Entry  Thu Feb 22 15:15:20 2018, awade, Craig, Misc, Safety, Water leak in the lab 
    Reply  Fri Feb 23 13:15:22 2018, awade, Misc, Safety, Water leak in the lab 
       Reply  Mon Feb 26 14:16:38 2018, awade, Misc, Safety, Water leak in the lab 
          Reply  Wed Feb 28 11:50:21 2018, awade, Misc, Safety, Pipe work scheduled for lab Friday March 2nd 
             Reply  Wed Feb 28 13:43:15 2018, awade, Craig, Misc, Safety, Pipe work scheduled for lab Friday March 2nd IMG_2310.JPGIMG_2311.JPGIMG_2312.JPG
Message ID: 2110     Entry time: Wed Feb 28 11:50:21 2018     In reply to: 2106     Reply to this: 2111
Author: awade 
Type: Misc 
Category: Safety 
Subject: Pipe work scheduled for lab Friday March 2nd 

The Caltech plumbing shop called to say they will have all the parts they need to start work Friday morning.  There is a bit of masonary work to be done to the down pipe hole.  So there will be some dust.

I have ordered materials from McMaster for wrapping the experiment up again.  I got extra so we will have a cling-wrap-kit® for the WB labs ready to go in the future. I didn't get a tracking recipt, but the order went through around COB on the 26th.  Should be here today or tomorrow.

Quote:

I called facilities.  They say with their new purchase approval process, and lead time on parts, that they expect the repair jobs on piping would start early next week.  

There will be a bit of manual alterations to the through hole coming down into the ceiling so we need to do some dust mitigation.  I will order some more cling wrap and salvage some of the plastic sheeting from the last episode.

 