40m QIL Cryo_Lab CTN SUS_Lab CAML OMC_Lab CRIME_Lab FEA ENG_Labs OptContFac Mariner WBEEShop
  40m elog, Page 336 of 357  Not logged in ELOG logo
ID Date Authorup Type Category Subject
  3347   Mon Aug 2 10:26:15 2010 steveConfigurationVACvery slow pumpdown completed

Quote:

Bob and Steve closed BS chamber with the help of the manual Genie lift and the pump down started. The PSL shutter was closed and manual block was placed in the beam path. High voltage power supplies were checked to be off.

Pumping speed ~ 1 Torr/min was achieved at  1/8 of a turn opened roughing valve RV1

 3 days pump down #69 completed. Thanks to Koji  and Kiwamu  who did more roughing on Saturday and Sunday.

Attachment 1: veryslowpd.jpg
veryslowpd.jpg
  3371   Fri Aug 6 08:09:15 2010 steveUpdatePSLPSL preparation work

Quote:

PSL preparation work

Aug 5th 10am-4pm?: (Kiwamu, Alberto, Koji)

  • Removing the unused cables around the PSL table and the control room

Aug 6th 10am-4pm?: (Kiwamu (ex. noon-2pm), Alberto, Koji, Jenne ('till noon) )

  • Labeling the cables to be disconnected / making the records ==> All
  • Removals
    • the big nuts at the side of the PSL table ==> Steve
    • the cable ties on the PSL frame ==> Easy
    • Innolight 2W ==> Kiwamu
    • the green pickoff optics at the edge, if necessary ==> Kiwamu talking with Steve
    • Optics on the shelf ==> Jenne / Koji
    • Oscilloscopes on the shelf ==> Jenne / Koji
    • CCD camera connections (optional, as far as not critical for the operation)
  • Put poles on the table (for the plastic sheet) ==> Alberto / Koji

Aug 9th  9am-5pm: (Steve, Jenne, Alberto, Koji)

  • Disconnecting the cables ==> All
  • Shutting down the PSL ==> Steve/Koji
    • Draining the cooling water  ==> Steve
  • Removals
    • The accelerometers ==> Jenne
    • the PSL chamber ==> Steve
    • Periscopes ==> Alberto
  • Sealing of the table with the plastic sheets

 

  • The chiller is planned to go to MIT

 

Monday, August 9

 We should move the reference cavity too. Will this cavity be pumped while relocated?

Check and insure that attached and cut-free cables of PSL have enough room to tolerate the raising of the enclosure by 6"

I had second thoughts about the power line to the OMC. Koji was right, we should disconnect them from the power supplies.

The PSL enclosure doors on the north side will have to be removed some times to move exiting and entering ports.

 

  3394   Tue Aug 10 17:21:48 2010 steveUpdateGeneralPSL optical table is at 30" height

Mike Gerfen, Koji and Steve,

 

Our old ( 6 x 10 x 1 ) ft Newport optical table will have the same height as the neighboring AP table when this job is finished.

Today's work was to elevate the optical table ~ 2400 lbs to 30" clearance to create a workable space below.

 

Atm1,  enclosure frame was raised by 6"

Atm2,  2 pellet jacks and 4x4 technology in the work.

Atm3,  ready for drill and tap with jig plate in place, note 4 Al legs 8" OD. 1/4" wall safely supporting the load

Atm4,  showing clamps that holding 1/2" plywood with jigs

Atm5, We removed the 4 old legs: 6" OD steel, 1/4" wall and 10" high after they were unloaded.

Attachment 1: P1060586.JPG
P1060586.JPG
Attachment 2: P1060583.JPG
P1060583.JPG
Attachment 3: P1060591.JPG
P1060591.JPG
Attachment 4: P1060593.JPG
P1060593.JPG
Attachment 5: P1060597.JPG
P1060597.JPG
  3404   Thu Aug 12 10:56:31 2010 steveUpdateEnvironment dusty floor work in progres

I powered down 1Y1 and 1Y2 instrument racks of MC and RF-systems this morning.

Both racks, SP table, clean tools-parts boxes and MC2 area are also covered with plastics.

Bertin Bros. Construction, Inc is working on the floor preparation. Their head man is Robby Bertin, cell 626. 831.2264

Today's job:

remove tiles, clean off tile glue, drill for ribbed  steel bars, rough clean- surface for good bounding. paint floor with bounding agent

  3410   Thu Aug 12 16:18:46 2010 steveUpdateEnvironmenttiles and adhesive removed

Quote:

I powered down 1Y1 and 1Y2 instrument racks of MC and RF-systems this morning.

Both racks, SP table, clean tools-parts boxes and MC2 area are also covered with plastics.

Bertin Bros. Construction, Inc is working on the floor preparation. Their head man is Robby Bertin, cell 626. 831.2264

Today's job:

remove tiles, clean off tile glue, drill for ribbed  steel bars, rough clean- surface for good bounding. paint floor with bounding agent

Tiles and adhesive removed. There were no dust storms created. Solvent paint- removal made the hole IFO -lab smell like the paint shop.

The south door is open with a fan blowing air inside. The north-west door is open through control room to outside to let air rinse the drying

paint-removal. Koji is  taking lunch break while test riding our new PSL table legs.

Attachment 1: P1060604.JPG
P1060604.JPG
Attachment 2: P1060606.JPG
P1060606.JPG
Attachment 3: P1060603.JPG
P1060603.JPG
Attachment 4: P1060610.JPG
P1060610.JPG
Attachment 5: DSC_2388.JPG
DSC_2388.JPG
  3422   Fri Aug 13 18:32:48 2010 steveUpdatePEM new legs attached to optical table

Koji, Rana and Steve

 

The floor preparation continued today. The really messy part of drilling and jack-hammering the concrete were done in controlled manner.

Particle counts peaked at 106K of 0.3 micron and 13 K of 1.0 micron particles/ cfmin at the top of SP table.

Legs were installed with the help of Koji and strongman Rana. Professor Rana was very useful lifting the 85 lbs legs. 

 

Atm1, Drilling holes for ribbed bar reinforcement of concrete

Atm2, Koji and Rana are playing hide and seek while installing legs

Atm3-4, 6 Rigid tripod legs attached by 6x3 of 1/4-20x 7/8 screws. The top plates of the legs were torqued to 108 ft/lbs by Rana

Attachment 1: P1060612.JPG
P1060612.JPG
Attachment 2: P1060626.JPG
P1060626.JPG
Attachment 3: P1060631.JPG
P1060631.JPG
Attachment 4: P1060636.JPG
P1060636.JPG
  3430   Tue Aug 17 14:09:15 2010 steveUpdatePEMPSL optical table schedule

Tuesday, 17 August : fill tunnel, set table height, level table and balance load

Wednesday : grout tripod legs and leave it alone

Thursday : built  guide-form for concrete

Friday :  pour concrete

Monday, 23 August : remove guide forms and clean up

  3435   Wed Aug 18 16:42:14 2010 steveUpdatePEMPSL optical table legs load balanced

 

 Rana, Koji, Alberto and Steve, Tuesday afternoon

 

Atm3, Part of the tunnel under the table was filled with quick drying concrete this morning  to give solid support for tripod legs.

          PVC tube 6 " ID with TEE will able us to connect AP table, PSL table and Control room if needed

Atm4, Table height set to equal AP at  ~32.75 " on copper plates using 5/8-11 x 4.5" set screw-bolt in tripod foot

           Rough leveling was done by 4 individual levels at the four corners with 9" long Stanley cast aluminum levels.

          Load balancing of the total weight  ~ 3000 lbs over  6 legs x3 = ~170 lbs on each jack screw with Snap-On torque wrench at 140 lbs/ft

Atm1, Three crew members at work. Prof. Rana's calibrated right hand was used at jack screws where insufficient space was available for socket head wrench.

Atm2, Table is ready for no shrink grouting now.

         

 

 

 

 

Attachment 1: P1060671.JPG
P1060671.JPG
Attachment 2: P1060674.JPG
P1060674.JPG
Attachment 3: P1060670.JPG
P1060670.JPG
Attachment 4: P1060676.JPG
P1060676.JPG
  3444   Thu Aug 19 16:03:59 2010 steveUpdatePEMgrouting of PSL tripod legs

The 10' x 6' optical table is seating on 6 tripods. Each tripod leg has 3 feet. They are supported by jack screws against copper plates on the concrete floor.                            These set screws allowed us to set the height,  level and distribute the load of the table.

To lock this position of the table grouting is used around the jack screws and between the concrete floor and the tripod feet.

Once the grout set the load will be carried by the hole feet  of 4" x 3.25" x3 = 39 sq inches per tripod leg

 

These ~4" thick grouted islands of 8-9" OD will be covered by 4" concrete. The area between the legs will be filled with 8" thick concrete.

http://www.fivestarproducts.com/techinfo/GroutHandbook.pdf

 

Atm1, http://www.fivestarproducts.com/cementgrouts/specsheets/grout_ss.pdf

         Cement based grout, early height change 0 - 4%, hardened height change 0 - 0.3%

Atm2-3,  pouring grout

Atm4,  south west leg is done

 

Tomorrow: setting up ribbed bars, building frame to hold concrete and pour concrete

Attachment 1: P1060687.JPG
P1060687.JPG
Attachment 2: P1060681.JPG
P1060681.JPG
Attachment 3: P1060686.JPG
P1060686.JPG
Attachment 4: P1060696.JPG
P1060696.JPG
  3448   Fri Aug 20 15:49:14 2010 steveUpdatePEMgrouting is done

The preparation for pouring concrete is continuing. The grout forms were removed. Half inch ribbed steel bars were epoxied into our 4" thick floor.

The concrete holding sides- forms are cut to size. They will be installed on Monday morning and pouring concrete should follow.

We can be planning for cleaning up on Tuesday

 

Atm1, epoxy used bars

Atm2, south west tripod feet grouted

Atm3, ribbed bars are getting ready

Attachment 1: P1060699.JPG
P1060699.JPG
Attachment 2: P1060700.JPG
P1060700.JPG
Attachment 3: P1060704.JPG
P1060704.JPG
  3449   Fri Aug 20 16:17:35 2010 steveUpdatePEMPEM-count channels are not working

C1: PEM-count channels are dead since August 12, 2010

  3455   Mon Aug 23 08:28:27 2010 steveUpdateSUSETMY sus damping restored
  3462   Tue Aug 24 11:23:32 2010 steveUpdatePEMtripod leg installation completed

Bertine Robby, Bertin and Jerry completed the installation by pouring concrete yesterday and cleaning up today.

Atm1-2, steel bars, grouted feet and side forms are ready

Atm3,    bounding agent is applied for better bounding

Atm4,    pumping concrete

Atm5,    shaker is used to fill-all

Atm6,    late after noon the forms- sides were removed,     NOTE: actual table to concrete distance is 12.75"

Atm7,    construction people left and the tile man is on the way

 

The tile patching should complete today so tomorrow we can remove plastic covers.

 

Attachment 1: P1060731.JPG
P1060731.JPG
Attachment 2: P1060719.JPG
P1060719.JPG
Attachment 3: P1060736.JPG
P1060736.JPG
Attachment 4: P1060738.JPG
P1060738.JPG
Attachment 5: P1060742.JPG
P1060742.JPG
Attachment 6: P1060757.JPG
P1060757.JPG
Attachment 7: P1060755.JPG
P1060755.JPG
  3472   Wed Aug 25 16:13:32 2010 steveSummaryPEMPSL optical table is back into operation at 32.75" level

The tile work was done yesterday after noon.

This morning Mike Gerfen and me lowered the enclosure frame to normal height.

Keven- janitor and I removed plastic covers from chambers, racks, SP, MC2 and clean tool boxes.

 

The afternoon Jenne, Kiwamu, Joe and Aiden cleaned the enclosure inside out. The particle count measured zero inside the enclosure with HEPAs on when the covers were

removed. The MOPA and all other components were happy to see us in excellent condition.

This table height is very user friendly!

 

Safety grounds were reconnected.

 

Atm1, new tiles around the concrete slab

Atm2, frame lowered with low cross bars reinstalled

Atm3, the enclosure frame's north west foot is connected to ground

Atm4, PSL optical table is connected to ground at the north east corner through 1 Mohm

Atm5, PSL optical table level at a stimulating, back-friendly height

Attachment 1: P1060764.JPG
P1060764.JPG
Attachment 2: P1060768.JPG
P1060768.JPG
Attachment 3: P1060777.JPG
P1060777.JPG
Attachment 4: P1060776.JPG
P1060776.JPG
Attachment 5: P1060780.JPG
P1060780.JPG
  3477   Fri Aug 27 11:27:33 2010 steveUpdatePEMcrane safety document

I posted the crane safety document on the 40m wiki, vacuum page as 26 August 2010

Please add your comments and corrections.

 

The South End Crane will be balanced on Tuesday,  31 August 2010

This will mean that the back door of the south arm will be open on and off. Air quality will bad.

Please plan accordingly.

  3493   Tue Aug 31 10:44:17 2010 steveUpdatePEMconcrete sealed

The PSL -leg concrete was sealed with a single coat of SCOFIELD Cureseal-S to minimize shedding of particles.

The optical table was covered  and optics were removed from the shelf. Accelerometers were turned off.

Attachment 1: P1060787.JPG
P1060787.JPG
  3495   Tue Aug 31 13:31:00 2010 steveUpdatePEMroom temp lowered

I lowered room 101 thermostat setting from 74F to 72F

  3496   Tue Aug 31 14:47:53 2010 steveConfigurationPEMtoilet upgrade

Our toilets were replaced by a green Gerber 1.6 gpf ( 6 lpf ) last week.

Attachment 1: toil-n.JPG
toil-n.JPG
  3505   Wed Sep 1 10:54:15 2010 steveUpdatePEM more crane balancing

Crane balancing at the south end is continuing today.

  3513   Thu Sep 2 14:11:17 2010 steveSummaryPEMsouth end crane balancing is completed

The crane I -beam now leveled at all degrees of rotation.  The lower hinge was moved southward  about 1/4 of an inch.  Performance was tested at 2000 lbs

 

Atm1, work in progress

Atm2, load test at 1 Ton

Atm3, service report

Attachment 1: P1060798.JPG
P1060798.JPG
Attachment 2: P1060800.JPG
P1060800.JPG
Attachment 3: P1060804.JPG
P1060804.JPG
  3514   Thu Sep 2 16:41:32 2010 steveConfigurationSAFETYlaser is ON: safety glasses required!

I hooked up interlock to the Innolight 2W 1064 nm in the enclosure. The manual shutter  is closed on this unit.

SAFETY GLASSES REQUIRED !

  3547   Wed Sep 8 16:17:58 2010 steveUpdatePEMparticle counter problem

I played with the particle counter this morning. Now it's running and reading the correct numbers on the old COCHECKLIST.adl medm screen.

However, it can not be seen with dataviewer.

Koji just rebooted the frame builder and the problem was solved.

  3549   Thu Sep 9 08:23:45 2010 steveUpdateSAFETYmain laser turned off

Innolight 2W 1064nm main laser was turned off for more enclosure related work.

The electrician re rooting the power- conduit to the interlock under the floor and bring it through the new concrete tunnel.

Emergency laser power shut off switch was tested at entry door 104M.  It worked fine.

 

No laser glasses required. Laser will be turned back on around 11 am today.

  3550   Thu Sep 9 11:17:15 2010 steveUpdateSAFETYmain laser is back ON

Quote:

Innolight 2W 1064nm main laser was turned off for more enclosure related work.

The electrician re rooting the power- conduit to the interlock under the floor and bring it through the new concrete tunnel.

Emergency laser power shut off switch was tested at entry door 104M.  It worked fine.

 

No laser glasses required. Laser will be turned back on around 11 am today.

Atm1,   AC power line to enclosure and interlock  was extended.

Atm2,   24V line to interlock rerouted

Atm3,   job is completed

 

SAFETY GLASSES REQUIRED !  SAFETY GLASSES REQUIRED!

 

 The laser is turned on. Injection current set to 0.871A.

Actually some one turned the  laser  off last night and did  not enter it into the elog ! Burned toast award is granted !

Please  come forward voluntarily.

Attachment 1: P1060813.JPG
P1060813.JPG
Attachment 2: P1060814.JPG
P1060814.JPG
Attachment 3: P1060816.JPG
P1060816.JPG
  3551   Thu Sep 9 11:31:54 2010 steveUpdatePEMaccelerometer cable connection

I turned off/on the power to the accelerometers in order to re rout their connections. I found cable connector body-nut  #3 loose to Accelerometer 2X This connector should be checked for solid performance.

  3585   Fri Sep 17 17:35:35 2010 steveUpdatePEMcleaned up at 1Y1 PSL rack

Cleaned up cables on the top and bottom. Vacuumed both areas. We still have some remaining shading from the MOPA umbilical and more unknown BNC cables hanging around.

  3591   Mon Sep 20 17:10:10 2010 steveConfigurationPSL enclosure beam guides to IFO are installed

The PSL out  2" OD beam guide tube was cut  1.5" shorter to 13.5"

The 10" OD  0.25" wall Al tube was replaced by a  lighter, not anodized and thinner  wall 0.094" tube of 15.5" lenght, that is 0.75" shorter.

The new position of the PSL table made these cuts necessary.

  3592   Tue Sep 21 15:33:02 2010 steveMetaphysicsTreasureWagonga alart

John Miller has arrived from Australia with 3 bags of  Wagonga Coffee. Trade bargaining has started on

250 mgs of Sumatran Mandehling, Timur and Papua New Guine.

Attachment 1: P1060866.JPG
P1060866.JPG
Attachment 2: P1060872.JPG
P1060872.JPG
  3605   Fri Sep 24 16:31:35 2010 steveConfigurationGeneralopen frame- rack is moved

The squeezing open frame rack was moved from the south side of the PSL enclosure to the north side of the SP table.

AC power breaker is PC-2  #1

 

Attachment 1: P1060881.JPG
P1060881.JPG
  3611   Mon Sep 27 08:59:50 2010 steveConfigurationVACslow vent has started

Blocked PSL output beam  into IFO

Checked: HV at IOO & OMC are off, jam nuts in position,

Closed V1 and VM3, opened VV1 to N2 regulator

We are venting at 1 Torr/min rate

  3616   Tue Sep 28 14:12:14 2010 steveUpdateGeneralvertex crane drive is out of order

The vertex crane drive is overheating, it stopped functioning. Service man will be here tomorrow morning.

I crane was just turned  on for for may be  about 5 minutes. The vertical drive was fine for a while, but the horizontal did not worked at all.

The crane is tagged out again and the controller box is cooling down.

  3624   Thu Sep 30 09:34:58 2010 steveUpdateGeneralvertex crane trolly drive fixed

Quote:

The vertex crane drive is overheating, it stopped functioning. Service man will be here tomorrow morning.

I crane was just turned  on for for may be  about 5 minutes. The vertical drive was fine for a while, but the horizontal did not worked at all.

The crane is tagged out again and the controller box is cooling down.

 Atm1, Vertex crane controller unit on horizontal I-beam.

            Module CCES-407 1HP 2.3A 460V/3 phase on the right was replaced. Speed was increased  to 30 Hz

Atm2, See burned insulation on black wire that was shorting to the large suppressor resistor on Atm3 One can see the pit marks on the right end of it.

        This large power dissipater resistor got hot as the malfunctioning controller 407 broke down.   Touching black power wire insulation melted and made a short.

          So the heat was created and finally the fuses were blown. The unnecessary large fuses were replaced by small ones.

Fortunately we had one spare controller on hand that made this repair to be done fast.

We used the new Crane Safety Check list  from LIGO-E1000379-v1 the first time yesterday before doors were removed.

Attachment 1: P1060891.JPG
P1060891.JPG
Attachment 2: P1060887.JPG
P1060887.JPG
Attachment 3: P1060889.JPG
P1060889.JPG
Attachment 4: P1060893.JPG
P1060893.JPG
  3626   Thu Sep 30 13:43:29 2010 steveUpdateSAFETYpropane gas smell in control room

The control room's north west corner smelled like propane gas  yesterday around 16:30

We all agreed that the smell was real and I called the safety office. I was told that they received 6 other calls from different parts of the campus.

The smell disappeared in about a half an hour.

  3637   Fri Oct 1 16:46:20 2010 steveBureaucracySAFETYYuta received 40m-101-safety training

Our visiting graduate student Yuta Michimura received 40m specific basic safety training today.

  3646   Tue Oct 5 09:26:04 2010 steveConfigurationPEMmoved accelerometers

Accelerometers xyz were moved from IOO-south/west  corner to under PSL table. They were turned off for ~20 minutes.

Guralp was also moved eastward about 2 ft. It is not leveled.

This is part of the preparation to remove access connector.

  3654   Tue Oct 5 17:39:21 2010 steveConfigurationVACwest access connector removed

Kiwamu, Koji, Yutah, Rana, Jan and Steve

We removed the west access connector this afternoon.

  3664   Thu Oct 7 08:39:39 2010 steveBureaucracySAFETYJoonho receives safety training

Our new undergrad Joonho Lee received 40m specific basic safety training yesterday.

Yuta and Joonho are scheduled to participate in the LIGO-laser safety tutelage with Peter K on Oct 12

  3670   Thu Oct 7 15:21:51 2010 steveUpdatePSLRF filter for PMC

We got two small RF filter for the PMC from Valera  They are made by http://www.larkengineering.com/   "MC35.5-3-AB" sma, 29300-01

Attachment 1: 35.5MHZ.pdf
35.5MHZ.pdf
  3676   Fri Oct 8 07:41:42 2010 steveConfigurationSAFETY2W laser shutter is closed

The 2 W Innolight shutter is closed and enclosure door removed. Beam path blocked. Do not change this condition.

  3677   Fri Oct 8 10:38:03 2010 steveConfigurationSAFETY2W laser shutter is closed

Quote:

The 2 W Innolight shutter is closed and enclosure door removed. Beam path blocked. Do not change this condition.

The PSL output beam guide was upgraded from 2" to 8" OD . It is green ready. Shutter is open.

Attachment 1: P1060905.JPG
P1060905.JPG
Attachment 2: P1060910.JPG
P1060910.JPG
  3682   Fri Oct 8 17:36:16 2010 steveFrogsPhotosvisiting undergrads

Prof Alan Weistein guided the 24 student through the 40m. His performance was rated as  an enthusiastic 9.5

Attachment 1: P1060916.JPG
P1060916.JPG
Attachment 2: P1060921.JPG
P1060921.JPG
Attachment 3: P1060922.JPG
P1060922.JPG
Attachment 4: P1060915.JPG
P1060915.JPG
  3688   Mon Oct 11 10:51:36 2010 steveUpdateSUSOSEMs, OSEMs, OSEMs...those lovely little OSEMs
Attachment 1: 40dll.jpg
40dll.jpg
  3698   Tue Oct 12 16:35:17 2010 steveConfigurationPSLPSL output monitor in place

Innolight PSL laser is set to @2.1A , ~1.6W output ! Please scan out when finished! 

The output monitoring pick up window W2-LW-2-2050-UV-1064-45S is in place. IOO_ANG_OPD and IOO_POS_QPD roughly aligned.

The PMC alignment and/ or mode matching is bad. PMC reflected is 50%, throughput 600mW

Remember to block PSL output ! into IFO

 

  3733   Mon Oct 18 09:01:48 2010 steveHowToGeneralHow not to

This BNC cable is crying for help. Please do not do this to me.  It should be reported  to the  abused center.Throw this cable into the garbage now.

Attachment 1: P1060926.JPG
P1060926.JPG
  3745   Wed Oct 20 16:41:41 2010 steveOmnistructureGeneral laser chiller leaving for MIT
Attachment 1: P1060929.JPG
P1060929.JPG
  3751   Thu Oct 21 10:44:56 2010 steveMetaphysicsTreasure1987 supernova tapes plus....?

I'm cleaning out to make room for our new optical cabinet. Are we keeping these? There are  ~20  pieces of 10" od 1" wide tapes and large number of cassettes.

AJW,  Zucker,  Stuart A and Koji were notified in this matter.

Alan suggested to save data of Bruce Allen paper of observation of binary neutron stars in the 40m on 1994 November 14-20 and save back up tapes of his period in the 40m.

Mike: reels are not readable any more, it is time to let go

Attachment 1: P1060932.JPG
P1060932.JPG
  3792   Wed Oct 27 09:02:29 2010 steveUpdateElectronicsHP4195A is NOT fixed

www.avalontest.com has fixed the 25MHz oscillation.  Contact: Jim Burnham 760-536-0191

Actually, NOT FIXED.

  3808   Thu Oct 28 09:16:17 2010 steveUpdatePEMwelding in the vertex area

Fire-smoke sensors in the vertex area #2-31, 2-30 east, 2-32 south/MC2 and 2-37 old control room area are turned off to accommodate the welding

activity of folding crane. These sensors will be reactivated at 3:30pm today.

Stay out of the 40m lab: IFO room till 6 pm today.

  3810   Thu Oct 28 13:01:34 2010 steveUpdatePEMcrane repair guys left for the day

Quote:

Fire-smoke sensors in the vertex area #2-31, 2-30 east, 2-32 south/MC2 and 2-37 old control room area are turned off to accommodate the welding

activity of folding crane. These sensors will be reactivated at 3:30pm today.

Stay out of the 40m lab: IFO room till 6 pm today.

 The new cord wheel was to big. They be back tomorrow?

The lab is open.

  3832   Mon Nov 1 10:17:55 2010 steveUpdateGeneralbreakers relabelled

Pedro of the electrical shop helped to retrace wires from the racks to the breakers. Many wrong labels were replaced. These labels are  still representing                          the south arm as Y and  the east arm as X.

Racks: 1X1,2,3,4 and 1Y3,4,5,6,7 and 9 are connected through manual disconnect swithes to  AC power breaker PC-1 on the west wall of IFO room 104.

             This panel PC-1 is connected to T1 isolation transformer in room 101 Panel L - # 38, 40, 42

Racks: 1Y1 & 2  psl and mc are connected through manual disconnect switches to AC power breaker PC-2 just west of the psl enclosure.

             This panel is connected to T2 isolation transformer in room 101 Panel L - # 32, 34, 36

Attachment 1: P1060970.JPG
P1060970.JPG
Attachment 2: P1060972.JPG
P1060972.JPG
Attachment 3: P1060975.JPG
P1060975.JPG
ELOG V3.1.3-