  3594   Wed Sep 22 16:35:45 2010 josephbUpdateCDSFibers pulled, new FB install tomorrow[Aidan, Tara, Joe]
We pulled out what used to be the
LSC/ASC fiber from the 1Y3 arm rack, and
  
  3593   Tue Sep 21 16:05:21 2010 josephbUpdateCDSFirst pass at rack diagramI've made a first pass at a rack diagram
for the 1X1 and 1X2 racks, attached as png.
Gray is old existing boards, power
 1X1_1X2_racks.png 
  3592   Tue Sep 21 15:33:02 2010 steveMetaphysicsTreasureWagonga alartJohn Miller has arrived from Australia
with 3 bags of  Wagonga Coffee. Trade
bargaining has started on
 P1060866.JPGP1060872.JPG 
  3591   Mon Sep 20 17:10:10 2010 steveConfigurationPSL enclosure beam guides to IFO are installed The PSL out  2" OD beam guide
tube was cut  1.5" shorter to 13.5"
The 10" OD  0.25"
  
  3590   Mon Sep 20 16:59:26 2010 josephbUpdateCDSMegatron in 1X2 rack, to be come c1ioo[Rana, Koji, Joe]
We pulled the phase shifters in the
1X2 rack out to make room for megatron. 
  
  3589   Mon Sep 20 11:39:45 2010 josephbUpdateCDSSwitch overI talked to with Alex this morning, discussing
what he needed to do to have a frame builder
running that was compatible with the new
  
  3588   Mon Sep 20 10:33:21 2010 josephbBureaucracyComputersLarry stopped by - GC machine had conflicting IPLarry stopped by today and had to disconnect
the m25 machine (this is the 1st GC machine
on the left as you walk into the control
  
  3587   Sun Sep 19 18:52:52 2010 ranaConfigurationPSLNPRO SLOW servo settings updated for Innolight NPROOur new 2W Mephisto has a pretty zippy
"SLOW" temperature input. Tuning
the perl PID servo, I found that the best
 Untitled.png 
  3586   Sun Sep 19 18:09:09 2010 ranaConfigurationCamerasBlue IP Camera installed on the PSL table   Untitled.png 
  3585   Fri Sep 17 17:35:35 2010 steveUpdatePEMcleaned up at 1Y1 PSL rackCleaned up cables on the top and bottom.
Vacuumed both areas. We still have some remaining
shading from the MOPA umbilical and more
  
  3584   Fri Sep 17 14:55:01 2010 josephbUpdateCDSTook 5565 RFM card from IOVME to place in the new IOO chassisI took the 5565 RFM card out of the IOVME
machine to so I could put it in the new IO
chassis that will be replacing it. 
  
  3583   Fri Sep 17 12:11:42 2010 josephbUpdateCDSDowns updateIn doing a re-inventory prior to the IOO
chassis installation, I re-discovered we
had a missing interface board that goes in
  
  3582   Fri Sep 17 03:32:11 2010 KojiUpdateSUSArrangement of the SUS towersThe day before yesterday, I was cleaning
a flow bench in the clean room.
I found that one SOS was standing
  
  3581   Fri Sep 17 03:06:06 2010 KojiUpdateSUSSOS sent for bakingTwo SOS suspensions for the ETMs were
disassembled and packed for cleaning and
baking by Bob.
 IMG_3596.jpgIMG_3597.jpg 
  3580   Fri Sep 17 01:36:14 2010 valeraUpdate PMC line widthThe attached plots show the PMC cavity
line width measurement with 1 mW and 160
mW into the PMC. The two curves on each plot
 TEK00009.PNGTEK00010.PNG 
  3579   Wed Sep 15 19:29:13 2010 valeraSummary PSL power budget
    
        

            Location
  
  3578   Wed Sep 15 16:12:35 2010 koji, steveUpdateMOPAMOPA Controller is taken out of the PSL rackWe removed the Lightwave MOPA Controller,
PA#102, NPRO206 power supply to make room
for the IOO chassy at 1X1 (south) rack.
 P1060843.JPG 
  3577   Wed Sep 15 16:00:26 2010 koji, steveUpdateMOPA We removed the Lightwave MOPA Controller
from 1X1 (south)  It was a real painfully
messy job to pull out the umbilical.
  
  3576   Wed Sep 15 14:34:57 2010 josephbSummaryCDSPlan for RFM switch overSteps for RFM switch over:
1) Ensure the new frame builder code
is working properly:
  
  3575   Wed Sep 15 03:08:26 2010 KojiUpdatePSLFSS lockingBrilliant! This is the VERY way
how the things are to be conquered!

  
  3574   Wed Sep 15 01:58:28 2010 valeraUpdatePSLFSS lockingThe RefCav is locked and aligned. I changed
the fast gain sign by changing the jumper
setting on the TTFSS board. The RefCav visibility
 DSC_2510.JPG 
  3573   Wed Sep 15 01:27:52 2010 rana, steve, valeraUpdatePSLFSS cables connected- connected the TTFSS cables (FSS fast
goes directly to NPRO PZT for now)
- measured the reference cavity 21.5
  
  3572   Tue Sep 14 18:07:41 2010 AlbertoUpdateElectronicsFrequency Box Documentation Added to the SVNI completed a LIGO document describing
design, construction and characterization
of the RF System for the 40m upgrade.
  
  3571   Tue Sep 14 00:21:51 2010 ranaOmnistructureEnvironmentOffice area temperature changeI changed the setpoint for the HVAC control
(next to Steve) from 73F to 72F. This is
to handle the temperature increase in the
  
  3570   Mon Sep 13 22:51:07 2010 tara,valeraConfigurationPSLbeam scan for RCAVOn Friday, Valera and I calculated the
modematching for reference cavity from AOM.
We scan the beam profile where the
 2010_09_10_w.mat 
  3569   Mon Sep 13 21:52:53 2010 kiwamuUpdateGreen Lockingthe X end laser is ON
 I turned ON the laser
at the X end station, which had
  
  3568   Mon Sep 13 19:41:38 2010 ranaUpdatePSLFSS AOM alignmentThe IR sensitive Olympus 570 camera gives
us a really nice view of these IR beams.
Its actually a lot better than what you can
  
  3567   Mon Sep 13 12:09:42 2010 kiwamuSummaryGeneralelog restarted Elog didn't respond, so I restarted
it with the script.
Before killing the process somehow
  
  3566   Mon Sep 13 11:49:34 2010 kiwamuUpdatePSLmode matching from PMC to IMCI have been working on the mode matching
lenses which are sitting after the boradband
EOM.
 psl_mmt1.pngnewMM.png 
  3565   Mon Sep 13 11:40:50 2010 AlbertoUpdateElectronicsFrequency Box Documentation Added to the SVNI uploaded all the material about the RF
frequency Generation Box  into the SVN under
the path:
 freqBoxSVNdierctoryStructure.png 
  3564   Mon Sep 13 10:22:48 2010 josephbUpdateCDSRCG bugs/feature request wiki pageI've started a wiki page under the Upgrade
09/New CDS section regarding known bugs and
pending feature requests for the Real Time
  
  3563   Mon Sep 13 02:45:59 2010 ranaConfigurationDMFseisBLRMS restartsI restarted the seisBLRMS DMF monitor by
ssh'ing into mafalda and starting up a matlab
session. I also have started a StripTool
  
  3562   Mon Sep 13 00:19:32 2010 ranaUpdate VCO Driver Output power v. slider control voltageI measured the RF power output of the VCO
Driver box as a function of slider value.
I measured using the Gigatronics Handheld
 vco.png 
  3561   Sun Sep 12 23:16:52 2010 valeraUpdate FSS mode matchingThe attached plot shows the beam scans
of the beam leaking from the back mirror
of the PMC to the BS cube that first turns
 fss.pdffssaom-abcd.tifffssrc-abcd.tiff 
  3560   Sun Sep 12 23:02:53 2010 valeraUpdate PMC mode matchingKiwamu and I found that the first lens
in the PMC mode matching telescope was mislabeled.
It is supposed to be PLCX-25.4-77.3-C and
 pmc.pdfpmc-abcd.tiff 
  3559   Sun Sep 12 22:36:03 2010 ranaConfigurationComputersrossa notesI found Sanjit's instructions for doing
the Nvidia settings too complicated and so
I followed these instructions from Facebook:
  
  3558   Sat Sep 11 22:42:07 2010 valeraUpdatePSLPSL update- The PMC REFL PD was moved from the temporary
location to the one called for by the PSL
layout (picture attached). The leakage beams
 DSC_2502.JPGDSC_2505.JPG 
  3557   Sat Sep 11 03:16:51 2010 ranaConfigurationComputersrossa notesI wiped out the old CentOS install on rossa
and installed CentOS 5.5 on there. The DVDs
are on a spindle in the control room; there
  
  3556   Fri Sep 10 02:35:30 2010 rana, kiwamu, valera, taraConfigurationPSLupdateOver the last couple nights we got the
beam into the FSS path and all the way to
the IMC and out onto the AP table.
 40mPSL.pdf 
  3555   Thu Sep 9 18:53:56 2010 AlbertoConfigurationElectronicsBusby Box, Rai's Box, SR554 in the RF cabinetI stored the Busby Box, the Rai's Box and
the SR554 preamp in the RF cabinet down the
Y arm.
  
  3554   Thu Sep 9 16:54:56 2010 ranaUpdateSAFETYmain laser is back ONI turned off the laser last night to protect
against the electricians. but failed to elog
it. I accept the burnt toast completely.
  
  3553   Thu Sep 9 14:42:40 2010 josephbUpdateCDSUpdating suspensions modelI've been working on updating the suspensions
model, incorporating Koji's refinements as
well as trying to simplify the model and
 SingleSUS.png 
  3552   Thu Sep 9 12:02:03 2010 AlbertoUpdateElectronicsFrequency Generation Box - Amplitude Noise MeasurementsI measured the amplitude noise of the source
outputs and the EOM outputs of the Frequency
Generation box.
 FreqBoxAmplitudeNoiseMeasurementSetup.pngFreqBoxAmplitudeNoise_BusbyBox_AllChannels.png 
  3551   Thu Sep 9 11:31:54 2010 steveUpdatePEMaccelerometer cable connectionI turned off/on the power to the accelerometers
in order to re rout their connections. I
found cable connector body-nut  #3 loose
  
  3550   Thu Sep 9 11:17:15 2010 steveUpdateSAFETYmain laser is back ON


   
        
            
 P1060813.JPGP1060814.JPGP1060816.JPG 
  3549   Thu Sep 9 08:23:45 2010 steveUpdateSAFETYmain laser turned offInnolight 2W 1064nm main laser was turned
off for more enclosure related work.
The electrician re rooting the power-
  
  3548   Thu Sep 9 05:58:04 2010 kiwamuUpdatePSLmode matching from PMC to IMC I started mode matching of the
beam going to IMC. The work is still going
on.
  
  3547   Wed Sep 8 16:17:58 2010 steveUpdatePEMparticle counter problemI played with the particle counter this
morning. Now it's running and reading the
correct numbers on the old COCHECKLIST.adl
  
  3546   Wed Sep 8 14:44:37 2010 josephbUpdateCDSUpdated parse_mdl_to_ipc.py and feCodeGen.plI updated parse_mdl_to_ipc.py to correctly
work with the 3 new cdsIPCx parts, namely
cdsIPCx_PCIE (for dolphin connections), cdsIPCx_RFM
  
  3545   Wed Sep 8 11:56:24 2010 kiwamuSummaryCDSSeptember CDS test plan Joe and Kiwamu
We discussed about our CDS plan for
this September. The summary of the plan
  
ELOG V3.1.3-