with_OMC_PZT_bonding_fixture_from_D16003336-v3.PNG
  400   Mon Nov 9 22:06:18 2020 KojiMechanicsGeneral5th OMC Transport Fixture

I helped to complete the 5th OMC Transport Fixture. It was built at the 40m clean room and brought to the OMC lab. The fixture hardware (~screws) were also brought there.

Attachment 1: IMG_0211.jpg
IMG_0211.jpg
Attachment 2: IMG_0221.jpg
IMG_0221.jpg
  478   Sat Jan 28 00:38:56 2023 KojiMechanicsGeneralOMC #1 cable bracket replacement / OMC #1 repair completed

The AL metal bracket was replaced with a PEEK version.

Attachments 1/2: Before the replacement. The photos show how the cables are arranged.

Attachment 3: How the replacement work is going. The 1/4-20 screws were super tight. Once the connectors were removed, an Allen key was inserted to a hole so that the 1/4-20 on the short sides were removed by closing Allen key arms. For the screws on the longer sides, the same technique can be applied by using three Allen keys. This time none of the screws/cable pegs were wasted. The clothes were used to protect the breadboard from any impact of the action.

Attachments 4/5: Final state.

OMC #1 repair has been 100% done

---------

We still have 4 correct cable pegs and many 1/4-20 BHSCs for OMC #4.

Attachment 1: PXL_20230128_011405446.jpg
PXL_20230128_011405446.jpg
Attachment 2: PXL_20230128_011401778.jpg
PXL_20230128_011401778.jpg
Attachment 3: PXL_20230128_013509885.jpg
PXL_20230128_013509885.jpg
Attachment 4: PXL_20230128_014001006.jpg
PXL_20230128_014001006.jpg
Attachment 5: PXL_20230128_014035044.jpg
PXL_20230128_014035044.jpg
  479   Sat Jan 28 00:46:21 2023 KojiMechanicsGeneralOMC #4: Replaced the locks of the transport fixture

Yesterday, we noticed that we could not close the transport fixture for OMC #4. We could not fully rotate the knobs of the locks. Today, I took the hooks from the functioning locks of the spare transport fixture.

It turned out that the default dimension of the lock seemed too tight. The functioning one has the through holes elongated by a file or something. This modification will be necessary for future transport fixtures.

Attachment 1: PXL_20230128_022952669.jpg
PXL_20230128_022952669.jpg
  480   Wed Feb 1 01:33:03 2023 KojiMechanicsGeneral5th OMC Transport Fixture

The transport fixture was brought to the 40m clean room to use as an assembly reference.

Attachment 1: PXL_20230201_005912224.jpg
PXL_20230201_005912224.jpg
  481   Wed Feb 1 01:39:41 2023 KojiMechanicsGeneralDCPD housing / QPD housing

Inserted 4-40 and 2-56 helicoils into the DCPD/QPD housings for the 4th OMC. The retainer caps were also fastened to the housings.

Attachment 1: PXL_20230201_021505299.jpg
PXL_20230201_021505299.jpg
Attachment 2: PXL_20230201_021455728.jpg
PXL_20230201_021455728.jpg
  1   Fri Jun 15 15:45:49 2012 KojiGeneralGeneralOMC Plan

LIGO Document G1200683-v1:
aLIGO OMC fabrication and testing plan

aLIGO OMC wiki

  2   Sat Jun 16 08:53:09 2012 KojiGeneralGeneralTo Do List

Facility

Mechanics

  • Work 
    •  
  • Design
    • How do we hold the PDs, QPDs, and black glass - we put 2 PDs and 2 QPDs on the PD mounting blacket.
    •  
  •  
  • Test
     
  • Things to be tested
    • New suspension scheme (cup & cone design)
    • Balancing the plates
    • Dummy metal payload?
  • => Suspending test with a suspension cage for a Faraday isolator@CIT
    • Supporting block for the suspension cage (to mimic the OMC suspension)
  • Things to be designed
    • Wire end (cone)
    • Diode holding structures
      PD/QPD/PZT holding structure
  • PZT alignment
  • Prototyping with metal parts?
  • UV glue? (heat) / gluing test
  • Balance / ballast
     
  • Solid works

Optics

  • Mirrors to be delivered ~Aug
  • Design down select
    • Between "Single output & BS" vs "Two outputs & no BS"
  • Mode design
  • Finalization of scattering paths / PD angles etc
     
  • Things to be decided / confirmed:
    • How to handle optics / assemblies (Talk to the prev people)
    • First contact? (Margot: applicable to a short Rc of ~2.5m)
    • Gluing templates to be designed (how to handle it?)
  • Things to be tested:
    • R&T of each mirror
    • Cavity ref/trans/finesse
    • PD QE / incident angle
       
  • What PD do we use?
     
  • CCD beam analyzer (Zach: It is fixed.)
     
  • PD angle measurement
  • Obtain EG&G 3mm PDs

Electronics

  • Electronics / CDS electronics / software
     
  • Things to be tested
    • QPD/PD pre-selections (QE/noise)
    • Functionality test of QPD/PD/PZT

Shipping, storage etc


Jun/July
    - Lab renovtion
    - Mechanics design
    - Glue training
Aug
    - Mirror delivery
    - Basic optics test
Sept
    - Cavity test
    - Suspending test
NOV~DEC
    - Shipping to LLO

Open questions
    Two optical designs
    Procedure
    Modeling
    Clamp design / stencil design
    gluing-installation procedure

  7   Sat Jul 14 02:16:07 2012 KojiGeneralGeneralPlan Update: July

Facility/Supplies

  • Work in progress
    • Floor cleaning
    • Plug slits on the roof of the HEPA booth - blanking panels have been ordered (Peter)
    • Install laser safety barrier (Peter is working on this)
    • Place a sticky mat
       
  • Work to be done
    • Replacing a file cabinet next to the south wall by a lockable cabinet
    • Replacing a lab desk at the west side of the room. (Vladimir's)
    • Replacing Vladimir's rack with nicer one.
    • Laser sign
    • Safety glass holder
    • Prepare clean supplies (Shoes/Coverall/Hats/Gloves) => go to VWR stock room
      • glove 8.5,9,9.5
         
    • Label maker (P-Touch) & Tape
        
  • Design
    • Optical layout - Laser SOP
    • Additional HEPA stage
       
  • Test
    • Confirm particle level
       
  • Note: Optical Table W96" x D48" x H27"

Beaurocracy

  • Laser SOP
  • HV use?
  • UV?

Mechanics

  • Ongoing Work 
    • Cone-shaped wire clamp design (at the OMC end) - Jeff
       
  • Design
    • Wire preparation fixture - Jeff
    • How do we hold the PDs, QPDs, and black glass - we put 2 PDs and 2 QPDs on the PD mounting blacket. - Jeff
    • Integrated solidwork model - Sam
      • Q: How the wires are clamped at the top side?
      • Q: How much the length of the wire should be?
      • Q: Locations of the wire mounts on the plate
    • Cabling investigation:
      • Where do the cables from the feed-thrus anchored? - Sam
      • List of the current internal cables and their lengths - Sam
      • List of the required internal cables and their lengths
      • Can we route the intermediate stage of the suspension? Do we need new cables?
    • Dummy intermediate stage structure
       
    • Metal templates
      • First, decide an optical design
      • takes at least a month
         
    • Weights how heavy / how many
       
  • Test
    • Cone-shaped wire clamp test - Jeff/Koji 
    • Balancing the plates
      • The Faraday isolator cage isn't clean
    • Dummy metal payload test at the sites???
       
  • Procedures to be decided
    • PZT alignment
    • Prototyping with metal parts?
    • UV glue? (heat) / gluing test
    • Balance

Optics

  • Ongoing Work 
    • Mirrors to be delivered ~Aug
       
    • Design down select - Between "Single output & BS" vs "Two outputs & no BS"
    • Down selecting procedure:
      1. Assume ELIGO beam component
      2. Assume amount of 9MHz / 45MHz sidebands at the OMC input
      3. Calculate transmitted power
      4. Require HOM to be smaller than the TEM00 offset 
         
    • UV cured epoxy (Quate obtained)
  • Design
    • Mode design for HAM6 layout
    • Finalization of scattering paths
       
  • Tests
    • Measurement of PD angles
    • R&T of each mirror
    • Curvature of the curved mirrors
    • Cavity ref/trans/finesse
    • PD Q.E. & Reflectivity measurement vs incident angle
       
  • Things to be decided / confirmed
    • How to handle optics / assemblies (Talk to the prev people)
    • First contact? (Margot: applicable to a short Rc of ~2.5m)
    • Gluing templates to be designed (how to handle it?)
       
  • PDs
  • Misc
    • CCD beam analyzer (Zach: It is fixed.)
    • Are two PZTs used?
      • YES, for redundancy, range, upconversion tests.
         
  • Things to buy
  • Need to buy a fiber for mode cleaning?
  • Mode content of the ELIGO dark beam?
  • Jitter noise?
  • How to determine the design?
  • Why Fused Silica? (How much is the temp fluctuation in the chamber?)
  • How to align the cavity mirrors, input mirrors, QPDs, PDs, beam dumps.
     

Electronics

  • Thorough scrutinization of cabling / wiring / electronics
  • Electronics / CDS electronics / software
  • Things to be tested
    • QPD/PD pre-selections (QE/noise)
    • Functionality test of QPD/PD/PZT

Shipping, storage etc


Jun/July
    - Lab renovtion
    - Mechanics design
    - Glue training
Aug
    - Mirror delivery
    - Basic optics test
Sept
    - Cavity test
    - Suspending test
NOV~DEC
    - Shipping to LLO

Open questions
    Two optical designs
    Procedure
    Modeling
    Clamp design / stencil design
    gluing-installation procedure

 


July:Facility/Supplies

Attachment 1: P7071878.jpg
P7071878.jpg
  11   Tue Jul 24 11:41:29 2012 KojiGeneralGeneralUseful references

Nicolas Smith,
LIGO Document T0900383-v1
3mm Photodiode Characterization for Enhanced LIGO
https://dcc.ligo.org/cgi-bin/private/DocDB/ShowDocument?docid=4498

Tobin Fricke,
LIGO Document P1000010-v1
Homodyne detection for laser-interferometric gravitational wave detectors
https://dcc.ligo.org/cgi-bin/private/DocDB/ShowDocument?docid=8443

Nicolas Smith,
LIGO Document P1200052-v1
Techniques for Improving the Readout Sensitivity of Gravitational Wave Antennae
https://dcc.ligo.org/cgi-bin/private/DocDB/ShowDocument?docid=90498

  12   Tue Jul 31 21:29:43 2012 KojiGeneralGeneralWork completed in July [!]

 

  13   Tue Jul 31 21:33:17 2012 KojiGeneralGeneralPlan Update: August [!]

Completed work of the previous months: [Jul] [Aug] [Sep] [Oct] [Nov] [Dec]


Facility/Supplies

  • Work done
  • Things ordered
    • Office Depot
      • [delivered] Office Depot(R) Brand Stretch Wrap Film, 20 x 1000 Roll, Clear / 445013
      • [delivered] Eveready(R) Gold AA Alkaline Batteries, Pack Of 24 / 158448
      • [delivered] Rubbermaid(R) Roller Sponge Mop / 921841
      • [delivered] Rubbermaid(R) Roller Sponge Mop Replacement / 921858
      • [delivered] Rubbermaid(R) Sanitizing Caddy, 10 Quarts, Yellow / 674125
      • [delivered] Glad(R) Tall Kitchen Trash Bags, 13 Gallon, White, Box Of 28 / 269268
    • Global Industrial Equipment
      • [delivered] Extended Surface Pleated Cartridge Filter Serva-Cell Mp4 Slmp295 12X24X2 Gl    WBB431699
    • Global Industrial Equipment
      • [delivered] Nexel Poly-Z-Brite Wire Shelving 30"W x 21"D x 63"H Nexel Poly-Z-Brite™ Wire Shelving Starter Unit WB189209
      • [delivered] Stem Casters Set of (4) 5" Polyurethane Wheel, 2 With Brakes 1200 lb. Capacity WB500592    
    • Rack Solutions
      • [delivered] Open Frame Server Racks
        1 x 20" Depth Kit (Ideal for Audio/Video or Networking Racks) P/N: 111-1779
        1 x 36U, Rack-111 Post Kit P/N: 111-1728
        1 x Caster Kit for Open Frame RACK-111 P/N: 111-1731
      • [delivered] 36U Side Panel Kit $199.99 P/N: 102-1775
    • Rack shelf
      • [delivered] 1 RMS 19 X 15 SINGLE SIDED NON-VENTED SHELF 70121637
    • Work bench, Stools
      • [not yet] 72"L X 30"W Production Bench - Phenolic Resin Square Edge-Blue Form attached WB237381LBL    
      • [not yet] 72"W Lower Shelf For Bench - 15"D- Blue Form attached WB606951    
      • [not yet] ESD-Safe Vinyl Clean Room Stool with Nylon Base with Drag Chain Blue Form attached WBB560852    
    • P Touch
      • [delivered] Brother PT-2030 Desktop Office Labeler Punch-out product 672828    
      • [delivered] Brother(R) TZe-241 Black-On-White Tape, 0.75 x 26.2 Punch-out product 239384    
      • [delivered] Brother(R) TZe-231 Black-On-White Tape, 0.5 x 26.2 Punch-out product 239400    
    • UV light guide
      • [delivered] Fiber Optic Single Light Guide 5mm OD X 3mm ID X 1M L Note: This light guide can be used with MKIII UV Cure unit. OLB1081
    • Gloves (7.5, 8.0)
      • [delivered] GLOVE ACCTCH NR-LTX SZ7.5 PK25 Punch-out product 79999-306
      • [delivered] GLOVE ACCTCH NR-LTX SZ8 PK25 Punch-out product 79999-308
    • Lab coat (L,XL), Sticky Mat, Shoe Covers (L, XL), Cap, Mask
      • [delivered] LAB XP WH EL WR.COLL. NP L30EA Punch-out product 82007-618
      • [delivered] LAB XPWH EL WR.COLL. NP XL30EA Punch-out product 82007-620    
      • [delivered] VWR MAT ADHESIVE 30L 18X36 BLU Punch-out product 21924-110 (This was too small)
      • [delivered] VWR SHOECVR NSKID AP 2XL 150PR Punch-out product 414004-651    
      • [delivered] VWR SHOECVR NSKID AP XL 150PR Punch-out product 414004-650    
      • [delivered] CAP BOUFFANT 24IN RAYON CS500 Punch-out product 10843-053    
      • [delivered] MASK VLTC TIES N/STRL PK50 Punch-out product 10869-020
    • VWR
      • [delivered] FACE SHIELD UVC-803 Supplier: UVP 33007-151
         
    • [Delivered] Laser safety glasses
  • Work in progress

    •  
  • Work to be done
    • Replacing a file cabinet next to the south wall by a lockable cabinet
    • Laser sign
    • Safety glass holder/rack/shelf
    • Prepare clean supplies ~ glove 8.5,9,9.5
    • Ion gun safety issues: https://dcc.ligo.org/cgi-bin/private/DocDB/ShowDocument?docid=88631
        
  • Design
    • Optical layout - Laser SOP
    • Additional HEPA stage
       
  • Test
    • Confirm particle level
       
  • Note: Optical Table W96" x D48" x H27"

Beaurocracy

  • Laser SOP
  • HV use?
  • UV?

Mechanics

  • Ongoing Work 
    • Cone-shaped wire clamp design (at the OMC end) - Jeff
       
  • Design
    • Wire preparation fixture - Jeff
    • How do we hold the PDs, QPDs, and black glass - we put 2 PDs and 2 QPDs on the PD mounting blacket. - Jeff
    • Integrated solidwork model - Derek
      • Q: How the wires are clamped at the top side?
      • Q: How much the length of the wire should be?
      • Q: Locations of the wire mounts on the plate
    • Cabling investigation:
      • Where do the cables from the feed-thrus anchored?
      • List of the current internal cables and their lengths
      • List of the required internal cables and their lengths
      • Can we route the intermediate stage of the suspension? Do we need new cables?
    • Dummy intermediate stage structure
       
    • Metal templates
      • First, decide an optical design
      • takes at least a month
         
    • Weights how heavy / how many
       
    • Earthquake stop design (Sam B)
       
  • Test
    • Cone-shaped wire clamp test - Jeff/Koji 
    • Balancing the plates
      • The Faraday isolator cage isn't clean
    • Dummy metal payload test at the sites???
       
  • Procedures to be decided
    • PZT alignment
    • Prototyping with metal parts?
    • UV glue? (heat) / gluing test
    • Balance

Optics

  • Things ordered
    • Newport LB servo
    • Halogen Lamp
    • N2 cylinder/lines/filter
  • Ongoing Work 
    • Mirrors to be delivered ~Aug
       
    • Design down select - Between "Single output & BS" vs "Two outputs & no BS"
    • Down selecting procedure:
      1. Assume ELIGO beam component
      2. Assume amount of 9MHz / 45MHz sidebands at the OMC input
      3. Calculate transmitted power
      4. Require HOM to be smaller than the TEM00 offset 
         
    • UV cured epoxy (Quate obtained)
  • Design
    • Mode design for HAM6 layout
    • Finalization of scattering paths
       
  • Tests
    • Measurement of PD angles
    • R&T of each mirror
    • Curvature of the curved mirrors
    • Cavity ref/trans/finesse
    • PD Q.E. & Reflectivity measurement vs incident angle
       
  • Things to be decided / confirmed
    • How to handle optics / assemblies (Talk to the prev people)
    • First contact? (Margot: applicable to a short Rc of ~2.5m)
    • Gluing templates to be designed (how to handle it?)
       
  • PDs
  • Misc
    • CCD beam analyzer (Zach: It is fixed.)
    • Are two PZTs used?
      • YES, for redundancy, range, upconversion tests.
         
  • Things to buy
  • Need to buy a fiber for mode cleaning?
  • Mode content of the ELIGO dark beam?
  • Jitter noise?
  • How to determine the design?
  • Why Fused Silica? (How much is the temp fluctuation in the chamber?)
  • How to align the cavity mirrors, input mirrors, QPDs, PDs, beam dumps.
  • PZTs @LLO
     

Electronics

  • Thorough scrutinization of cabling / wiring / electronics
    • ELIGO OMC Wiring diagram D070536-A2
      • Occupies 2 DB25s -> They were anchored on the sus cage
      • Preamps for DCPDs will be fixed on the ISI table
        -> DB25 for the DCPDs will be anchored on the table
      • Use longer thin cables for the DCPDs in order to route them through the suspension stages
      • Turn the heater cable to the one for the other PZT
  • Electronics / CDS electronics / software
  • Things to be tested
    • QPD/PD pre-selections (QE/noise)
    • PD preamp design (Rich)
    • Functionality test of QPD/PD/PZT

Shipping, storage etc


Jun/July
    - Lab renovation
Aug

    - Mechanics design
    - Mirror delivery
Sept

    - Basic optics test
    - Glue training
Oct
    - Cavity test
Nov

    - Suspending test
Dec
    - Shipping to LLO

Open questions
    Two optical designs
    Procedure
    Modeling
    Clamp design / stencil design
    gluing-installation procedure

  27   Tue Oct 16 14:50:54 2012 jamie, jeffGeneralGeneralOMC breadboard/plate measurement dimensions

We have measured the dimensions and mass of the OMC glass plates/breadboards:

S/N Mass (g) Length (mm) Width (mm) Height (mm) Notes
01 6146 449.66 149.85 41.42, 41.42  for LLO
02 6126 449.66 149.97 41.32, 41.32  for LHO
03 6143 449.76 149.98 41.39, 41.43  
04 6139 449.78 149.81 41.40, 41.40  for 3IFO
05 6132 449.76 150.03 41.27, 41.31 corner chip, front-bottom-left*
06 6138 449.84 149.71 41.42, 41.42  
  • * orientation is relative to "front" face, i.e. long-short face with S/N on it, with S/N upright.
  • Height measurements were made twice, once at each end.
  • TMeasurements of 03, 05, 02, and 06 were done in the open in the OMC lab.  This was not thought to be too much of an issue since the plates
    are already covered with particulate matter from the tissue paper that they were wrapped in. 
    Measurements of 04 and 01 were done on the optics table, under the clean room enclosure.

Note by Koji:

  • The scale of the bake lab was used. (Max 60kg, Min resolution of 1g)
  • The dimensions were measured by a huge caliper which Jeff brought from Downs.
  • S/N 01, 03, 04 look pretty similar. They should be the primary candidates.
  28   Tue Oct 16 15:50:09 2012 KojiGeneralGeneralWork completed in August/September [!]
  • Work done
  • Things ordered
    • Office Depot
      • [delivered] Office Depot(R) Brand Stretch Wrap Film, 20 x 1000 Roll, Clear / 445013
      • [delivered] Eveready(R) Gold AA Alkaline Batteries, Pack Of 24 / 158448
      • [delivered] Rubbermaid(R) Roller Sponge Mop / 921841
      • [delivered] Rubbermaid(R) Roller Sponge Mop Replacement / 921858
      • [delivered] Rubbermaid(R) Sanitizing Caddy, 10 Quarts, Yellow / 674125
      • [delivered] Glad(R) Tall Kitchen Trash Bags, 13 Gallon, White, Box Of 28 / 269268
    • Global Industrial Equipment
      • [delivered] Extended Surface Pleated Cartridge Filter Serva-Cell Mp4 Slmp295 12X24X2 Gl    WBB431699
    • Global Industrial Equipment
      • [delivered] Nexel Poly-Z-Brite Wire Shelving 30"W x 21"D x 63"H Nexel Poly-Z-Brite™ Wire Shelving Starter Unit WB189209
      • [delivered] Stem Casters Set of (4) 5" Polyurethane Wheel, 2 With Brakes 1200 lb. Capacity WB500592    
    • Rack Solutions
      • [delivered] Open Frame Server Racks
        1 x 20" Depth Kit (Ideal for Audio/Video or Networking Racks) P/N: 111-1779
        1 x 36U, Rack-111 Post Kit P/N: 111-1728
        1 x Caster Kit for Open Frame RACK-111 P/N: 111-1731
      • [delivered] 36U Side Panel Kit $199.99 P/N: 102-1775
    • Rack shelf
      • [delivered] 1 RMS 19 X 15 SINGLE SIDED NON-VENTED SHELF 70121637
    • Work bench, Stools
      • [not yet] 72"L X 30"W Production Bench - Phenolic Resin Square Edge-Blue Form attached WB237381LBL    
      • [not yet] 72"W Lower Shelf For Bench - 15"D- Blue Form attached WB606951    
      • [not yet] ESD-Safe Vinyl Clean Room Stool with Nylon Base with Drag Chain Blue Form attached WBB560852    
    • P Touch
      • [delivered] Brother PT-2030 Desktop Office Labeler Punch-out product 672828    
      • [delivered] Brother(R) TZe-241 Black-On-White Tape, 0.75 x 26.2 Punch-out product 239384    
      • [delivered] Brother(R) TZe-231 Black-On-White Tape, 0.5 x 26.2 Punch-out product 239400    
    • UV light guide
      • [delivered] Fiber Optic Single Light Guide 5mm OD X 3mm ID X 1M L Note: This light guide can be used with MKIII UV Cure unit. OLB1081
    • Gloves (7.5, 8.0)
      • [delivered] GLOVE ACCTCH NR-LTX SZ7.5 PK25 Punch-out product 79999-306
      • [delivered] GLOVE ACCTCH NR-LTX SZ8 PK25 Punch-out product 79999-308
    • Lab coat (L,XL), Sticky Mat, Shoe Covers (L, XL), Cap, Mask
      • [delivered] LAB XP WH EL WR.COLL. NP L30EA Punch-out product 82007-618
      • [delivered] LAB XPWH EL WR.COLL. NP XL30EA Punch-out product 82007-620    
      • [delivered] VWR MAT ADHESIVE 30L 18X36 BLU Punch-out product 21924-110 (This was too small)
      • [delivered] VWR SHOECVR NSKID AP 2XL 150PR Punch-out product 414004-651    
      • [delivered] VWR SHOECVR NSKID AP XL 150PR Punch-out product 414004-650    
      • [delivered] CAP BOUFFANT 24IN RAYON CS500 Punch-out product 10843-053    
      • [delivered] MASK VLTC TIES N/STRL PK50 Punch-out product 10869-020
    • VWR
      • [delivered] FACE SHIELD UVC-803 Supplier: UVP 33007-151
         
    • [Delivered] Laser safety glasses

 

  29   Tue Oct 16 15:51:01 2012 KojiGeneralGeneralPlan Update: October [!]

Completed work of the previous months: [Jul] [Aug] [Sep] [Oct] [Nov] [Dec]


Facility/Supplies

  • Work in progress
    • RoC measurement
    • R&T measurement
    • Wedge measurement
  • Work to be done
    • Replacing a file cabinet next to the south wall by a lockable cabinet
    • Additional clean supplies ~ glove 8.5,9,9.5
    • Stainless bats
    • Ion gun safety issues: https://dcc.ligo.org/cgi-bin/private/DocDB/ShowDocument?docid=88631
        
  • Design
    • Laser SOP
       
  • Test
    • Continuous monitoring of the particle level
       
  • Note: Optical Table W96" x D48" x H27"

Beaurocracy

  • Laser SOP / HV use? / UV?
  • Procedures to be decided
    • PZT alignment
    • UV glue? (heat) / gluing test
    • Balance
    • N2 cylinder/lines/filter
  • Design
    • Mode design for HAM6 layout
    • Finalization of scattering paths
       
  • Things to be decided / confirmed
    • How to handle optics / assemblies (Talk to the prev people)
    • First contact? (Margot: applicable to a short Rc of ~2.5m)
    • Gluing templates to be designed (how to handle it?)
       
  • PDs
  • Things to buy
  • Need to buy a fiber for mode cleaning?
  • Mode content of the ELIGO dark beam?
  • Jitter noise?
  • How to determine the design?
  • Why Fused Silica? (How much is the temp fluctuation in the chamber?)
  • How to align the cavity mirrors, input mirrors, QPDs, PDs, beam dumps.
  • PZTs @LLO
     

Electronics

  • Thorough scrutinization of cabling / wiring / electronics
    • ELIGO OMC Wiring diagram D070536-A2
      • Occupies 2 DB25s -> They were anchored on the sus cage
      • Preamps for DCPDs will be fixed on the ISI table
        -> DB25 for the DCPDs will be anchored on the table
      • Use longer thin cables for the DCPDs in order to route them through the suspension stages
      • Turn the heater cable to the one for the other PZT
  • Electronics / CDS electronics / software
  • Things to be tested
    • QPD/PD pre-selections (QE/noise)
    • PD preamp design (Rich)
    • Functionality test of QPD/PD/PZT

Shipping, storage etc

  33   Wed Nov 7 20:21:42 2012 KojiGeneralGeneralWork completed in October [!]

Completed work of the previous months: [Jul] [Aug] [Sep] [Oct] [Nov] [Dec]


 

  34   Wed Nov 7 20:44:11 2012 KojiGeneralGeneralPlan Update: November [!]

Completed work of the previous months: [Jul] [Aug] [Sep] [Oct] [Nov] [Dec]


  • Work done
    • Wedge measurement (1st trial) [ELOG]
    • RoC measurement [ELOG]
  • Work in progress
    • R&T measurement
    • Wedge measurement
  • Work to be done
    • QPD/PD pre-selections (QE/noise)
    •  
    •  
    •  
    • Misc. / Beaurocracy?
      • Continuous monitoring of the particle level
      • Replacing a file cabinet next to the south wall by a lockable cabinet
      • Ion gun safety issues: https://dcc.ligo.org/cgi-bin/private/DocDB/ShowDocument?docid=88631
      • Laser SOP / HV use? / UV?
  • Things delivered
  • Things ordered
    • Power strips Tripp Lite PS3612 (Ordered Nov. 8, Delivered Nov. 12)
    • Kapton tapes (1in x 6, 1/2in x 12 Delivered Nov. 15)
    • Sticky Mats (VWR 18888-216 Delivered Nov. 12 and 21992-042)
    • Duck tape (PK3) (Delivered Nov. 12)
    • Wipers 12"x12" 2ply x 119 pairs x case15 (Delivered Nov. 12)
    • Syringes (1mL&2mL) & Needles (20G x dozen)
    • Stainless trays with cover (Steve Delivered Nov. 12)
    • Gold Plated allen keys (Steve Delivered Nov. 12)
    • Forceps (Delivered Nov. 12) / Tweezers / Scissors (Delivered Nov. 12)
  • Things to buy / get
    • OMC testing optics / opto-mechanics
    • Black Glass / Black Glass holder / AR ==> Some at the 40m, some from LLO
    • Ionized air blow
      • N2 or Air cylinder: 4N - UHP or 5N - Research Grade.  (... steal from Downs)
    • Clean tools, tray, storage
    • Supply
      • Additional clean supplies ~ glove 8.5,9,9.5
      • Stainless bats / Pure solvents (Metha / Aceton / Iso) / Syringes / Lint free cloth / Paper lens tissue
      • Lab coats
    • ATF
      • Tefron tape
      • Thorlabs 8-32 screw kit / Thorlabs HW-KIT1
      • Pedestal Shims - Newport
  • Things to be done
    • Cavity ref/trans/finesse
    • PD Q.E. & Reflectivity measurement vs incident angle
    • Functionality test of QPD/PD (PeterK) /PZT
       
  • Procedures to be decided
    • PZT alignment
    • UV glue? (heat) / gluing test
    • Balance
    • N2 cylinder/lines/filter
    • Shipping procedure: New shipping cage design on going (Jeff) => Plastic box similar to COC
  • Design
    • Solidworks raytracing model
    • Mode design for HAM6 layout
       
  • Things to be decided / confirmed
    • How to handle optics / assemblies (Talk to the prev people)
    • First contact? (Margot: applicable to a short Rc of ~2.5m)
    • Gluing templates to be designed (how to handle it?)
  • Jitter noise?
  • How to align the cavity mirrors, input mirrors, QPDs, PDs, beam dumps.

Electronics ==> Rich

Attachment 1: OMC_Project_Schedule.pdf
OMC_Project_Schedule.pdf
  47   Mon Dec 31 01:45:04 2012 KojiGeneralGeneralWork completed in Nov and Dec [!]

Completed work of the previous months: [Jul] [Aug] [Sep] [Oct] [Nov] [Dec]


  • Work done
  • Things delivered
    • The ionized gun used in the clean room at Downs: made by Terra Universal.com (Jeff's room)
      http://www.terrauniversal.com/static-control/ionizing-blow-off-guns.php
    • Flow path: N2 cylinder - Filter - Gun (Jeff's room)
    • Power strips Tripp Lite PS3612 (Ordered Nov. 8, Delivered Nov. 12)
    • Kapton tapes (1in x 6, 1/2in x 12 Delivered Nov. 15)
    • Sticky Mats (VWR 18888-216 Delivered Nov. 12 and 21992-042)
    • Duck tape (PK3) (Delivered Nov. 12)
    • Wipers 12"x12" 2ply x 119 pairs x case15 (Delivered Nov. 12)
    • Syringes (1mL&2mL) & Needles (20G x dozen)
    • Stainless trays with cover (Steve Delivered Nov. 12)
    • Gold Plated allen keys (Steve Delivered Nov. 12)
    • Forceps (Delivered Nov. 12) / Tweezers / Scissors (Delivered Nov. 12)
    • OMC testing optics / opto-mechanics
    • SolidWorks raytracing model
    • Mode design for HAM6 layout [Zach]
       
    • Black Glass / Black Glass holder / AR ==> Some at the 40m, some from LLO
    • Ionized air blow
      • N2 or Air cylinder: 4N - UHP or 5N - Research Grade.  (... steal from Downs)
  61   Thu Feb 7 21:35:46 2013 KojiGeneralGeneralDmass's loan of LB1005 / A2&C2 sent to Fullerton / First Contact @40m

Dmass borrowed the LB1005 servo amp from the OMC lab.
It happened this week although it seems still January in his head.
Got it back on Mar 24th

The A2 and C2 mirrors have been sent to Josh Smith at Fullerton for the scatterometer measurement.

First Contact kit (incl. Peek Sheets)
Manasa borrowed the kit on Feb 7.
Got it back to the lab.

Attachment 1: P2053119.jpg
P2053119.jpg
Attachment 2: P2053120.JPG
P2053120.JPG
  71   Thu Mar 14 22:18:23 2013 KojiGeneralGeneralNew loans for the diode test

ALL returned

Loan from ATF:

2 blue banana cables returned on Jun 4, 2013

BNC cable returned on Mar 21, 2013