40m
QIL
Cryo_Lab
CTN
SUS_Lab
TCS_Lab
OMC_Lab
CRIME_Lab
FEA
ENG_Labs
OptContFac
Mariner
WBEEShop
|
PSL |
Not logged in |
 |
|
Fri Oct 4 13:41:44 2019, anchal, Notes, FSS, FSS Plant Model  
|
Fri Oct 4 14:56:42 2019, Ian MacMillan, Notes, FSS, FSS Plant Model
|
Tue Oct 8 10:41:43 2019, anchal, Notes, FSS, FSS Plant Model
|
Mon Oct 14 12:54:41 2019, anchal, Notes, FSS, FSS Plant Model v2  
|
Tue Oct 22 13:07:45 2019, Ian MacMillan, Notes, FSS, FSS Plant Model v2  
|
Thu Oct 24 11:42:06 2019, Ian MacMillan, Notes, FSS, FSS Plant Model v2
|
Tue Dec 3 17:27:54 2019, Ian MacMillan, Notes, FSS, FSS Plant Model v2 
|
Mon Dec 9 18:08:13 2019, Ian MacMillan, Notes, FSS, FSS Plant Model v2 
|
Tue Dec 10 11:57:58 2019, Ian MacMillan, Notes, FSS, FSS Plant Model v2
|
Thu Dec 12 11:54:11 2019, Ian MacMillan, Notes, FSS, FSS Plant Model v2   
|
Thu Dec 12 19:05:33 2019, rana, Notes, FSS, FSS Plant Model v2
|
Mon Dec 16 09:43:56 2019, Ian MacMillan, Notes, FSS, FSS Plant Model v2  
|
Tue Jan 14 13:30:39 2020, Ian MacMillan, Notes, FSS, FSS Plant Model v2  
|
Tue Jan 14 13:32:16 2020, Ian MacMillan, Notes, FSS, FSS Plant Model v2  
|
Tue Jan 28 13:27:25 2020, Ian MacMillan, Notes, FSS, FSS Plant Model v2  
|
Mon Feb 10 12:46:17 2020, Ian MacMillan, Notes, FSS, FSS Plant Model v2
|
Fri Feb 14 16:46:47 2020, Ian MacMillan, Notes, FSS, FSS Plant Model v2 
|
Tue Feb 18 15:42:46 2020, Ian MacMillan, Notes, FSS, FSS Plant Model v2  
|
Tue Mar 3 17:13:04 2020, Ian MacMillan, Notes, FSS, FSS Plant Model v2    
|
Wed Mar 11 15:40:50 2020, Ian MacMillan, Notes, FSS, FSS Plant Model v2 
|
Thu Mar 12 16:21:49 2020, Ian MacMillan, Notes, FSS, FSS Plant Model v2 
|
Thu Mar 12 17:18:51 2020, rana, Notes, FSS, FSS Plant Model v2
|
|
Message ID: 2520
Entry time: Tue Jan 28 13:27:25 2020
In reply to: 2511
Reply to this: 2527
2537
|
Author: |
Ian MacMillan |
Type: |
Notes |
Category: |
FSS |
Subject: |
FSS Plant Model v2 |
|
|
Added all documents to the LIGO document for the FSS Plant Circuit LIGO-D2000020-v1. The updated board and schematic are also below with the zip file of all the Eagle files.
The board was ordered from JLCPCB. The current status is "In Production." Its production will take longer because of the Chinese new year but its shipping should not because it is being shipped with DHL. The low-noise thin-film resistors were ordered from Digikey and should arrive on Friday 01/31/2020.
The next step is assembling the circuit and putting it in a box. I can't assemble the circuit until the parts arrive but I can get a box and add the power supply. This will make the production faster once the board arrives.
Once the board is assembled its transfer functions will be measured and I will work with Anchal to implement it. We are almost done.
|
|
|
|
|
|