40m QIL Cryo_Lab CTN SUS_Lab TCS_Lab OMC_Lab CRIME_Lab FEA ENG_Labs OptContFac Mariner WBEEShop
  40m Log, Page 169 of 344  Not logged in ELOG logo
ID Date Authorup Type Category Subject Text Attachments
  4954   Thu Jul 7 14:27:16 2011 SureshUpdateIOOsomething wrong ? : Power incident on REFL11 and REFL55Just tying up a loose end.  The next
day Kiwamu and I checked to see what the
trouble was.  We concluded that the
  
  4957   Fri Jul 8 19:50:19 2011 SureshUpdateRF SystemLSC rack channel assignment[Jamie, Suresh]
   We looked at the ADC
channel assignments in the LSC model and
 1Y2_Rack_Layout.png 
  4990   Tue Jul 19 13:45:22 2011 SureshUpdateSAFETYPainful Voltage Regulator and Circuit-Testing LessonsThere is should be a few IDC connectors
in the lab (and some ribbon cable) using
which you can proceed with the testing of
  
  4994   Wed Jul 20 06:17:04 2011 SureshUpdateGreen LockingY-end green laser power issuesThe Y-end green beam power is 0.47 mW.
While
aligning the Y-end aux laser light into the
fiber we noticed that the green power out
 Y-end_table_powers.pdfY-end_table.png 
  4995   Wed Jul 20 06:36:39 2011 SureshUpdateIOOWFS1 and 2 gainsGains of individual quadrants in both
the WFS
As a simple check of the
gains on all the quadrants I hooked up the
 WFS1_7kHz_105Hz.pdfWFS2_7kHz_105Hz.pdf 
  4996   Wed Jul 20 06:52:01 2011 SureshUpdateLSCABSL - PSL beat lockThe ABSL locking setup to the PSL is down. 
According
the plan, I started to use the IR beam dumped
after the doubling crystal for the IR beat
  
  5009   Wed Jul 20 23:31:44 2011 SureshUpdateIOOMC Trans QPD is down 
The
mode cleaner is not locking because
  
  5021   Sat Jul 23 02:24:10 2011 SureshUpdateIOOrestarted the frame builderI restarted the fb twice during the last
15mins.   This was after I added
test points into the C1IOO/WFS1.mdl and C1IOO/WFS2.mdl.
  
  5041   Wed Jul 27 08:59:10 2011 SureshUpdateLSClocking status I had to realign PSL beam into the
MC in order to reobtain the MC lock. 
We lost lock at sometime around 8:30 AM on
 MC_RFPD_DCMon.png 
  5042   Wed Jul 27 10:04:29 2011 SureshUpdateIOOWFS transfer function measurementsThis is part of the WFS activity. 
So far I have completed the following tasks:
1)  I fixed the 
 WFS_TF_Phase_Sheet1.png 
  5066   Sat Jul 30 05:11:45 2011 SureshUpdateGreen LockingY- end table clean-upThe optics on the Y-end table which required
to be moved have been repositioned. 
 Y-end_table_work.png 
  5115   Thu Aug 4 01:49:08 2011 SureshUpdateIOOMC is lockedI measured the power transmitted from the
PSL to the MC.
It is 19mW.
  
  5130   Sat Aug 6 03:10:05 2011 SureshSummaryGeneralSummary of today's in-vacuum workThe table below gives the OSEM positions
as seen on the slow chanels C1:SUS-ETMX_{UL,UR,LL,LR,SD}PDMon
 ETMX_OSEMs.pngAfter_osem_adjustment.JPGBefore_osem_adj.JPG 
  5132   Sun Aug 7 11:10:54 2011 SureshSummaryGeneralOSEM positioning
  
  5146   Tue Aug 9 01:35:45 2011 SureshUpdateSUSETMX Side Sensor slow channel down for a long timeThe slow signal from the side sensor on
ETMX was last seen in action sometime in
May 2010!  And then the frame builder
 ETMX-SDSEN_trend1.pngETMX_SDSEN_trend2.png 
  5150   Tue Aug 9 02:44:32 2011 SureshUpdateSUSETMX free swinging dataI switched off damping to the ETMX and
used a reduced version of  freeswing-all.csh
script (called freeswing-ETMX.csh) to set
 ETMX_freeswing.png 
  5167   Wed Aug 10 11:22:55 2011 SureshUpdateIOOMC A2L alignment[Kiwamu, Suresh]
We attempted to minimise the A2L
coupling in the MC mirrors (centering the
  
  5182   Thu Aug 11 04:45:07 2011 SureshUpdateIOOAligning the 1064nm beam with the in-vacuum pzt's[Kiwamu, Suresh]
We worked on the beam path from MC
to BS this evening. 
 FI_input_spot.jpg 
  5199   Thu Aug 11 19:01:45 2011 SureshUpdateSUSITMX given a kick to start it freeswing' but to no avail.We started an ITMX freeswing run at this
time
Thu Aug 11 18:58:59 PDT 2011
  
  5266   Fri Aug 19 01:15:22 2011 SureshUpdateSUSFreeSwing all opticsI ran "freeswing all" at Fri
Aug 19 01:09:28 PDT 2011 (997776583) 
and "opticshutdown"  as well.
  
  5267   Fri Aug 19 01:46:06 2011 SureshUpdateGeneralIFO alignment[Keiko, Jamie, Kiwamu, Anamaria,
We followed the procedure that we
laid-out in our elog
  
  5277   Mon Aug 22 16:28:44 2011 SureshUpdateGeneralSRM tower shifted on Friday[Kiwamu,
Suresh]   This is a belated elog
entry from last Friday night + Saturday morning! 
  
  5283   Tue Aug 23 02:03:04 2011 SureshUpdateIOOMC realigned and spot positions recenteredAfter the MC1 and MC3 OSEMs were 
repositioned 
MC had to be realigned and the beam spots
 mcdecenter20110822.png 
  5305   Thu Aug 25 17:57:35 2011 SureshUpdateSUSBroken UL magnet on ITMX
  
  5313   Sat Aug 27 20:38:17 2011 SureshUpdateIOOLight is back on WFS[Valera, Suresh]
   We wanted to continue
the work with WFS servo loops.  As the
  
  5315   Sun Aug 28 22:49:40 2011 SureshUpdateCDSfb downI recompiled c1ioo after making some changes
and restarted fb. (about 9:45 - 10PM PDT) 
But it failed to restart.  It responds
  
  5321   Mon Aug 29 19:14:31 2011 SureshUpdateIOOWFS phase adjustments[Valera, Suresh]
1) To see if there are significant
dark-offsets on the WFS sensors we closed
 Screenshot-1.png 
  5327   Tue Aug 30 17:31:55 2011 SureshUpdateIOOC1IOO model reverted and fb restartedI reverted
the C1IOO model to the last working version
and restarted the fb at this time..Tue Aug
  
  5344   Tue Sep 6 17:43:01 2011 SureshUpdateIOOFree Swing ITMY startedFree swing of ITMY started at
Tue Sep  6 17:41:43 PDT 2011
 
  
  5351   Wed Sep 7 00:01:23 2011 SureshUpdateIOOITMY chamber ready for heavy doors[Jenne, Suresh]
We did the following things in the
ITMY chamber today:
  
  5362   Wed Sep 7 20:44:11 2011 SureshUpdateelogrestartedElog crashed / dormant for long time. 
A look at the log file indicated that it
was busy generating png thumbnails for pdf
  
  5390   Mon Sep 12 23:45:14 2011 SureshConfigurationComputer Scripts / ProgramsStripTool does not scale properly on PianosaWhen I run StripTool on Pianosa, I get
the following message
==== StripTool Xt Warning Handler
  
  5393   Tue Sep 13 09:16:00 2011 SureshUpdateIOOMC spots recentered and input beam alignedThe shift of MC2 which Rana noted
caused the beam spots on the MC mirrors to
decenter. I used the mcassUp and mcassOn
 mcdecenter20110912_1.pngmcdecenter20110912_2.png 
  5396   Tue Sep 13 19:04:58 2011 SureshUpdateComputer Scripts / ProgramsRestarted Frame builder several times while compiling c1ioo, c1mcs and c1rfmI restarted the frame builder at the following
times
 
  
  5397   Tue Sep 13 19:12:53 2011 SureshUpdateComputer Scripts / Programschanges to the c1ioo, c1mcs and c1rfm[Suresh, Jamie]
The new versions of these three models
have been committed to the svn.  I copy
  
  5416   Thu Sep 15 11:37:24 2011 SureshUpdateComputer Scripts / Programsfb restarted at Thu Sep 15 11:30:30 PDT 2011I changed a filter bank name (C1IOO-WFS1_PIT)
in c1ioo model reverting it to its earlier
name.  Had to restart c1ioo model and
  
  5433   Fri Sep 16 14:43:43 2011 SureshUpdateComputer Scripts / ProgramsChanged c1ioo model and restarted fbI had to change the c1ioo model and restart
the fb since the paths allowing us to select
various signals to demodulate using the lockins
  
  5490   Tue Sep 20 21:13:39 2011 SureshUpdateIOOMC aligned and PSL beam into MC readjustedThis morning after Kiwamu maximised the
PSL beam coupling into the MC we noticed
that the MC2 face camera showed the spot
  
  5505   Wed Sep 21 19:20:41 2011 SureshUpdateIOOPSL beam into MC was off in Pitch. Readjusted.I found the PSL beam into the MC off in
pitch by large amount.  I readusted
the PSL beam for optimal coupling.
  
  5524   Thu Sep 22 22:53:06 2011 SureshUpdateComputer Scripts / ProgramsActivated DAQ channels in C1IOO model and restared fbTo look at the WFS servo signals I was
using test points in the servo filter banks. 
This is not recommended for regular operation
  
  5526   Thu Sep 22 23:02:15 2011 SureshUpdateIOOno light on WFS2. Realigned input onto both WFSRana noticed that the sum on WFS2 was about
10 times smaller than that on WFS1. Though
the beam appeared centered on the DC QPD
  
  5527   Thu Sep 22 23:10:07 2011 SureshUpdateIOOproposed modifications to the C1IOO modelRana advised that we put in a lockin-output
matrix which will allow us to excite any
combination of MC mirrors so that we can
  
  5533   Fri Sep 23 18:00:54 2011 SureshUpdateIOOPSL beam realigned to MCI noticed that the beam centering on the
WFS had changed over night and the MC_TRANS_SUM
was about 40k counts.  When well aligned
 trend.png 
  5555   Tue Sep 27 09:47:52 2011 SureshUpdateAdaptive FilteringPlan for making MC_F


   
        
            
  
  5566   Wed Sep 28 15:33:58 2011 SureshUpdateComputer Scripts / Programsediting database files for medm screens and restarting the slow c1psl machineI changed the names on a switch(SW1) in
the C1:PSL-FSS screen.  To do this I
had to edit the psl.db database file in the
  
  5581   Fri Sep 30 03:36:19 2011 SureshUpdateComputer Scripts / ProgramsCIOO modified, but not yet compiledI have added a switch in series with the
WFS_GAIN. And I have also added a LKIN_OUT_MATRX
between the lockin-outputs and the MC suspensions. 
  
  5606   Mon Oct 3 20:02:59 2011 SureshUpdatePSLAM / PM ratio[Koji, Suresh]
In the previous measurement, the
PDA 255 had most probably saturated at DC,
  
  5614   Tue Oct 4 15:57:30 2011 SureshUpdateIOOMC Trans channels are digital 0
I thought this problem might be arising
because the MC2_TRANS QPD signals are not
being passed from the c1mcs to c1ioo models
  
  5615   Tue Oct 4 16:10:45 2011 SureshUpdateComputer Scripts / ProgramsMC was not dampingThe MC was not damping earlier this morning
around 11:45AM.  The reason was that
the INMATRIX on all the three MC1, 2 and
  
  5616   Tue Oct 4 16:58:45 2011 SureshUpdatePSLAM / PM ratioCorrection:        Koji noted that Mirko
actually reports a PM modulation index of
0.17 for the 11 MHz sideband (
  
ELOG V3.1.3-