40m QIL Cryo_Lab CTN SUS_Lab CAML OMC_Lab CRIME_Lab FEA ENG_Labs OptContFac Mariner WBEEShop
  OMC elog, Page 6 of 8  Not logged in ELOG logo
Entry  Fri Aug 16 17:21:38 2013, Koji, General, General, [OMC002] Build started 
[Jeff Koji]

The breadboard (SN2) was loaded on the transportation fixture.

The laser side template was installed and the cavity mirrors were placed.
Entry  Fri Aug 16 16:36:19 2013, Koji, Optics, General, Optics List 
Link to the "Mirror/PZT Characterization links"

Breadboard

BB1 OMC(001) OMC
Entry  Tue Apr 16 09:43:58 2013, Koji, Optics, Configuration, Mirror list for L1OMC OMC_breadboard_mirror_config.png
L1 OMC
Cavity Mirrors
FM1 (input coupler): A8
    Reply  Fri Aug 16 15:31:17 2013, Koji, Optics, Configuration, Mirror list for OMC(002) 
OMC(002)

Cavity Mirrors

FM1 (input coupler): A9
Entry  Fri Aug 9 10:09:56 2013, Koji, General, General, PZT Assembly #3/#4 PZT_assembly.pdf
Yesterday, Jeff and I bonded the PZT assemblies (#3/#4).
The attached is the arrangement of the components
    Reply  Mon Aug 12 20:22:19 2013, Koji, General, General, PZT Assembly #5/#6 
PZT Assembly #5/#6 were glued on Fri Aug 9th
They are removed from the fixture on Mon Aug 12th.
All of the four PZT assemblies were moved to the OMC lab.
Entry  Sat Jul 6 17:10:07 2013, Koji, Mechanics, Characterization, PZT Response analysis PZT_Scan.pdfL1OMC_PZT_Response.pdf
Analysis of the PZT scan / TF data taken on May 31st and Jun 1st.
[DC scan]
Each PZT was shaken with 10Vpp 1Hz triangular voltage to the thorlabs amp.
Entry  Fri Jun 28 12:20:49 2013, Koji, General, General, Dmass's loan of Thorlabs HV amp 
http://nodus.ligo.caltech.edu:8080/Cryo_Lab/799
(KA: Returned upon H1OMC building)
Entry  Tue Jun 18 15:45:38 2013, Koji, General, General, [LLO] OMC installation in HAM6 
OMC installed in HAM6!
https://alog.ligo-la.caltech.edu/aLOG/index.php?callRep=7486
   
Entry  Tue Jun 18 10:01:11 2013, Koji, Optics, Characterization, Cavity Finesse analysis finesse_measurements.pdf
This is the analysis of the cavity finesse data taken on  Apr/13/2013 (before baking), May/30/2013 (after baking), and Jun/02/2013 (after cleaning).
If we believe this result, baking contaminated the cavity, and the first contact removed it. That agrees with the power measurement of the transmitted
light.
Entry  Fri Jun 14 06:35:21 2013, Jeff, General, General, [LLO] L1 OMC status preamp_arrangement.png
https://alog.ligo-la.caltech.edu/aLOG/index.php?callRep=7410
Weights:
Suspension cage and transportation box: 250.8lb
Entry  Thu Jun 13 12:12:20 2013, Zach, General, General, [LLO] OMC and OMCS in LVEA 
https://alog.ligo-la.caltech.edu/aLOG/index.php?callRep=7395
Entry  Thu Jun 13 12:04:57 2013, Koji, General, General, [LLO] OMC Optical Test - completed 
https://alog.ligo-la.caltech.edu/aLOG/index.php?callRep=7373
Entry  Mon Jun 10 10:04:37 2013, Koji, General, General, [LLO] OMC Test OMC_pow_cal.pdfresponsivity.pdfOMC_pow_cal_compensated.pdf
[Koji Zach]
We worked on the OMC test over the weekend.
- At the beginning, the measured OMC transmission was ~85% even after subtracting the junk light and sidebands from the calculation.
Entry  Fri Jun 7 16:04:44 2013, Koji, General, General, [LLO] OMC arrived 
[Koji Zach Suresh]
The OMC arrived at LLO without any destruction!

    We found that one shock sensor on the box turned red, the other stayed white.
    We brought the Perican case to the changing
Entry  Wed Jun 5 18:51:31 2013, Koji, General, General, L1 OMC shipped out CAM00011.jpgP6054027.JPG
[Koji, Jeff]
The L1 OMC finally sent out from Caltech!
Entry  Wed Jun 5 18:19:51 2013, Koji, General, General, Some recent photos from the OMC final test at CIT 
Applying First Contact for the optics cleaning
Entry  Wed Jun 5 01:06:35 2013, Zach, General, Characterization, L1 OMC as-built diagram L1OMC_asbuilt.pdf
 D1300507
 
Entry  Mon Jun 3 21:19:03 2013, Koji, General, General, Planning 
Monday - Evening
(Koji)
[done] - DCPD alignment
Entry  Mon Jun 3 18:58:08 2013, Koji, Optics, Configuration, OMC final tests 
- QPD mount aligned, QPD output checked
  The spots are with 100um from the center of the diodes. [ELOG Entry (2nd photo)]
Entry  Fri May 31 14:07:54 2013, Koji, Optics, Characterization, Transverse Mode Spacing measurement afte the baking  Cav_scan_response_130530_Pitch.pdfCav_scan_response_130530_Yaw.pdf
Measurement for pitch
Free Spectral Range (FSR): 264.9703 +/− 0.0007 MHz
Cavity roundtrip length: 1.131419 +/− 0.000003 m
Entry  Thu May 30 15:00:28 2013, Koji, Optics, General, QPD alignment 
The QPD alignment was adjusted using the aligned beam to the cavity and the 4ch transimpedance amplifier.
As I have a test cable for the QPD, I attached a DB9 connector on it so that I can use the QPD transimpedance
amplifier to read the photocurrent. The transimpedance of the circuit is 1kV/A. 
    Reply  Fri May 31 05:46:54 2013, Koji, Optics, General, QPD alignment QPD1.JPGQPD2.JPGQPD_calib.nb.zip
Peter F suggested to check the bottom surface of the PD housings if there is any protrusion/interference/whatever.
And that was true! It was found that the front side of QPD1 (Left) was lifted by a machining burr.
It seems that this burr consistently exists as the other one also have it (see QPD2 picture (right)) although it is not too terrible compared to
Entry  Thu May 30 14:38:42 2013, Koji, Electronics, General, Cable fitting  
Yesterday Jeff and Chub worked on the cabling of the OMC. It turned out that the gender of the cable connectors 
going from the cavity side to  the connector bracket on top of the OMC were opposite from what is  needed.  
This way, the connectors can't fixed on the cable harness, thus they are free during the shipping.
Entry  Thu May 23 23:41:48 2013, Koji, Mechanics, General, DCPD/QPD Mount 
DCPD mounts and QPD mounts were attached on the breadboard. They are not aligned yet and loosely fastened.
DCPD (mounting 4-40x5/16 BHCS Qty4)
Entry  Wed May 8 15:36:50 2013, Koji, General, General, Latest OMC schedule 

May
(done) Mon  6th: Invar plate arrival / Spot position measurement
(done) Tue  7th: Invar plate cleaning / Spot position measurement
/ EP30-2 arrival / Invar plate gluing to the test mounting brackets
(done) Wed  8th: Invar plate cleaning done / Baking of the test pieces (with Bob's
oven)
Thu  9th: ***After bake torque/force test***

***If the invar plate passes the test***
Thu  9th Light side invar plate gluing
Fri 10th Cable
    Reply  Mon May 13 15:00:23 2013, Koji, General, General, Current most reliable OMC schedule 
May
Tue 14th The OMC given to Bob (Air bake & Vac bake)

Mon 20th The OMC received from Bob
         Apply First contact
 
       Diode mount adjustment / Electronic tests
Tue 21st Diode mount adjustment / Electronic tests / Optical tests
Wed 22nd Final cabling (***Chub***)
Thu
23rd Final cabling / Packing
Fri 24th Packing / Shipping

Mon 27th? Arrival to LLO / Koji fly to LLO
Tue 28th Test on the optical bench
Wed 29th Test
       Reply  Tue May 21 18:28:08 2013, Koji, General, General, Current most reliable OMC schedule 
- The wrong Mighty Mouse connectors for the PZT wires were prepared. The correct ones are in the vacuum oven till Tuesday morning.
- The thread holes for the cable pegs are 1/4-20 rather than 10-24.  This requires re-machining of the cable pegs & the C&B.
- We are waiting for the fast shipment of the from LHO
Entry  Mon May 20 14:59:21 2013, Koji, General, General, OMC is out from the oven 
The OMC came back to the table again.
No obvious change is visible: no crack, no delamination
The OMC was fixed on the table and the beam was aligned to the cavity
Entry  Tue May 14 19:06:00 2013, Koji, Clean, General, OMC Baking 
The OMC is in the air bake oven now.
Entry  Mon May 13 14:59:16 2013, Koji, Mechanics, General, Invar shim gluing 
The invar reinforcement shims were glued on the glass brackets on the breadboard. 
We worked on the light side on May 10th and did on the dark side on May 13rd.
U-shaped holding pieces are used to prevent each invar shim to be slipped from the right place. 
Entry  Mon May 13 14:49:35 2013, Koji, Mechanics, Characterization, Mounting Glass Bracket still broke with tightenin stress 
[Koji / Jeff]
This is the elog about the work on May 9th.
We made two glass brackets glue on the junk 2" mirrors with the UV glue a while ago when we used the UV bonding last time.
Entry  Fri May 10 09:33:22 2013, Koji, Supply, General, COMSOL simulation on the glass bracket stress COMSOL1.png
 
Entry  Mon May 6 19:31:51 2013, Koji, Optics, Characterization, Spot position measurement on the diode mounts DCPD1.pngDCPD2.pngQPD1.pngQPD2.png
Measurement Order: DCPD2->DCPD1->QPD1->QPD2
DCPD1: 1.50mm+0.085mm => Beam 0.027mm too low
DCPD2: 1.75mm+0.085mm => Beam 0.051mm too high (...less confident)
    Reply  Wed May 8 15:08:57 2013, Koji, Optics, Characterization, Spot position measurement on the diode mounts DCPD1.pngDCPD2.pngQPD1.pngQPD2.png
Remeasured the spot positions:
DCPD1: 1.50mm+0.085mm => Beam 0.084mm too high
DCPD2: 1.50mm+0.085mm => Beam 0.023mm too high
Entry  Fri May 3 21:09:08 2013, Koji, General, General, OMC is back 
L1 OMC is back on the table for the action next week.
Entry  Thu Apr 18 11:59:02 2013, Koji, General, General, DCPD path gluing 
[Jeff, Koji]
DCPD path gluing
Usual preparation
Entry  Thu Apr 18 11:43:59 2013, Koji, General, General, Mounting Glass Bracket Failure 
[Jeff, Koji]
- While we were working on the optics alignment, one of the mounting brackets made of glass god tore apart into two when a holding screw was removed.
The glass component had a crack at the very middle of the part.
Entry  Wed Apr 17 07:30:04 2013, Koji, Optics, General, QPD path glued 
Yesterday, all of the glass components for the QPD path were glued.

- Check the alignment of the beam with the cavity.
Entry  Thu Apr 4 01:43:06 2013, Koji, Optics, Characterization, Mirror T measurement 
[Zach, Koji]
The measurement setup for the transmission measurement has been made at the output of the fiber.
- First, we looked at the fiber output with a PBS. It wasn't P-pol so we rotated the ourput coupler.
    Reply  Mon Apr 8 11:11:37 2013, Koji, Optics, Characterization, More Mirror T measurement 
More Ts of the mirrors were measured.
A mirror specification:
Request: 8300+/-800 ppm
       Reply  Tue Apr 16 08:12:14 2013, Koji, Optics, Characterization, Further More Mirror T measurement 
T&Rs of the B mirrors and some of the E mirrors are measured.
I found that these BSs have high loss (1%~3%) . As this loss will impact the performance of
the squeezer
          Reply  Tue Apr 16 23:26:51 2013, Koji, Optics, Characterization, Further More Mirror T measurement 
Since the previous measurement showed too high loss, the optical setup was checked.
It seemed that a PBS right before the T&R measurement setup was creating a lot of scattering (halo) visible with a sensor card.
This PBS was placed to confirm the output polarization from the fiber, so it was ok to remove it.
Entry  Tue Apr 16 00:40:45 2013, Koji, Optics, General, PD/QPD path gluing ~ preparation 
[Jeff Koji]
- Placed the optics on the PD/QPD path
- Checked the alignment of the beam on the dummy PD/QPD mounts
Entry  Sat Apr 13 21:06:02 2013, Koji, Optics, General, OMC Bottom-side: cavity glued Cav_scan_response_130412_Pitch.pdfCav_scan_response_130412_Yaw.pdf
[Jeff, Zach, Lisa, Koji]
Gluing of the cavity mirrors went very well!!!
Preparation
Entry  Fri Apr 12 09:25:31 2013, Koji, Optics, Characterization, Alignment of the OMC (without glue) 
[Zach Koji]
The first attempt not to touch the curved mirrors did not work. (Not surprising)
The eigenmode is not found on the mirror surface.
Entry  Thu Apr 11 15:10:22 2013, Koji, General, General, OMC Progress 
[Zach, Jeff, Koji]

- Jeff configured the bottom side template to have a nominal value
obtained from the solid works model. Note that the thickness of the
Entry  Wed Apr 10 00:40:30 2013, Zach, Optics, Configuration, fauxMC locked fauxMC_labeled.jpg
[Koji, Zach]
Tonight, we locked the "fauxMC". We obtained
a visibility of >99%.
Entry  Mon Apr 8 21:11:14 2013, Koji, Optics, General, PZT assembly gluing 
[Jeff, Zach, Koji] 
PZT assembly gluing
Glue gun -> to be returned to MIT
    Reply  Tue Apr 9 13:56:09 2013, Koji, Optics, General, PZT assembly post gluing / pre baking pictures 
 
Entry  Mon Apr 8 23:42:33 2013, Koji, Optics, Configuration, Fake OMC roughly aligned beam_profile.pdfmode_matching.pdf
Mode matching:
 
Entry  Mon Apr 8 20:56:52 2013, Koji, Optics, Configuration, PZT & Curverd Mirror arrangement PZT_assembly.pdf
Assembly #1:
Mounting Prism #16
PZT #26
Entry  Mon Apr 8 11:49:18 2013, Koji, Mechanics, Characterization, PZT actuator tested at LLO 
Test result of the PZTs by Valera and Ryan
PZT  Length Angle
 #   [nm/V] [urad/um]
 11  14.5   17.6
 12  13.8   17.8
 13  11.2   25.0
 14  14.5    6.6
 15  12.5   10.6


21  14.5    9.7
 22  13.8   28.8
 23  14.5    6.8  ==> Assembly #2
 24  18.5   51.7  ==> Used for prototyping
 25  17.1   13.8
Entry  Mon Apr 8 11:29:08 2013, Koji, Optics, Characterization, Mirror/PZT Characterization links 

    Mirror List
    http://nodus.ligo.caltech.edu:8080/OMC_Lab/152
     
    Mirror T measurement:
Entry  Thu Mar 28 03:37:07 2013, Zach, Optics, Configuration, Test setup input optics progress OMC_test_setup_IO.jpg2013-03-27_05.48.20.jpg2013-03-28_02.29.36.jpg
[Lisa, Zach]
Last night (Tuesday), I finished setting up and aligning most of the input optics for the OMC characterization setup. See the diagram below, but
the setup consists of:
    Reply  Fri Mar 29 08:55:00 2013, Zach, Optics, Configuration, Beam launched into fiber 


    
        
            Quote:
        
        
            

           Lisa and I concurred that it felt like we had converged to the optimum alignment and polarization, which would mean that the lack of
       Reply  Thu Apr 4 23:44:52 2013, Koji, Optics, Configuration, Beam launched into fiber 
We had to move our flipper mirror to share the beam between Peter's setup and ours as our flipper is at the place where the ISS PD array base is supposed
to be!
There was no place to insert the flipper in the setup. We (Peter and Koji) decided to move the laser back for ~2".
          Reply  Fri Apr 5 18:18:36 2013, Zach, Optics, Configuration, AOM probably broken Isomet_1250C_zin_4_5_13.png


    
        
            Quote:
        
        
            

           Then, I started to check the AOM path. I noticed that the 1st (or -1st) order beam is very weak. 
Entry  Wed Apr 3 17:39:38 2013, Koji, Mechanics, Characterization, Calibration of the test PZTs before the glue test P4033491.JPGshadow_sensor_calib.pdf
We want to make sure the responses of the PZT actuator does not change after the EP30-2 gluing.
A shadow sensor set up was quickly set-up at the fiber output. It turned out the ring PZTs are something really not-so-straightforward. 
If the PZT was free or just was loosely attached on a plane by double-sided tape, the actuation response was quite low (30% of the spec). 
    Reply  Fri Apr 5 14:39:26 2013, Koji, Mechanics, Characterization, Calibration of the test PZTs after the heat cure shadow_sensor_calib_after_bake.pdfPZTresponse.pdf
We attached fused silica windows on the test PZTs. http://nodus.ligo.caltech.edu:8080/OMC_Lab/93
The glued assemblies were brought to Bob's bake lab for the heat cure. There they are exposed to 94degC heat for two hours (excluding ramp up/down
time).
Entry  Thu Apr 4 01:35:04 2013, Koji, Optics, Characterization, Mode matching to the OMC cavity 
The fiber output was matched with the lenses on a small bread board.
The detailed configuration is found in the following elog link.
http://nodus.ligo.caltech.edu:8080/OMC_Lab/105
Entry  Thu Apr 4 00:35:42 2013, Zach, Optics, Configuration, MMT installed on breadboard, periscope built 2013-04-03_23.43.00.jpg
[Koji, Zach]
We installed the MMT that matches the fiber output to the
OMC on a 6"x12" breadboard. We did this so that we can switch from the "fauxMC" (OMC mirrors arranged with standard
Entry  Wed Apr 3 18:42:45 2013, Koji, Optics, General, EP30-2 gluing test 
EP30-2 gluing test
Entry  Mon Apr 1 18:17:01 2013, Koji, Optics, General, Mirror curvature center test 6x
Locations of the curvature minimum on the OMC curved mirrors have been measured. 

Motivation:

When a curved mirror is misaligned, the location of the curvature center is moved.
ELOG V3.1.3-