26
|
Wed Jun 29 16:44:17 2016 |
Gabriele | General | Configuration | First disk eigenfrequency | The following table shows the lowest eigenfrequency
(Hz) for different sizes of disks
|
 |
37
|
Mon Jul 11 15:21:12 2016 |
Gabriele | General | Daily Progress | One disk installed into the chamber | [Alena, Gabriele]
We attached one of the silicon
lenses to a 1" optical post using some |
    |
44
|
Fri Jul 15 17:56:50 2016 |
Gabriele | General | Daily Progress | QPD connected to digital system | I connected the QPD to the ADC interface
with a temporary cable running on the floor.
I could get signals. I still have |
|
48
|
Mon Jul 18 14:29:07 2016 |
Gabriele | General | Daily Progress | Status of the test setup | I checked that the QPD electronics works
as expected, and that I can acquire the signals
using the ADCs. A new model (x3cr1) is up |
 |
49
|
Mon Jul 18 17:46:04 2016 |
Gabriele | General | Daily Progress | First look at QPD signals | Here's the first spectrum of the QPD
X and Y signals, acquired with the digital
system. Roughing and turbo pumps are still |
|
53
|
Tue Jul 19 17:21:48 2016 |
Gabriele | General | Daily Progress | First modes excited! | We can't generate any arbitary signal
with the real time model, since awg is not
working properly yet. For the moment being |
|
56
|
Thu Jul 21 12:10:14 2016 |
Gabriele | General | Daily Progress | Glitch hunting | Yesterday I could clearly see the glitches
as jumps in the time domain plot of X and
Y signals, and trace them to somewhat harder |
  |
68
|
Thu Jul 28 14:01:27 2016 |
Alena | General | Daily Progress | Clean room | Ordered the clean room (hardware+hepa filters)
and vacuum gauges |
|
70
|
Fri Jul 29 14:08:31 2016 |
Gabriele | General | Daily Progress | Peak tracking code for real time model | Summary
I wrote a C function
to reconstruct the amlplitude and frequency
of a line. It can be added as a block into |
  |
74
|
Mon Aug 8 10:42:46 2016 |
Gabriele | General | General | Dependency of eigenmode frequencies on thickness and diameter | I ran a set of COMSOL simulations to determine
the dependency of the frequency of each eigenmode
on the disk thickness and diameter, within |
26x |
77
|
Thu Aug 11 08:45:19 2016 |
Gabriele | General | General | QPD signals with dielectric filter | I installed a dielectric laser line filter
(Thorlabs FLH05633-5, center wavelength 633
nm, FWHM 5 nm) in front of the QPD. In this |
 |
82
|
Sat Aug 13 14:05:02 2016 |
Gabriele | General | Daily Progress | First work on the measurement user interface | Today I started programming part of the
user interface that will be used to perform
the measurements. Not much implemented so |
 |
85
|
Sun Aug 14 18:26:19 2016 |
Gabriele | General | General | Plans for the automatic mode search | Here's how I imagine the mode search
to proceed:
the user select the list |
|
92
|
Sat Aug 20 17:01:10 2016 |
Gabriele | General | Daily Progress | First ring down measurements | Everything is working pretty well. This
morning the pressure was about 1.2e-6 Torr.
I connected the high voltage amplifier and |
|
93
|
Sat Aug 20 22:18:26 2016 |
Gabriele | General | Daily Progress | First measured Qs | Using the first ring down of the day (GPS 1155754513
+ 3600 seconds), I computed the amplitude
of each of the modes already identified, |
22x |
94
|
Sun Aug 21 08:51:22 2016 |
Gabriele | General | Daily Progress | New disk installed | Vented the chamber. Installed a new disk
(MO 03). The one I measured yesterday is
now named MO 02 and it is the one with the |
|
96
|
Sun Aug 21 15:36:16 2016 |
Gabriele | General | Daily Progress | New test | Roughing pump stopped at about 3:30:30pm.
HV amplifier on at 3:33:30pm, excitation
at 3:35:30pm. Recentered QPD at 3:36pm |
|
97
|
Sun Aug 21 17:16:03 2016 |
Gabriele | General | Daily Progress | Ring down measurement with new disk | After fixing the setup, the measurement
with the new disk looks great. After more
than one hour the first two modes are still |
22x |
98
|
Sun Aug 21 17:41:34 2016 |
Gabriele | General | Daily Progress | New test | I checked the status at about 5:20pm, the
turbo pump was in error and spinning down,
since the roughing pump has been off for |
|
99
|
Mon Aug 22 08:29:24 2016 |
Gabriele | General | Daily Progress | New test | Restarted roughing and turbo pump at about
8:10am.
|
|
100
|
Mon Aug 22 12:01:52 2016 |
Gabriele | General | General | Tests of the day | Disk excited at 12:01pm. Exited the room
at 12:03pm.
Opened the chamber at about 2:30pm, |
|
102
|
Tue Aug 23 08:46:04 2016 |
Gabriele | General | Daily Progress | Daily tests | MO03 - edge polished:
Turbo off, QPD centered, before
excitation (60 seconds) |
|
103
|
Tue Aug 23 09:21:25 2016 |
Gabriele | General | General | Status of Mark Optics disks | We initially received 20 disks (75 mm diameter,
1 mm thickness) from Mark Optics. Here's
their status as of today |
|
104
|
Tue Aug 23 09:44:11 2016 |
Gabriele | General | General | Measurements on MO-02 | Two good ring-downs measurements were performed
on MO-02. The first one was already reported
in a previous elog |
7x |
106
|
Sun Sep 11 10:05:33 2016 |
Gabriele | General | Daily Progress | New substrate in the chamber | I installed one of the new substrates (with
flats) into the chamber, and started the
pumpdown at about 9:45am LT. |
|
107
|
Mon Sep 12 16:00:06 2016 |
Gabriele | General | Daily Progress | First fully automated measurements of ring down | I finished the first version of the automation
software to measure the ring down of the
disk modes. I tested it with the new substrate |
   |
108
|
Tue Sep 13 10:33:35 2016 |
Gabriele | General | General | Disk excited | Disk excited with white uniform noise,
amplitude 5 V, for some tens of seconds.
Excitation off at |
|
109
|
Wed Sep 14 13:08:05 2016 |
Gabriele | General | General | Ringdown with roughing pump off | At 1:05pm LT I stopped the roughing pump
and started a ring-down measurement. Pump
restarted at 2:18pm LT. |
|
110
|
Wed Sep 14 20:17:33 2016 |
Gabriele | General | General | Band-limited excitation | Excitation started at 20:15:30LT, 20 seconds
long. The excitation is band-limited (10
Hz) centered around each of the predicted |
|
111
|
Thu Sep 15 08:13:20 2016 |
Gabriele | General | General | Pump had no effect on ring down measurements | The plot below shows three measurements
of the Q of the same disk: during the first
two the roughing pump was on, while during |
|
112
|
Thu Sep 15 08:27:57 2016 |
Gabriele | General | General | New band-limited excitation | Same as in elog #110,
but now the amplitude is proportional to
frequency squared: |
|
114
|
Thu Sep 15 15:15:10 2016 |
Gabriele | General | General | Edge effect on losses | I made a COMSOL model that can compute
the distribution of elastic energy for each
mode, dividing it into: |
  |
115
|
Fri Sep 16 14:06:43 2016 |
Gabriele | General | General | Pump had no effect on ring down measurements | Same plot as below, but this time with
estimated 95% confidence intervals for the
Q values, as obtained from the fit only. |
|
117
|
Tue Sep 20 16:12:09 2016 |
Gabriele | General | General | Pump down | As a test, I installed MO1 (the disk with
the burn mark, used for the first edge laser
polishing test) and started pumping down. |
|
118
|
Tue Sep 20 16:43:58 2016 |
Gabriele | General | General | Excitation and ring down | The pressure is at abour 3e-6 Torr. I centered
the QPD and started an excitation. The HV
amplifier manual states that the driver can |
|
119
|
Wed Sep 21 08:12:13 2016 |
Gabriele | General | General | Excitation and ring down | New excitation (2000V) at about 8:06am.
Had to recenter the QPD again after the excitation.
Engaged the 500Hz high pass filter |
|
120
|
Wed Sep 21 14:42:47 2016 |
Gabriele | General | General | Serialized (etched) disk installed | Just for fun, I installed the disk thas
has been etched in the center with "1234".
I figured out that the ESD PCB was probably |
|
121
|
Thu Sep 22 09:49:21 2016 |
Gabriele | General | General | Ring-down of etched disk | QPD centerd, quiet data, light off, one
minute from
PDT: 2016-09-22 09:46:29.393609 |
|
128
|
Tue Sep 27 08:53:46 2016 |
Gabriele | General | Vacuum | Etched disk installed | Installed the etched disk: using manually
the centering ring allowed me to get the
beam on the QPD. A couple of taps to the |
|
130
|
Tue Sep 27 15:10:59 2016 |
Gabriele | General | Measurements | Ring-down of etched disk | Quiet (roughing pump off, lights off):
60 seconds from
PDT: 2016-09-27 15:05:30.805667 PDT |
|
131
|
Wed Sep 28 10:26:58 2016 |
rana | General | General | references on ideal glasses | Some easy to read reviews on
thin films and ideal glass for people getting
started in this Q measuring game.
|
|
133
|
Mon Oct 17 10:50:50 2016 |
Gabriele | General | Vacuum | No sign of problems in the electrostatic drive | I opened the chamber and took the etched
disk out. Inspection of the electrostatic
drive does not show any sign of burn or damage. |
|
134
|
Tue Oct 18 16:29:37 2016 |
Gabriele | General | Measurements | S1600433 | S1600433, annealing run 10/10/2016
Installation
Installed
in the measurement system, chamber closed
pump
down started at 4:27pm LT
turbo |
17x |
135
|
Tue Oct 18 16:52:16 2016 |
Gabriele | General | Measurements | Sample inspections from annealing run 10/10/2016 | LIGO-T1600466
S1600432 shows some residual
on face, close to the edge, probably from |
|
136
|
Wed Oct 19 13:35:23 2016 |
Gabriele | General | Measurements | S1600438 | S1600438, not annealed, as received
from Mark Optics
Installation
Turbo
pump switched off at 11:42am (2016-10-19)
Turbo |
    |
137
|
Wed Oct 19 16:40:24 2016 |
sults: | General | Measurements | S1600349 | S1600439, not annealed, as received
from Mark Optics
Installation
installed
and balanced, pump down started at 4:38pm |
10x |
138
|
Wed Oct 19 17:08:47 2016 |
Gabriele | General | Measurements | S1600433 vs S1600438 |
S1600433 has been annealed, was
contaminated by the iron oxide, and it was
cleaned using first contact. No residual |
|
139
|
Thu Oct 20 11:04:03 2016 |
Gabriele | General | Measurements | Sample with flame polished edges | Sample with edges flame polished in Glasgow
Installation
into
the chamber and balanced at 11am. Pump down
started at 11:00am.
it looks like |
7x |
141
|
Fri Oct 21 13:45:21 2016 |
Gabriele | General | Measurements | S1600447 | Sample S1600447, as received from Mark
Optics, second batch
Measurements
Installed
into the chamber, pumping down started at |
13x |
142
|
Fri Oct 21 14:03:17 2016 |
Gabriele | General | Vacuum | Roughing pump moved | I moved the roughing pump out of the clean
room, adding an extension hose.
|
 |