Sat Jul 2 16:12:49 2016, Antonio, Notes, FSS, FSS : THINGS TO BE DONE (some notes)
|
Wed Jul 13 10:24:24 2016, rana, Notes, FSS, FSS : THINGS TO BE DONE (some notes)
|
Wed Jul 13 13:31:33 2016, Evan, Notes, FSS, FSS : THINGS TO BE DONE (some notes)
|
Wed Jul 13 20:03:07 2016, Antonio, Notes, FSS, FSS : THINGS TO BE DONE (some notes)
|
Wed Oct 5 14:20:53 2016, awade, Notes, FSS, FSS : THINGS TO BE DONE (some notes)
|
Wed Jan 4 12:02:51 2017, awade, Notes, EOM, EOM drivers
|
|
Message ID: 1659
Entry time: Sat Jul 2 16:12:49 2016
Reply to this: 1665
|
Author: |
Antonio |
Type: |
Notes |
Category: |
FSS |
Subject: |
FSS : THINGS TO BE DONE (some notes) |
|
|
In order to have a frequency stabilization system (FSS) working with a new frequency modulation (FM)
I collect some notes of things that need to be done;
In vacuum cavities
- Choose the FM for both South and North cavities;
- Currently we are using ~14MHz;
- PMC are not into the path;
- Buy the oscillators;
- Modify the photodetectors to the right frequencies or build new ones;
- Buy one BB EOM
- Currently we have a resonant ~14MHz and one BB with an external resonant circuit;
- Build two resonant circuits for the BB EOMs: one applied to what we already have just replacing the external circuit and one to new BB EOM that we will buy;
- We need to buy (perhaps) a HV driver;
- Later we may need to modify the FSS servo board;
- (...please add if something is missing...)
PMCs
In parallel and/or later in order to implement both the PMCs in the North and South path we need:
- Buy one BB EOM;
- We currently have a resonant 21.5MHz;
- Build a resonant circuit at 21.5MHz;
- Build a resonant photodetector at 21.5MHz;
- We currently have one at that frequency;
- Build two servo boards for both PMCs;
- We may have one available;
|