12
|
Tue Jul 31 21:29:43 2012 |
Koji | General | General | Work completed in July [!] |
Completed Work: Facility/Supplies
|
|
13
|
Tue Jul 31 21:33:17 2012 |
Koji | General | General | Plan Update: August [!] | Completed work of the previous months:
[Jul]
[Aug] [Sep] [Oct] [Nov] [Dec] |
|
14
|
Wed Aug 1 19:35:00 2012 |
Koji | Facility | General | Floor cleaned / Workbench being built / Table top defect | -
The floor of the room was cleaned and waxed!
- |
  |
15
|
Sat Aug 11 00:59:14 2012 |
Koji | Facility | General | Laser Safety Barrier | It seemed that a laser safety barrier was
installed today!?
|
|
16
|
Mon Aug 13 16:59:11 2012 |
Koji | Clean | General | Room Cleaning Log | Floor wiped with a wet wiper (Aug 13, 2012)
Floor wiped with a wet wiper (Aug
15, 2012) |
|
17
|
Mon Aug 13 17:01:35 2012 |
Koji | Clean | General | Particle Counts | Aug 13, 2012 / 0.5um 1000~2000/(0.1 cu
ft) / 0.7um 400-600/(0.1 cu ft)
by ATF particle counter (MET ONE 227A) |
|
18
|
Tue Aug 14 03:29:06 2012 |
Koji | Supply | General | Clean supply rack | Clean supplies & some cleaning tools
are located at the right side of the entrance.
The file cabinet there was moved to |
 |
19
|
Wed Aug 22 20:16:43 2012 |
Koji | Facility | General | Workbenches have been installed / Clean room stools | Last Friday, new workbenches were installed.
Vladimir got a new table and a cleanroom
stool. |
 |
20
|
Tue Sep 25 14:18:14 2012 |
Koji | Clean | General | Particle Counts | Particle counts
Before the prefilter is installed:
0.5um 1191cnts, 0.7um 346cnts |
|
21
|
Mon Oct 1 16:06:55 2012 |
Koji | Clean | General | Particle Counts | 1. It turned out that the particle
counter MET ONE 227A at ATF shows
(particle count)/(0.1 ft^3) |
|
22
|
Fri Oct 5 03:39:58 2012 |
Koji | Optics | General | RoC Test setup | Based on Zach's experiment design, I wrote
up a bit more detailed optical layout for
the mirror test. |
 |
23
|
Mon Oct 8 11:30:47 2012 |
Koji | Optics | General | EG&G 2mm photodiode angle response | EGE&G 2mm photodiode angle response
measured by Sam T1100564-v1 |
|
24
|
Tue Oct 9 04:59:24 2012 |
Koji | Optics | General | OMC Test Optical Setup | |
 |
25
|
Tue Oct 9 05:03:15 2012 |
Koji | Electronics | General | OMC Test Electronics Setup | |
 |
26
|
Fri Oct 12 17:15:19 2012 |
Koji | Optics | General | Loan from the 40m / ATF |
HWP set
|
|
27
|
Tue Oct 16 14:50:54 2012 |
jamie, jeff | General | General | OMC breadboard/plate measurement dimensions | We have measured the dimensions and mass
of the OMC glass plates/breadboards:
|
|
28
|
Tue Oct 16 15:50:09 2012 |
Koji | General | General | Work completed in August/September [!] |
Work done
|
|
29
|
Tue Oct 16 15:51:01 2012 |
Koji | General | General | Plan Update: October [!] | Completed work of the previous months:
[Jul]
[Aug] |
|
30
|
Wed Oct 17 20:36:04 2012 |
Koji | Optics | General | RoC test cavity locked | The RoC test setup has been built on
the optical table at ATF.
|
  |
33
|
Wed Nov 7 20:21:42 2012 |
Koji | General | General | Work completed in October [!] | Completed work of the previous months:
[Jul]
[Aug] |
|
34
|
Wed Nov 7 20:44:11 2012 |
Koji | General | General | Plan Update: November [!] | Completed work of the previous months:
[Jul]
[Aug] |
|
37
|
Thu Nov 8 19:52:57 2012 |
Koji | Optics | General | How to apply UV epoxy | KA's question:
Do |
|
43
|
Thu Nov 29 21:18:23 2012 |
Koji | Optics | General | OMC Mounting Prisms have come | |
 |
45
|
Wed Dec 19 18:47:03 2012 |
Koji | Clean | General | First Contact Training with Margot | Steve and I visited Margot to have a training
session for application of First Contact
on optics. |
|
46
|
Wed Dec 26 14:33:33 2012 |
Koji | Facility | General | Lase Interlock wired | Two switches are connected in series. |
  |
47
|
Mon Dec 31 01:45:04 2012 |
Koji | General | General | Work completed in Nov and Dec [!] | Completed work of the previous months:
[Jul]
[Aug] |
|
48
|
Mon Dec 31 03:10:09 2012 |
Koji | Optics | General | SolidWorks model of the OMC breadboard | |
 |
52
|
Sun Jan 6 23:22:21 2013 |
Koji | Mechanics | General | SolidWorks model of the OMC suspension | |
 |
57
|
Tue Jan 22 11:10:25 2013 |
Koji | Facility | General | Eyeware storage and hooks for the face shields are installed | A carpenter has come to install the eyeware
storage and hooks for the face shields. |
|
58
|
Tue Jan 22 17:56:32 2013 |
Koji | Mechanics | General | Rotary stage selection | Newport UTR80
Sensitivity: 4 arcsec
|
|
61
|
Thu Feb 7 21:35:46 2013 |
Koji | General | General | Dmass's loan of LB1005 / A2&C2 sent to Fullerton / First Contact @40m | Dmass
borrowed the LB1005 servo amp from the OMC
lab. |
 |
69
|
Thu Mar 7 15:53:47 2013 |
Koji | Mechanics | General | OMC Transportation fixture, OMC PD/QPD mounts | |
    |
70
|
Thu Mar 14 17:06:21 2013 |
Koji | Mechanics | General | OMC SUS work @LLO | EDIT (ZK): All photos on
Picasa. Also, I discovered that |
 |
71
|
Thu Mar 14 22:18:23 2013 |
Koji | General | General | New loans for the diode test | ALL
returned
Loan
from ATF: |
|
75
|
Sat Mar 23 02:32:23 2013 |
Koji | Facility | General | N2 cylinder delivered | Preparation for ionized N2 blow
- 99.9998% N2 cylinder delivered
(ALPHAGAZ 2 grade by AIR LIQUIDE) ALPHAGAZ |
|
76
|
Sat Mar 23 02:41:00 2013 |
Koji | Optics | General | Black glass beam dumps for the first OMC | Received black glass beam dumps from
MIT
- gluing by EP30-2 looks pretty fine. |
  |
77
|
Sat Mar 23 13:34:14 2013 |
Koji | Optics | General | PZT assembly prototype glued |
Prototype
PZT assembly |
   |
79
|
Mon Mar 25 02:04:05 2013 |
Koji | General | General | OMC building plan / procedure ~ WB18 | WB 18 March
Diode test
Dark current |
|
80
|
Mon Mar 25 18:34:25 2013 |
Koji | General | General | OMC building plan / procedure ~ Mar 25 Mon | 25 March (Mon):
Inspect the test PZT assembly
=> Give it to Bob. |
|
81
|
Mon Mar 25 19:31:16 2013 |
Koji | Optics | General | OMC Top-side gluing | [Koji Jeff Zach]
AAA
|
   |
82
|
Tue Mar 26 22:33:07 2013 |
Koji | General | General | Loan for the OMC building | Loan from PSL Lab
- 300mm mirror with Ultima mount
and pedestal |
|
83
|
Wed Mar 27 20:54:45 2013 |
Koji | General | General | OMC building plan / procedure ~ Mar 26 Mon | 26 March (Tue):
- Curved mirror characterization
(Koji, done) |
|
84
|
Wed Mar 27 20:54:54 2013 |
Koji | General | General | OMC building plan / procedure ~ Mar 27 Wed | 27 March (Wed)
- AOM drift investigation (Lisa,
Zach) |
|
85
|
Wed Mar 27 20:55:10 2013 |
Koji | General | General | OMC building plan / procedure ~ Mar 28 Thu | 28 March (Thu):
Rebuild the bottom template
in the lab
Place the bottom |
|
88
|
Mon Apr 1 03:13:41 2013 |
Koji | Optics | General | Failure of PZT-glass joints | [Koji, Jeff, Zach, Lisa]
We glued a test PZT-mirror assembly
last week in order to make sure the heat |
|
89
|
Mon Apr 1 03:23:48 2013 |
Koji | Optics | General | UV power calibration | [Koji Lisa Jeff Zach]
Eric G bought a UV power meter from
American Ultraviolet. |
|
90
|
Mon Apr 1 10:28:03 2013 |
Koji | Mechanics | General | Additional UV blast for the top surface | [Koji, Lisa, Jeff, Zach]
Jeffs concern after talking with the |
  |
91
|
Mon Apr 1 18:17:01 2013 |
Koji | Optics | General | Mirror curvature center test | Locations of the curvature minimum
on the OMC curved mirrors have been measured.
|
6x |
93
|
Wed Apr 3 18:42:45 2013 |
Koji | Optics | General | EP30-2 gluing test | EP30-2 gluing test
|
|
104
|
Mon Apr 8 21:11:14 2013 |
Koji | Optics | General | PZT assembly gluing | [Jeff, Zach, Koji]
PZT assembly gluing
Glue gun -> to be returned to |
|