  9397   Fri Nov 15 14:08:13 2013 manasaUpdatePSLPSL Innolight shuts down again

Quote:

I have just turned on the PSL Innolight laser. The laser shut down  with unknown reason a day ago.

PSL NPRO shut down again today for reasons unknown. I was working near the IOO rack and noticed there was no light at both the refl and trans PMC cameras. Jenne and I checked the PSL and found the 'OFF' red switch on the laser driver lit up. Switching ON the green button brought the laser back. PMC and MC autolocked after this.

  9396   Fri Nov 15 13:26:00 2013 JenneUpdateCDSAUXEY is back

Quote:

Quote:

Please just try rebooting the vxworks machine.  I think there is a key on the card or create that will reset the device.  These machines are "embeded" so they're designed to be hard reset, so don't worry, just restart the damn thing and see if that fixes the problem.

 This is what I remember doing all the time when Rob was around, but with all the new computers, I forgot whether or not this was allowed for the slow computers.

Anyhow, I went down there and keyed the crate, but auxey isn't coming back.  I'll give it a few more minutes and check again, but then I might go and power cycle it again.  If that doesn't work, we may have a much bigger problem.

 I went and keyed the crate again, and this time the computer came back.  I burt restored to Nov 10th.  ETMY is damping again.

  9395   Fri Nov 15 12:38:50 2013 JenneUpdateCDSCan't talk to AUXEY?

Quote:

Please just try rebooting the vxworks machine.  I think there is a key on the card or create that will reset the device.  These machines are "embeded" so they're designed to be hard reset, so don't worry, just restart the damn thing and see if that fixes the problem.

 This is what I remember doing all the time when Rob was around, but with all the new computers, I forgot whether or not this was allowed for the slow computers.

Anyhow, I went down there and keyed the crate, but auxey isn't coming back.  I'll give it a few more minutes and check again, but then I might go and power cycle it again.  If that doesn't work, we may have a much bigger problem.

  9394   Fri Nov 15 12:00:28 2013 KojiUpdateCDSCan't talk to AUXEY?

Quote:

Please just try rebooting the vxworks machine.  I think there is a key on the card or create that will reset the device.  These machines are "embeded" so they're designed to be hard reset, so don't worry, just restart the damn thing and see if that fixes the problem.

 Don't forget to run burtrestore for the target.

  9393   Fri Nov 15 10:49:55 2013 jamieUpdateCDSCan't talk to AUXEY?

Please just try rebooting the vxworks machine.  I think there is a key on the card or create that will reset the device.  These machines are "embeded" so they're designed to be hard reset, so don't worry, just restart the damn thing and see if that fixes the problem.

  9392   Fri Nov 15 10:31:45 2013 SteveUpdateISSSR560 ISS loop connection

Quote:

Quote:

We have implemented an SR560-based ISS loop using the AOM on the PSL table. This is a continuation of the work in 40m:9328.

We dumped the diffracted beam from the AOM onto a stack of razor blades. This beam is not terribly well separated from the main beam, so the razor blades are at a very severe angle. Any alternatives would have involved either moving the AOM or attempting to dump the diffracted beam somewhere on the PMC refl path. We trimmed the RF power potentiometer on the driver so that with 0.5 V dc applied to the AM input, about 10% of the power is diverted from the main beam.

We ran the PMC trans PD into an AC-coupled SR560. To shape the loop, we set SR560 to have a single-pole low- pass at 300 Hz and an overall gain of 5×104. We take the 600 Ω output and send it into a 50 Ω feed-through terminator; this attenuates the voltage by a factor of 10 or so and thereby ensures that the AOM driver is not overdriven.

The AOM driver's AM input accepts 0 to 1 V, so we add an offset to bias the control signal. The output of the 50 Ω feedthrough is sent into the 'A' input of a second SR560 (DC coupled, A − B setting, gain 1, no filtering). Using a DS345 function generator, a 500 mV offset is put into the 'B' input (the function generator reads −0.250 V because it expects 50 Ω input). The 50 Ω output of this SR560 is sent into the AOM driver's AM input.

A measurement of suppressed and unsuppressed RIN is attached. We have achieved a loop with a bandwidth of a few kilohertz and with an in-loop noise suppression factor of 50 from 100 Hz to 1 kHz. This measurement was done using the PMC trans PD, so this spectrum may underestimate the true RIN.

 A small followup measurement. Here are spectra of the MC trans diode with and without the ISS on. The DC value of the diode (in counts) changed from 17264.2 (no ISS) to 17504.3 (with ISS), but I didn't account for this change in the plot.

There is a small inkling of benefit between 100Hz and 1kHz. Above about 100Hz, the RIN is suppressed to about the noise level of this measurement. Below 100Hz there is no change, which probably means that power fluctuations are introduced downstream of the AOM, which argues for an outer-loop ISS down the road.

Atm #2 is in units of RIN.

 I have disconnected the cable from the SR560 to LSC -ch8 for 15minutes this morning. It is moved from the floor to the top of the chambers as preparation for 40m tour. The SR560 seems to be overloading.

The  ISS servo is off according to the MEDM screen. Why MC-T plot showing zero?  The MC was happy yesterday.

 

Attachment 1: ISS.png
ISS.png
  9391   Fri Nov 15 10:19:26 2013 manasaUpdateCDSCan't talk to AUXEY?

Quote:

 

 This problem is now worse - the sliders on IFO_ALIGN for ETMY are white.  I can't telnet to the machine either, although auxex works okay.  Rather, it looks like maybe I'm getting to auxey, but then I'm immediately booted.  I can ping both c1auxex and c1auxey with no problem.
 

Heeeeelllp please.  Is this just a "shut off, then turn back on" problem?  I'm wary of hard rebooting things, with all the warnings and threats in the elog lately.  I've sent an email to Jamie to ping him.

There are some vague instructions in the wiki, but they begin at doing the burt restores, not actually restarting the computers: wiki  Back in July, elog 8858 was written, from which the wiki instructions seem to be based.  But in the elog it says "...went to the /cvs/cds/caltech/target/ area and started to (one by one) inspect all of the targets to see if they were alive.", but I don't know what "inspected" means in this case.  I probably should, since I've been here for something like a millennia, but I don't.

 

This is what was done (as I recollect) when we said "inspected":Tenet into the computer, ping them and look at the status. Since c1auxey is not responding, here is how c1auxex responds.

controls@rossa:/cvs/cds/caltech/target 0$ telnet c1auxex
Trying 192.168.113.59...
Connected to c1auxex.martian.
Escape character is '^]'.

c1auxex > h
  1  i
  2  -help
  3  --help
  4  h
  5  2
  6  h
  7  -help
  8  i
  9  h
value = 0 = 0x0
c1auxex > i

  NAME        ENTRY       TID    PRI   STATUS      PC       SP     ERRNO  DELAY
---------- ------------ -------- --- ---------- -------- -------- ------- -----
tExcTask   _excTask       fde244   0 PEND          87094   fde1ac   3006b     0
tLogTask   _logTask       fdb944   0 PEND          87094   fdb8a8       0     0
tShell     _shell         ddad00   1 READY         6d974   dda9c8  3d0001     0
tRlogind   _rlogind       fbc11c   2 PEND          2b604   fbbdf4       0     0
tTelnetd   _telnetd       fba278   2 PEND          2b604   fba1a8       0     0
tTelnetOutT_telnetOutTa   db7578   2 READY         2b604   db72e0       0     0
tTelnetInTa_telnetInTas   db6060   2 READY         2b5dc   db5d68       0     0
callback   _callbackTas   f7941c  40 PEND          2b604   f793d4       0     0
scanEvent  ee7ca8         ecacb4  41 PEND          2b604   ecac6c       0     0
tNetTask   _netTask       fd75b8  50 READY         6be6c   fd7550       0     0
scanPeriod ee78f8         ecd554  53 READY         6d192   ecd508       0     0
scanPeriod ee78f8         f23e48  54 DELAY         6d192   f23dfc       0     6
tFtpdTask  _ftpdTask      fb7848  55 PEND          2b604   fb778c       0     0
scanPeriod ee78f8         f266e8  55 READY         6d192   f2669c       0     0
scanPeriod ee78f8         f38678  56 READY         6d192   f3862c       0     0
callback   _callbackTas   f7bcbc  57 PEND          2b604   f7bc74       0     0
scanPeriod ee78f8         f906d8  57 DELAY         6d192   f9068c       0    59
scanPeriod ee78f8         f995ac  58 DELAY         6d192   f99560       0   238
scanPeriod ee78f8         f9c908  59 DELAY         6d192   f9c8bc       0   538
callback   _callbackTas   fa4c1c  65 PEND          2b604   fa4bd4       0     0
scanOnce   ee7764         f9f96c  65 PEND          2b604   f9f92c       0     0
epicsPrint f0501c         e88fa0  70 PEND          2b604   e88f64   c0002     0
ts_Casync  ee5bae         f76b7c  70 DELAY         6d192   f76880  3d0004   178
tPortmapd  _portmapd      fb8d60 100 PEND          2b604   fb8c2c      16     0
EgRam      ea00e4         fa14ac 100 PEND          2b604   fa1458       0     0
CA client  _camsgtask     d85878 180 PEND          2b604   d85774  3d0004     0
CA client  _camsgtask     df91e8 180 PEND          2b604   df90e4       0     0
CA client  _camsgtask     d98bf4 180 PEND          2b604   d98af0       0     0
CA client  _camsgtask     e03cd0 180 PEND          2b604   e03bcc       0     0
CA client  _camsgtask     ddf2b8 180 PEND          2b604   ddf1b4       0     0
CA client  _camsgtask     faaec8 180 PEND          2b604   faadc4       0     0
CA client  _camsgtask     d79f3c 180 PEND          2b604   d79e38       0     0
CA TCP     _req_server    f305dc 181 PEND          2b604   f30540       0     0
CA repeaterf109e2         f215a8 181 PEND          2b604   f21474       0     0
CA event   _event_task    d7fe58 181 PEND          2b604   d7fe10       0     0
CA event   _event_task    d6ce5c 181 PEND          2b604   d6ce14       0     0
CA event   _event_task    dab7e0 181 PEND          2b604   dab798       0     0
CA event   _event_task    d76efc 181 PEND          2b604   d76eb4       0     0
CA event   _event_task    d9bddc 181 PEND          2b604   d9bd94       0     0
CA event   _event_task    d9a864 181 PEND          2b604   d9a81c       0     0
CA event   _event_task    da8d8c 181 PEND          2b604   da8d44       0     0
CA UDP     _cast_server   f2f064 182 READY        efcabe   f2efe4       0     0
CA online  _rsrv_online   f2d84c 183 DELAY         6d192   f2d7bc       0   265
EV save_res_event_task    de88dc 189 PEND          2b604   de8894   3006b     0
save_restor_save_restor   df61cc 190 PEND          2b604   df5c44  3d0002     0
RD save_res_cac_recv_ta   fb47d8 191 READY         2b604   fb46a4  3d0004     0
logRestart f05d42         e861c0 200 PEND+T        2b604   e86174      33  1714
taskwd     ef4d46         e85030 200 DELAY         6d192   e84f7c       0   224
value = 0 = 0x0
c1auxex >
telnet> quit
Connection closed.
controls@rossa:/cvs/cds/caltech/target 0$

  9390   Fri Nov 15 09:27:58 2013 KojiUpdateIOOWFS with beam dumps

Unfortunately this does not work. These WFSs are not the detectors which we can move freely.
In order to move the WFS detectors, we need the precise design of the Gouy phase for each WFS heads.
Without the design, we can't move the detectors.

  9389   Fri Nov 15 09:24:41 2013 SteveUpdateIOOWFS with beam dumps

This is a proposal to move WFSs such way that their reflected beam can be trapped.

Later ps: Nic will take care of the Gouy phase telescopes.

Attachment 1: MCwfsRefTraped.jpg
MCwfsRefTraped.jpg
  9388   Fri Nov 15 08:01:20 2013 SteveUpdateSUSETMY damping restored

ETMY sus damping restored

Attachment 1: ETMYsus.png
ETMYsus.png
  9387   Thu Nov 14 22:23:22 2013 JenneUpdateCDSCan't talk to AUXEY?

Quote:

The restore scripts from the IFO config screen half-failed, with this error:

retrying (1/5)...
retrying (2/5)...
CA.Client.Exception...............................................
    Warning: "Virtual circuit disconnect"
    Context: "c1auxey.martian:5064"
    Source File: ../cac.cpp line 1214
    Current Time: Wed Nov 13 2013 17:24:00.389261330
..................................................................

Jamie, do you know what this might be?  When requested, ETMY was not misaligned or restored, but we got these errors.  So, somehow we're not talking properly to EY, but other things seem fine (the models are running okay, the suspension is damped, etc, etc.)

 This problem is now worse - the sliders on IFO_ALIGN for ETMY are white.  I can't telnet to the machine either, although auxex works okay.  Rather, it looks like maybe I'm getting to auxey, but then I'm immediately booted.  I can ping both c1auxex and c1auxey with no problem.
 

Heeeeelllp please.  Is this just a "shut off, then turn back on" problem?  I'm wary of hard rebooting things, with all the warnings and threats in the elog lately.  I've sent an email to Jamie to ping him.

There are some vague instructions in the wiki, but they begin at doing the burt restores, not actually restarting the computers: wiki  Back in July, elog 8858 was written, from which the wiki instructions seem to be based.  But in the elog it says "...went to the /cvs/cds/caltech/target/ area and started to (one by one) inspect all of the targets to see if they were alive.", but I don't know what "inspected" means in this case.  I probably should, since I've been here for something like a millennia, but I don't.


controls@rossa:~ 0$ telnet c1auxey
Trying 192.168.113.60...
Connected to c1auxey.martian.
Escape character is '^]'.
Connection closed by foreign host.
controls@rossa:~ 1$ telnet c1auxex
Trying 192.168.113.59...
Connected to c1auxex.martian.
Escape character is '^]'.

c1auxex >
telnet> ^]
?Invalid command
telnet> exit
?Invalid command
telnet> quit
Connection closed.
controls@rossa:~ 0$ telnet c1auxey
Trying 192.168.113.60...
Connected to c1auxey.martian.
Escape character is '^]'.
Connection closed by foreign host.
  9386   Thu Nov 14 14:35:12 2013 SteveUpdateSUSIR effect on MC and PRM sensors

 Sorry to say but MC1, MC2, MC3 and PRM face OSEMS are having the same problem of leaking IR into the sensors

The PMC was not locked for 11 minutes on this plot.

 

Attachment 1: MC_PRM_IReffect.png
MC_PRM_IReffect.png
  9385   Thu Nov 14 14:27:51 2013 nicolasOmnistructureGeneralSR785 Analyzer CRT replaced

 The 785 analyzer in the 40 had a wonky hard to read screen. I was hoping that a new white CRT would fix all the problems. 

I installed a white CRT, which didn't fix the wonkyness, but I adjusted the CRT position, brightness, focus settings to make the screen somewhat more readable.

BEFORE:

IMG_20131114_125728.jpg

AFTER:

IMG_20131114_141425.jpg

If we want to send the thing in for service to fix the wonkyness, we should probably hold on to the old CRT because they will probably replace the whole screen assembly and we'll lose our white screen.

  9384   Thu Nov 14 11:41:19 2013 SteveUpdateSUSPRM sensors effected by IR

 IR off for 11 minutes. The PRM  face sensors are effected. The PRM side and the rest of the SUS OSEMS are not effected.

 

Attachment 1: IRon_off.png
IRon_off.png
  9383   Thu Nov 14 02:55:26 2013 ranaUpdateSUSPRM motion correlated to intracavity power

 

Some more words about the ISS -> OSEM measurement:

The calibration of the OSEMs have been done so that these channels are each in units of microns. The SIDE channel has the lower noise floor because Valera increased the analog gain by 5x some time ago and compensated with lower digital gain.

The peak heights in the plot are:

UL   0.85

LL   0.78

UR   0.61

LR   0.45

S    0.27

So that tells us that the coupling is not uniform, but mostly coming in from the left side (which side is the the SIDE OSEM on?).

Jenne and I discussed what to do to mitigate this in the loops. Before we vent to fix the scattering (by putting some covers around the OSEMs perhaps), we want to try to tailor the OSEM damping loops to reduce their strength and increase the strength of the OL loops at the frequencies where we saw the bulk of the instability last time.

Jenne is optimizing OL loops now, and I'm working on OSEM tweaking. My aim is to lower the overall loop gains by ~3-5x and compensate that by putting in some low Q, resonant gain at the pendulum modes as we did for eLIGO. We did it here at the 40m several years ago, but had some troubles due to some resulting instability in the MC WFS loops.

 

In parallel, Steve is brainstorming some OSEM shields and I am asking around LIGO for some AC OSEM Satellite modules.

  9382   Thu Nov 14 02:50:43 2013 JenneUpdateLSCPRM oplev measured and modeled TF

In the process of figuring out what we can do to fix our PRM motion problem, I am looking at the PRM oplev. 

Eventually (as in, tomorrow), I'd like to be able to simulate some optic motion as a result of an impulse, and see what the oplev loops do to that motion.  (For starters, I'll take the impulse response of the OSEM loop as my time series that the oplev loop sees).

One thing that I have done is look at the oplev model that Rana put together, which is now in the noisebudget svn: /ligo/svncommon/NbSVN/aligonoisebudget/trunk/OpLev/C1

This script plots the open loop gain of the modeled oplev:

PRM_OL_TF_model.png

This should be compared to the pitch and yaw measured transfer functions:

 PRM_OLPIT_TF.pdf

PRM_OLYAW_TF.pdf

In the YAW plot, there are 2 transfer functions.  The first time around, the UGF was ~2.5Hz, which is too low, so I increased the gain in the C1:SUS-PRM_OLYAW filter bank from -3 to -9. 

The shapes of the measured and modeled transfer functions look reasonably similar, but I haven't done a plot overlay.  I suspect that the reason I don't see the same height peak as in the model is just that I'm not taking a huge number of points.  However, if the other parts of the TF line up, I'll assume that that's okay.

I want to make sure that the modeled transfer function matches the measured ones, so that I know I can trust the model.  Then, I'll figure out how to use the time series data with the simulated loop.  Ideally, I'd like to see that the oplev loop can fully squish the motion from the OSEM kicks.  Once I get something that looks good (by hand-tweaking the filter shape), I'll give it a try in the actual system.  We should, as soon as I get the optimal stuff working, redo this in a more optimal way.  Both now, and after I get an optimal design, I'll look at the actual step and impulse responses of the loop, to make sure there aren't any hidden instabilities.

Other thoughts for the night:

Rana suggests increasing the gain in some of the oplev QPD heads (including PRM), so that we're getting more than a few hundred counts of power on each quadrant.  Since our ADCs go to 32,000 counts, a few hundred is very small, and keeping us close to our noise limits.

Also, just an observation, but when I watch the REFL camera along with POP and AS, it's clear that the PRM is getting kicked, and I don't have the ETMs aligned right now, so this is just PRMI flashes.  There is also a lot of glow in the BS chamber during flashes (as seen on the PRM face video camera).

  9381   Thu Nov 14 00:33:37 2013 ranaConfigurationPSLPMC LO is dying...

Back in 2009, Jenne replaced the PMC board mixer with a Level 13 one. Today I noticed that the LO level on the PMC screen was showing a LO level of ~5-10 dBm and fluctuating a lot. I think that it is related to the well known failure of the Mini-Circuits ERA-5SM amplifier which is on the D000419-A schematic (PMC Frequency Reference Card). The Hanford one was dying for 12 years and we found it in late 2008. If we don't have any in the blue bin, we should ask Steve to order 10 of them.

The attached trend shows 2000 days of hour trend of the PMC LODET channel. The big break in 2009 is when Jenne changed the mixer and then attenuated the input by 3 dB. The slow decay since then is the dying amplifier I guess.

Since the LOCALC channel was not in the trend, I added it to the C0EDCU file tonight and restarted the FB DAQD process. Its now in the dataviewer list.

I went out and took out the 3 dB attenuator between the LO card and the PMC Mixer. The LO monitor now reads 14.9 dBm (??!!). The SRA-3MH mixer data sheet claims that the mixer works fine with an LO between 10 and 16 dBm, so I'll leave it as is. After we get the ERA-5, lets fix the LODET monitor by upping its gain and recalibrating the channel.

Attachment 1: Untitled.png
Untitled.png
  9380   Wed Nov 13 20:02:12 2013 Nic, EvanUpdateISSSR560 ISS loop

Quote:

We have implemented an SR560-based ISS loop using the AOM on the PSL table. This is a continuation of the work in 40m:9328.

We dumped the diffracted beam from the AOM onto a stack of razor blades. This beam is not terribly well separated from the main beam, so the razor blades are at a very severe angle. Any alternatives would have involved either moving the AOM or attempting to dump the diffracted beam somewhere on the PMC refl path. We trimmed the RF power potentiometer on the driver so that with 0.5 V dc applied to the AM input, about 10% of the power is diverted from the main beam.

We ran the PMC trans PD into an AC-coupled SR560. To shape the loop, we set SR560 to have a single-pole low- pass at 300 Hz and an overall gain of 5×104. We take the 600 Ω output and send it into a 50 Ω feed-through terminator; this attenuates the voltage by a factor of 10 or so and thereby ensures that the AOM driver is not overdriven.

The AOM driver's AM input accepts 0 to 1 V, so we add an offset to bias the control signal. The output of the 50 Ω feedthrough is sent into the 'A' input of a second SR560 (DC coupled, A − B setting, gain 1, no filtering). Using a DS345 function generator, a 500 mV offset is put into the 'B' input (the function generator reads −0.250 V because it expects 50 Ω input). The 50 Ω output of this SR560 is sent into the AOM driver's AM input.

A measurement of suppressed and unsuppressed RIN is attached. We have achieved a loop with a bandwidth of a few kilohertz and with an in-loop noise suppression factor of 50 from 100 Hz to 1 kHz. This measurement was done using the PMC trans PD, so this spectrum may underestimate the true RIN.

 A small followup measurement. Here are spectra of the MC trans diode with and without the ISS on. The DC value of the diode (in counts) changed from 17264.2 (no ISS) to 17504.3 (with ISS), but I didn't account for this change in the plot.

There is a small inkling of benefit between 100Hz and 1kHz. Above about 100Hz, the RIN is suppressed to about the noise level of this measurement. Below 100Hz there is no change, which probably means that power fluctuations are introduced downstream of the AOM, which argues for an outer-loop ISS down the road.

Atm #2 is in units of RIN.

Attachment 1: ISS_560_rot.pdf
ISS_560_rot.pdf
Attachment 2: ISS_560cal.pdf
ISS_560cal.pdf
  9379   Wed Nov 13 19:41:55 2013 JenneUpdateISSISS AOM

AOM driving from DAC:

I found that the DAC channels for TT3 and TT4 are connected up in the simulink model, but we aren't using them, since we don't actually have those tip tilts installed.  So, we hooked up the TT4 LR DAC output, which is channel 8 on the 2nd set of SMA outputs.  We put our AOM excitations into TT4_LR_EXC.

 

  9378   Wed Nov 13 19:22:58 2013 JenneUpdateLSCPRM motion correlated to intracavity power

[Gabriele, Jenne]

Nic and Evan put the ISS together (elog 9376), and we used an injection into the error point (?) to modulate the laser power before the PMC (The AOM had a bias offset, but there is no loop).  This gives us some RIN, that we can try to correlate with the PRM OSEM sensors. 

We injected several lines, around 100, 200, 500 and 800 Hz.  For 100, 200 and 800 Hz lines, we see a ratio between POPDC and the OSEM sensors of 1e-4, but at 500 Hz, the ratio was more like 1e-3. We're not sure why this ratio difference exists, but it does.  These ratios were true for the 4 face OSEMs.  The side OSEM saw a slightly smaller signal.  

For these measurements, the PRMI was sideband locked, and we were driving the AOM with an amplitude of 10,000 counts (I don't know what the calibration is between counts and actual drive, which is why we're looking at the POPDC to sensor *ratio*).  

To get a more precise number, we may want to consider locking the PRMI on carrier, so we have more power in the cavity, and so more signal in the OSEMs.  

These ratios look, by eye, similar to the ratios we see from the time back on 30 Oct when we were doing the PRMI+2arms test, and the arms were resonating about 50 units.  So, that is nice to see some consistency.

AOMmodulated_POPDC_OSEM.pdf

This time series is from 1067163395 + 27 seconds, from 30 Oct 2013 when we did the PRMI+2arms.

POPDC_sensors_30oct2013.png

 


Ideas to go forward:

We should think about chopping the OSEM LEDs, and demodulating the PD sensors. 

We should also take a look in the chamber with a camera from the viewport on the north side of the BS chamber, to see if we see any flashes in the chamber that could be going into the OSEMs, to see where we should maybe put aluminum foil shields.

  9377   Wed Nov 13 18:37:19 2013 ranaConfigurationElectronicsDAC available in c1lsc IO chassis for DAFI

The first picture shows that there is indeed a DAC next to the ADC in the LSC IO chassis. The second picture shows how there are two cables, each one carrying 8 channels of DAC. The third one shows how these come out of the coil drivers to handle the Tip/Tilt mirrors which point the beam from the IMC into the PRC. It should be the case that the second Dewhitening filter board can give us access to the next 8 channels for use in driving an audio signal into the control room or an ISS excitation.

  9376   Wed Nov 13 18:32:04 2013 Nic, EvanUpdateISSSR560 ISS loop

We have implemented an SR560-based ISS loop using the AOM on the PSL table. This is a continuation of the work in 40m:9328.

We dumped the diffracted beam from the AOM onto a stack of razor blades. This beam is not terribly well separated from the main beam, so the razor blades are at a very severe angle. Any alternatives would have involved either moving the AOM or attempting to dump the diffracted beam somewhere on the PMC refl path. We trimmed the RF power potentiometer on the driver so that with 0.5 V dc applied to the AM input, about 10% of the power is diverted from the main beam.

We ran the PMC trans PD into an AC-coupled SR560. To shape the loop, we set SR560 to have a single-pole low- pass at 300 Hz and an overall gain of 5×104. We take the 600 Ω output and send it into a 50 Ω feed-through terminator; this attenuates the voltage by a factor of 10 or so and thereby ensures that the AOM driver is not overdriven.

The AOM driver's AM input accepts 0 to 1 V, so we add an offset to bias the control signal. The output of the 50 Ω feedthrough is sent into the 'A' input of a second SR560 (DC coupled, A − B setting, gain 1, no filtering). Using a DS345 function generator, a 500 mV offset is put into the 'B' input (the function generator reads −0.250 V because it expects 50 Ω input). The 50 Ω output of this SR560 is sent into the AOM driver's AM input.

A measurement of suppressed and unsuppressed RIN is attached. We have achieved a loop with a bandwidth of a few kilohertz and with an in-loop noise suppression factor of 50 from 100 Hz to 1 kHz. This measurement was done using the PMC trans PD, so this spectrum may underestimate the true RIN.

Attachment 1: psl_aom_overhead.jpg
psl_aom_overhead.jpg
Attachment 2: aom_driver.jpg
aom_driver.jpg
Attachment 3: loop_on_settings.jpg
loop_on_settings.jpg
Attachment 4: fxn_gen.jpg
fxn_gen.jpg
Attachment 5: 40m_iss.pdf
40m_iss.pdf
  9375   Wed Nov 13 18:02:08 2013 JenneUpdateCDSCan't talk to AUXEY?

The restore scripts from the IFO config screen half-failed, with this error:

retrying (1/5)...
retrying (2/5)...
CA.Client.Exception...............................................
    Warning: "Virtual circuit disconnect"
    Context: "c1auxey.martian:5064"
    Source File: ../cac.cpp line 1214
    Current Time: Wed Nov 13 2013 17:24:00.389261330
..................................................................

Jamie, do you know what this might be?  When requested, ETMY was not misaligned or restored, but we got these errors.  So, somehow we're not talking properly to EY, but other things seem fine (the models are running okay, the suspension is damped, etc, etc.)

  9374   Wed Nov 13 11:30:07 2013 SteveUpdatePEM particle counter MOVED
Particle counter moved from the top of IOOC to the east wall
Attachment 1: Met1Moved.JPG
Met1Moved.JPG
  9373   Wed Nov 13 09:31:15 2013 GabrieleUpdateLSCPRM motion causing trouble?

Interesting results. When you compute the effect of ETM motion, you maybe should also consider that moving around the arm cavity axis changes the matching of the input beam with the cavity, and thus the coupling between PRC and arms. But I believe this effect is of the same order of the one you computed, so maybe there is only one or two factors of two to add. This do not change significantly the conclusion.

Instead, the numbers you're giving for PRM motion are interesting. Since I almost never believe computations before I see that an experiment agrees with them, I suggest that you try to prove experimentally your statement. The simplest way is to use a scatter plot as I suggested the past week: you plot the carrier arm power vs PRM optical lever signals in a scatter plot. If there is no correlation between the two motions, you should see a round fuzzy ball in the plot. Otherwise, you will se some non trivial shape. Here is an example: https://tds.ego-gw.it/itf/osl_virgo/index.php?callRep=18918

 

  9372   Wed Nov 13 08:46:03 2013 SteveUpdateVACvertex crane repair completed

nullQuote:

 

The smoke alarms were turned off and surrounding areas were covered with plastic.

The folding I-beam was ground down to be in level with the main beam.

Load bearing cable moved into correct position. New folding spring installed.

Crane calibration was done at 500 lbs at the end of the fully extended jib.

Than we realized that the rotating wheel limit switch stopped working.

This means that the crane is still out of order.

 

New limit switch installed and tested. The crane is back in full operational mode. Two spare limit switches on hand.

  9371   Wed Nov 13 01:35:40 2013 JenneUpdateLSCPRM motion causing trouble?

Quote:

* Still need to finish calculating what could be causing our big arm power fluctuations (Test mass angular motion?  PRM angular motion? ALS noise?) (Calculation)

 I think that our problem of seeing significant arm power fluctuations while we bring the arms into resonance during PRMI+arms tests is coming from PRM motion. I've done 3 calculations, so I will describe below why I think the first two are not the culprit, and then why I think the PRM motion is our dominant problem.

===============================================================

ALS length fluctuations

Arm length fluctuations seem not to be a huge problem for us right now, in terms of what is causing our arm power fluctuations.

What I have done is to calculate the derivative of the power in the arm cavity, using the power buildup that optickle gives me. The interferometer configuration I'm using is PRFPMI, and I'm doing a CARM sweep. Then, I look at the power in one arm cavity. The derivative gives me Watts buildup per meter CARM motion, at various CARM offsets. Then, I multiply the derivative by 60 nm, which is my memory of the latest good rms motion of the ALS system here at the 40m. I finally divide by the carrier buildup in the arm at each offset, to give me an approximation of the RIN at any CARM offset.

I don't know exactly what the calibration is for our ALS offset counts, but since we are not seeing maximum arm cavity buildup yet, we aren't very close to zero CARM offset. 

From this plot, I conclude that we have to be quite close to zero offset for arm length fluctuations to explain the large arm power fluctuations we have been seeing.

 xarmRIN_vs_CARM.png

=======================================================================

AS port contrast defect from ETM motion

For this calculation, I considered how much AS port contrast defect we might expect to see given some ETM motion. From that, I considered what the effect would be on the power recycling buildup. 

Rather than doing the integrals out, I ended up doing a numerical analysis. I created 2 Gaussian beams, subtracted the fields, then calculated the total power left. I did this for several separations of the beams to get a plot of contrast defect vs. separation. My simulated Gaussian beams have a FWHM of 1 unit, so the x-axis of the plot below is in units of spot motion normalized by spot size. 

Unfortunately, my normalization isn't perfect, so 2 perfectly constructively interfering beams have a total power of 0.3, so my y-axis should all be divided by 0.3. 

The actual beam separation that we might expect at the AS port from some ETM motion (of order 1e-6 radians) causing some beam axis shift is of the order 1e-5 meters, while the beam spot size is of the order 1e-3 meters. So, in normalized units, that's about 1e-2. I probably should change the x-axis to log as well, but you can see that the contrast defect for that size beam separation is very small. To make a significant difference in the power recycling cavity gain, the contrast defect, which is the Michelson transmission, should be close to the transmission of the PRM. Since that's not true, I conclude that ETM angular motion leading to PRC losses is not an issue. 

I still haven't calculated the effect of ITM motion, nor have I calculated either test mass' angular effect directly on arm cavity power loss, so those are yet to be done, although I suspect that they aren't our problem either. 

ASportOverlap_moveGaussianBeams.png

========================================================================

PRM motion

 

I think that the PRM moving around, thus causing a loss in recycling gain, is our major problem. 

First, how do I conclude that, then some thoughts on why the PRM is moving at all. 

=========

theta = 12e-6 radians (ref: oplev plot from elog 9338 last week)

L = 6.781 meters

g = 0.94

a = theta * L /(1-g) = 0.0014 meters axis displacement

w0 = 3e-3 meters = spot size at ITM

a^2/w0^2 = 0.204 ==>> 20% power loss into higher order modes due to PRM motion.

That means 20% less power circulating, hitting the ITMs, so less power going into the arm cavities, so less power buildup. This isn't 50%, but it is fairly substantial, using angular fluctuation numbers that we saw during our PRMI+arms test last week. If you look at the oplev plot from that test, you will notice that when the arm power is high (as is POP), the PRM moves significantly more than when the carrier buildup in the cavities was low. The rms motion is not 12 urad, but the peak-to-peak motion can occasionally be that large. 

So, why is that? Rana and I had a look, and it is clear that there is a difference in PRM motion when the IFO is aligned and flashing, versus aligned, but PSL shutter is closed. Written the cavities flash, the PRM gets a kick. Our current theory is that some scattered light in the PRC or the BS chamber is getting into the PRM's OSEMs, causing a spike in their error signal, and this causes the damping loops to push on the optic. 

We should think a little more on why the PRM is moving so much more that any other optic while the power is building up, and if there is anything we can do about the situation without venting. If we have to, we should consider putting aluminum foil beam blocks to protect the PRM's OSEMs. 

  9370   Tue Nov 12 23:48:23 2013 RANAUpdateIOOPSL pointing monitoring

Since I saw that the trend was good, I aligned the MC refl path to the existing IMC alignment:

  1. removed a broken IRIS that was clipping the reflected beam (and its mount)
  2. moved the first 1" diameter steering mirror on the high power path after the 2" diameter R=10% steering mirror. It was not centered.
  3. Moved the lens just upstream of the LSC RFPD away from the PD by ~5 mm. The beam going towards the WFS was too close to this mount and I could see some glow.
  4. Centered the beam on all optics in the WFS path and then the WFS DC.
  5. Centered beam on LSC RFPD.

The reflected spots from the PD are not hitting the dump correctly. WE need to machine a shorter post to lower the dump by ~1 cm to catch the beams.

  9369   Tue Nov 12 23:05:06 2013 ranaUpdatePEMthump noise from particle counter

Quote:
The particle counter is back on the IOOC location on a piece of FOAM
It needs this isolation, so when the pump is running, it's not shaking things.
The counter was counting for 6 sec and it was on holding for 20 mins.
Now I set the counter for 20 sec so it is easy to recognise it's signal and it holds for 2min only.
This will set the alarm handler in action.

Atm1: 40 mins plot
PEM-ACC_MC2_x,y,z up to 13 mins: pcounter at MC2 table, clamped, counting for 20s and holds for 2 mins
PEM-ACC_MC2_x,y,z from 13 to 26 mins: pcounter at MC2 table, not clamped, seated on 2" foam, counting 20s and holds for 2 mins
PEM-ACC_MC1_x,y,z from 26 to 40 mins: pcounter at MC1_IOOC location, not clamped, seated on 2" foam, counting 20s and holds for 2 mins

Rana won the bet

This noise source from 2008 is back. Somehow the particle counter snuck back up to the top of the BS chamber. Bad, noisy particle counter. Let's move it away from out sensitive optics and put it on the wall next to the router or maybe on some toolbox. Not on optics tables, chambers, or near them.
  9368   Tue Nov 12 21:50:01 2013 ranaUpdate zita network configured

 

 I installed 'nfs-client' on zita (the StripTool terminal). It now has mounted all the shared disks, but still can't do StripTool since its a 32-bit machine and our StripTool is 64.

  9367   Tue Nov 12 16:49:22 2013 JenneUpdateLSCXend QPD and Whitening board pulled

Quote:

* Whitening for the transmission QPDs needs to be thought about more carefully. (Calculation, then hardware)

 I have the X end transmission QPD, as well as the whitening board, out on the electronics bench.  Since the Thorlabs high-gain TRX PD also goes through this whitening board, we have no transmission signal for the Xarm at this time. The whitening board was in the left-most slot, of the top crate in the Xend rack.  The only cables that exist for it (like the Yend), are the ribbon from the QPD, the 4-pin lemo from the Thorlabs PD, and the ribbon going to the ADC.

I have taken photos, and want to make sure that I know what is going on on the circuits, before I put them back in. 

The QPD:

IMG_1262.JPG

IMG_1260.JPG

The whitening board:

IMG_1264.JPG

IMG_1276.JPG

  9366   Tue Nov 12 15:04:35 2013 ranaUpdateCDSFE Web view was fixed

Quote:

 Seems partially broken again. Not updating for most of the FE. I've commented out the cron lines for this as well as the mostly broken MEDM Snapshots job. I'm in the process of adding them to the megatron cron (since that machine is at least running 64 bit Ubuntu 12, instead of 32-bit CentOS)

 https://nodus.ligo.caltech.edu:30889/medm/screenshot.html

Seems to now be working. I made several fixes to the scripts to get it working again:

  1. changed TCSH scripts to BASH. Used /usr/bin/env to find bash.
  2. fixed stdout and stderr redirection so that we could see all error messages.
  3. made the PERL scripts executable. most of the PERL errors are not being logged yet.
  4. fixed paths for the MEDM screens to point to the right directories.
  5. the screen cap only works on screens which pop open on the left monitor, so I edited the screens so that they open up there by default.
  6. moved the CRON jobs from mafalda over to megatron. Mafalda no longer is running any crons.
  7. op540m used to run the 3 projector StripTool displays and have its screen dumped for this web page. Now zita is doing it, but I don't know how to make zita dump her screen.
  9365   Mon Nov 11 22:35:45 2013 RANAUpdateIOOPSL pointing monitoring

Since the pointing has gone bad again, I went to the PSL to investigate. Found some bad things and removed them:

1) There was a stopped down iris AGAIN in the main beam path, after the newly installed mirror mount. I opened it. Stop closing irises in the beam path.

2) The beam dump for the IOO QPD reflection was just some black aluminum. That is not a real dump. I removed it. We need two razor blade dumps for this.

3) There was an ND filter wheel (???) after one of the PMC steering mirrors. This is not good noise / optics practice. I removed it and dumped the beam in a real dump. No elog about this ?!#?

 

The attached trend shows the last 20 days. The big step ~2 weeks ago is when Steve replaced the steering mirror mount with the steel one. I don't understand the drift that comes after that.

 

Today I also spent ~1 hour repairing the Aldabella laptop. Whoever moved it from the PSL area to the SP table seems to have corrupted the disk by improper shutdown. Please stop shutting the lid and disconnecting it from the AC power unless you want to be fixing it. Its now running in some recovery mode. Lets leave it where it is next to the PSL and MC1.

I steered the MC suspensions back to where they were on the trends before the PSL mirror mount swap and then aligned the PSL beam into it by touching the last 2 steel mounts. Once the alignment was good without WFS, I centered the beams on the IOO QPDs. If it behaves good overnight, I will center the unlocked beams on the MC WFS.

 

Please stay off the PSL for a couple days if you can so that we can watch the drift. This means no opening the doors, turning on the lights, or heavy work around there.

Attachment 1: qpd.pdf
qpd.pdf
  9364   Mon Nov 11 12:19:36 2013 ranaUpdateCDSFE Web view was fixed

Quote:

FE Web view was broken for a long time. It was fixed now.

The problem was that path names were not fixed when we moved the models from the old local place to the SVN structure.

The auto updating script (/cvs/cds/rtcds/caltech/c1/scripts/AutoUpdate/update_webview.cron) is running on Mafalda.

Link to the web view: https://nodus.ligo.caltech.edu:30889/FE/

 Seems partially broken again. Not updating for most of the FE. I've commented out the cron lines for this as well as the mostly broken MEDM Snapshots job. I'm in the process of adding them to the megatron cron (since that machine is at least running 64 bit Ubuntu 12, instead of 32-bit CentOS)

  9363   Sat Nov 9 10:25:43 2013 KojiUpdateLSCNew Broadband PD for POP 22/110

General Remarks on the BBPD

- To form the LC network: Use fixed SMD inductors from Coilcraft. SMD tunable capacitors are found in the shelf right next to Steve's desk.
  If the tuning is too coarse, combine an appropriate fixed ceramic SMC C and the tunable C (in parallel, of course)

- L1/C1a/C1b pads are specifically designed for an additional notch

- Another notch at the diode stage can be formed between the middle PD pin (just left of the marking "C3b") to the large GND pad (between C1a/C1b to C3a).
  You have to scratch off the green resin with a small flat screw driver (or anything similar)

- A notch at the amplifier stage can be formed between the output of MAR-6SM ("+" marking)  and one of the GND pads (left side of the "U1" marking)

- The original design of the PD is broadband. So additional notches on the diode stage provides notches and resonances.
  Check if the resonances do not hit the signal frequencies.

- One would think the PD can have resonant feature to reduce the coupling of the undesired signals.
  In some sense it is possible but it will be different from the usual resonant tank circuit in the following two points.

  * Just adding a parallel L between the cathode and ground does not work. As this DC current should be directed to the DC path,
    L&C combo should be added. In fact this actually give a notch-resonance pair. This C should be big enough so that you can ignore it
    at the target resonant frequency. Supply complimentary small C if necessary to keep low impedance of the Cs at the target frequency.
    (i.e. Check SRF - self-resonant frequency of the big C)

  * Since the input impedance of MAR-6SM is 50Ohm, the top of the resonant curve will be cut at 50Ohm. So the resultant shape looks
    like a bandpass rather than a resonance.

- So in total, simulation of the circuit is very important to shape the transimpedance. And, consider the circuit can not be formed as simulated
  because of many practical imperfections like stray Ls and Cs.

 

  9362   Fri Nov 8 18:12:21 2013 JenneUpdateLSCPRFPMI: Not crossing any resonances

Quote:

There are several things at this point that we know we need to look into:

* Simulate an arm sweep, up to many orders of the sidebands, to see how close to the carrier resonance any sideband resonances might be.  If something like the 4th order sideband resonates, and then beats with a 1st order sideband, is that signal big enough to disturb our 3f locking of the PRMI / DRMI?  We want to be holding the arms off resonance with ALS closer to the carrier than any "important" sideband resonances (where the definition of "important" is still undetermined).  (Simulation)

 I have done a sweep of CARM, while looking at the fields inside of one arm (I've chosen the Xarm), to see where any resonances might be, that could be causing us trouble in keeping the PRMI locked as we bring the arms into resonance. 

2f_resonances_Xarm_CARMsweep.png

Since Gabriele pointed out to me that we're using the 3x55MHz signal for locking, we should be most concerned about resonances of the higher orders of 55, and not of 11.  So, on this plot, I have up to the 6th order 55 MHz sidebands, which are 332 MHz.  Although the Matlab default color chart has wrapped around, it's clear that the carrier is the carrier, and the +4f2, which is the same blue, is not the giant central peak.  So, it's kind of clear which trace is which, even though the legend colors are degenerate.  Also, the main point that I want to show here is that there is nothing going on near the carrier, with any relevant amplitude.  The nearest things are the plus and minus 55 MHz sidebands themselves, and they're more than 50 nm away from the carrier. 

Recalling from elog 9122, the PRFPMI and DRFPMI linewidths are about 40pm.  50pm away from the resonant point is ~1/10 the power, and 100pm away from the resonant point is ~1/100 the power.  So, 50 nm is a looooong ways away. 

Just for kicks, here is a plot of all the resonances of the 1f and 2f modulation frequencies, up to 30*f1, which is the same 6*f2:

AllModFreq_resonances_Xarm_CARMsweep.png

The resonances which are "close" to the carrier are the 9th order 11 MHz sidebands, and they're 280pm from the carrier, so twice as far as we need to be, to get our arm powers to ~1/100 of the maximum, and, they're a factor of ~1e4 smaller than the carrier.

  9361   Fri Nov 8 17:19:27 2013 JenneUpdateLSCNew Broadband PD for POP 22/110

Here is a photo of the board inside the broadband photodiode (one of them) that I took from the Gyro experiment:

IMG_1255.JPG

This PD is Serial Number S1200271.

We need to have a look at the schematic, figure out what's in here now, and then modify this to be useful (appropriate resonances / notches, as well as amplification) for POP 22/110.

  9360   Thu Nov 7 14:39:49 2013 JenneUpdateLSCLock Acquisition Game Plan

Between the 40m meeting, and chatting with Gabriele, there was lots of talking yesterday about our 40m Lock Acquisition game plan. 

From those talks, here is my current understanding of the plan, in a Ward-style cartoon:

 LockAcquisition_7Nov2013.pdf(This is a 2 page document - description of steps is on 2nd page)

If you look closely, you will notice that there are several places that I have used "?" rather than numbers, to indicate what RFPD signal we should be using.  To fill these in, I need to look at some more simulations, and think more carefully about what signals exist at what ports, and what SNR we have at each of those ports.

Also, while the overall scale of the arm power plot is correct, the power level at each step is totally arbitrary right now, and should just be taken to mean places (in time) where the CARM offset is reduced a little more.


There are several things at this point that we know we need to look into:

* POP 22/110 PD and filtering electronics should be switched to a broadband PD, rather than the Thorlabs PD + Miniciruits filters. (Hardware)

* Whitening for the transmission QPDs needs to be thought about more carefully. (Calculation, then hardware)

* Chose a good SNR REFL DC signal, which may or may not be from the PD we are currently using (I think it's the DC of REFL11, but I'll have to check). (Calculation)

* For DRMI locking, what is the size of the SRCL error signal at AS55, AS165, and the REFL ports?  Do we need to lock with AS port, and then switch over to a REFL 3f port, to make acquisition easier?  (Simulation)

* Similarly, I want to make the equivalent of Figure 3 of T1000294, with our 40m parameters. (Simulation)

* To set the phase of AS110, simulate the demod phase of AS110 in both DRMI and SRMI cases.  If no (significant) change, maybe we can set the phase in the real system by misaligning the PRM, and watching the SRMI flash.  (Simulation)

* Simulate an arm sweep, up to many orders of the sidebands, to see how close to the carrier resonance any sideband resonances might be.  If something like the 4th order sideband resonates, and then beats with a 1st order sideband, is that signal big enough to disturb our 3f locking of the PRMI / DRMI?  We want to be holding the arms off resonance with ALS closer to the carrier than any "important" sideband resonances (where the definition of "important" is still undetermined).  (Simulation)

* Check if we can hand DARM from the DC transmission signals to the final RF signal while we still have a large CARM offset. Is there a point where the CARM offset is too large, and we must be still using the DC signals? (Simulation)

* At what arm power level can we transition from ALS to IR DC transmission signals for the individual arms? (Simulation)

* Still need to finish calculating what could be causing our big arm power fluctuations (Test mass angular motion?  PRM angular motion? ALS noise?) (Calculation)


Replys, and comments are welcome, particularly to help me understand where I may have (likely did) go wrong in drawing my cartoon. 

  9359   Thu Nov 7 11:19:04 2013 SteveUpdateVACcrane work POSTPONED to Monday

Quote:

 

The smoke alarms were turned off and surrounding areas were covered with plastic.

The folding I-beam was ground down to be in level with the main beam.

Load bearing cable moved into correct position. New folding spring installed.

Crane calibration was done at 500 lbs at the end of the fully extended jib.

Than we realized that the rotating wheel limit switch stopped working.

This means that the crane is still out of order.

 

 New limit switch will be installed tomorrow morning

Konecranes postponed installation Friday morning Nov. 8

Friday 5pm : Konacranes promising to be here 8am Monday, Nov 11

It was rescheduled on Tuesday again for Wednesday, Nov 13

  9358   Thu Nov 7 08:57:20 2013 SteveUpdateIOOPSL pointing monitoring

 The qpd sees the power drop as position change.

The laser  monitoring screen shows little changes of the Innolight 2W output. See elog 9292 to compare

So why does the PMC downgrade if the laser output is stationary ?

The PMC-T power is down to 0.75V  The auto locker does maximize power output.

It needs a manual alignment touch up.

 

 

Attachment 1: PMC11072013.jpg
PMC11072013.jpg
Attachment 2: PMCTqpdMon.png
PMCTqpdMon.png
  9357   Wed Nov 6 17:21:58 2013 JamitUpdateCDSFB not talking to LSC?

Quote:

Something funny is going on with the framebuilder's communication with the LSC machine. 

This is a different failure mode / error than I have seen before.  It's not the type of problem that is solved by restarting the mxstreams (that is indicated by also the 2 blocks on top of one another, that are green on the lsc machine right now, being red), although I did try that, before I looked closer and realized that that wasn't the problem.

ssh-ing to c1lsc, and doing a "rtcds restart all" seems to be fixing the problem.  Both c1oaf and c1cal needed another round of restarting, because they needed their BURT buttons pressed manually.  All of the models on the lsc machine are running fine now, though.

Here's a screenshot of the CDS overview screen, with the error lights:

Screenshot-Untitled_Window-1.png

This definitely looks like a timing problem on the c1lsc front end computer.  The red lights on the left mean that the timing synchronization is lost at the user model.  I'm perplexed why it looks like the IOP is not seeing the same error, though, since it should originate at the ADC.  The red lights to the right just mean the timing synchronization is lost with the DAQ, which is too be expected given a timing loss at the front end.

We'll have to take a closer look when this happens again.

  9356   Wed Nov 6 15:59:41 2013 manasaUpdateElectronicsIOO rack +/-5V power supplies

Quote:

The power supply to the ADC box on the IOO rack (that reads the beat I & Q signals) was pulled out because it did not run through any fuse and was connected directly to the power supply. 

There were already connections running from the +/-5 V power supply. They were powering the mode cleaner demod board rack. In order to remove the ADC power connectors from the power supply, I notified Jenne in the control room because turning off the power supply would affect the MC. I switched off the +/-5V power supplies at the same time. The ADC power connectors were removed. The +/-5V power supplies were then turned ON again at the same time. Jenne relocked the MC after this.

I have still not connected the ADC to the fuse rack power supply because this requires the +/-5V power supplies to be turned OFF again in order to pull out new connections from the fuse rack and I need to make a new ADC power connector with thicker wires.

I switched OFF the +/-5V power supplies on the IOO rack to hook up the ADC power connectors through 250mA fuses to +/-5V. Since these power supplies were powering the MC demod boards, MC remained unlocked during the process. I turned the power supplies back ON and MC relocked itself after this.

  9355   Wed Nov 6 15:57:22 2013 JenneUpdateLSCPower Supply solution

We have decided that, rather than replacing the power source for the amplifiers that are on the rack, and leaving the Thorlabs PD as POP22/110, we will remove all of the temporary elements, and put in something more permanent.

So, I have taken the broadband PDs from Zach's Gyro experiment in the ATF.  We will figure out what needs to be done to modify these to notch out unwanted frequencies, and amplify the signal nicely.  We will also create a pair of cables - one for power from the LSC rack, and one for signal back to the LSC rack.  Then we'll swap out the currently installed Thorlabs PD and replace it with a broadband PD.

  9354   Wed Nov 6 15:12:01 2013 JenneUpdateCDSFB not talking to LSC?

Something funny is going on with the framebuilder's communication with the LSC machine. 

This is a different failure mode / error than I have seen before.  It's not the type of problem that is solved by restarting the mxstreams (that is indicated by also the 2 blocks on top of one another, that are green on the lsc machine right now, being red), although I did try that, before I looked closer and realized that that wasn't the problem.

ssh-ing to c1lsc, and doing a "rtcds restart all" seems to be fixing the problem.  Both c1oaf and c1cal needed another round of restarting, because they needed their BURT buttons pressed manually.  All of the models on the lsc machine are running fine now, though.

Here's a screenshot of the CDS overview screen, with the error lights:

Screenshot-Untitled_Window-1.png

  9353   Wed Nov 6 14:47:41 2013 SteveFrogsLSCDin connectors added at 1Y2

 The north side of the LSC rack is full. I installed more DIN connectors with fuses on the south side of the rack 1Y2

The access to this may be a little bit awkward. You just remove the connector, wire it and put it back in.

 

Attachment 1: 1Y2moreDinFuses.jpg
1Y2moreDinFuses.jpg
  9352   Wed Nov 6 08:33:53 2013 SteveUpdateIOOPoiting changes of PSL

Quote:

 Full list tomorrow: IP-Ang & Pos, ETMY-T, ETMY-Oplev, ETMX-T, IOO-Ang & Pos

 RA: No one in the control room this evening can understand what this ELOG means. Please use more words.

 Yesterday the last steering mirror mount on the PSL was changed, Manasa recovered the MC alignment and Jenne locked the arms.

 I centered the following qpds:  ASC-IBQPD, LSC-TRY, SUS-ETMY_OPLEV, LSC-TRX, SUS_ETMX_OPLEV

 Touching the PSL pointing IOO-QPD_ANG & POS was a mistake. We lost the reference of the well refined MC input.

 

One and 20 days TRENDS  plot showing the PSL output drift in pitch can be power drop

However initial pointing is amazingly good. ( I wonder about the lens in front of the qpd ?)

Attachment 1: 1dayTRENDofPOITING.png
1dayTRENDofPOITING.png
Attachment 2: 20dayTRENDioo.png
20dayTRENDioo.png
  9351   Tue Nov 5 19:55:12 2013 ranaUpdateSUSoplev XY-plots reflect new calibration

I used the same OSEM SUSPIT/YAW method as before to calibrate the ETMY optical lever signals. They were off by a factor of ~10.

ETMY Pitch     300  /  26    (old/new)     urad/counts

ETMY Yaw       300  /  31    (old/new)     urad/counts

These should be redone with the Kakeru / Ottaway arm cavity power technique if we want to get better than ~30% accuracy.

  9350   Tue Nov 5 19:50:07 2013 manasaUpdateElectronicsIOO rack +/-5V power supplies

The power supply to the ADC box on the IOO rack (that reads the beat I & Q signals) was pulled out because it did not run through any fuse and was connected directly to the power supply. 

There were already connections running from the +/-5 V power supply. They were powering the mode cleaner demod board rack. In order to remove the ADC power connectors from the power supply, I notified Jenne in the control room because turning off the power supply would affect the MC. I switched off the +/-5V power supplies at the same time. The ADC power connectors were removed. The +/-5V power supplies were then turned ON again at the same time. Jenne relocked the MC after this.

I have still not connected the ADC to the fuse rack power supply because this requires the +/-5V power supplies to be turned OFF again in order to pull out new connections from the fuse rack and I need to make a new ADC power connector with thicker wires.

  9349   Tue Nov 5 19:39:27 2013 JenneUpdateLSCOpLev time series

[Rana, Jenne]

We looked at the time series for all the oplevs except the BS, from last Tuesday night, during a time when we were building up the power in the arms.  We conclude from a 400 second stretch of data that there is not discernible difference in the amount of motion of any optic, when the cavities are at medium power, and when they're at low power.  Note however, that we don't have such a nice stretch of data for the really high powers, so the maximum arm power in these plots is around 5.  Both the TRX and TRY signals look fairly stationary up to powers of 1 or 2, but once you get to 4 or 5, the power fluctuations are much more significant.  So, since this isn't caused by any optic moving more, perhaps it's just that we're more sensitive to optic motion when we're closer to resonance in the arms.

However, from this plot, it looks like the ETMY is moving much more than any other optic.  On the other hand, ETMY has not ever been calibrated (there's an arbitrary 300 in there for the calibration numbers on the ETMY oplev screen).  So, perhaps it's not actually moving any more than other optics.  We should calibrate the ETM oplevs nicely, so we have some real numbers in there.  ETMX also only is roughly calibrated, relative to the OSEMs.  We should either do the move-the-QPD calibration, or a Kakeru-style pitch and yaw some mirrors and look at transmitted power.

Traces on this xml file have been filtered with DTT, using zpk([0],[0.03],1,"n").

OpLevs_during_PRMI_2arms.pdf

 

  9348   Tue Nov 5 17:12:48 2013 JenneFrogsLSCillegal power supply about to expire

Quote:

 Is this your illegally installed HP bench power supply?

 Steve has promised to add another row of fuses to the LSC rack first thing in the morning.  Then, during Wednesday Chores, we can move the wires from the power supply to the fused power.

STEVE:  NEVER MIND about doing this in the morning.  Let's chat at the lunch meeting about what needs to be done to power things down, then back up again, in a nice order, and we can do it after lunch.  

So, please do not do anything to the LSC rack tomorrow!  Thank you.

ELOG V3.1.3-