40m QIL Cryo_Lab CTN SUS_Lab TCS_Lab OMC_Lab CRIME_Lab FEA ENG_Labs OptContFac Mariner WBEEShop
  Coating Ring-down Measurement Lab elog  Not logged in ELOG logo
Entry  Mon Jul 11 14:56:45 2016, Alena, Facility, Daily Progress, Vacuum chamber tests 20160711.png
    Reply  Mon Jul 11 17:04:06 2016, Alena, Facility, Daily Progress, Vacuum chamber tests 
Message ID: 36     Entry time: Mon Jul 11 14:56:45 2016     Reply to this: 38
Author: Alena 
Type: Facility 
Category: Daily Progress 
Subject: Vacuum chamber tests 

Installed a gate valve between the roughing and tubbo pump. See below a pump down curve. The convection gauge is not calibrated. the turbo started at 14th min (at about 3 torr)

Attachment 1: 20160711.png  178 kB  | Hide | Hide all
20160711.png
ELOG V3.1.3-