  4588   Fri Apr 29 13:15:04 2011 kiwamuUpdateLSCY arm locked : detailsAs far as I know, this button works only
once after the launch of MEDM...

  
  4589   Fri Apr 29 13:58:36 2011 ranaUpdateLSCY arm locked : details

    
        
  
  4590   Fri Apr 29 14:36:36 2011 josephb, steveUpdateCDSRemoved hanging D-sub to SCSI in 1X5

    

       
            
 P1070621.JPG 
  4591   Fri Apr 29 18:24:05 2011 SureshUpdateRF SystemRF system: 1X2 Rack cabling[Joe, Jamie, Suresh]
We have installed the IDE to SCSI
adaptor module into the 1X2 rack and have
 P4290070.JPG 
  4592   Sat Apr 30 00:15:26 2011 kiwamuUpdateSUSDRMI prep : suspension diagnosticAs a part of the DRMI preparation,
I leave all
  
  4593   Sat Apr 30 05:14:33 2011 KojiUpdateGreen LockingElectronics schematic for vertex beatbox- AC coupling for the comparator
circuit of the green locking
In order to relieve the power consumption
 freq_divider.png 
  4594   Mon May 2 11:14:27 2011 kiwamuUpdateSUSscript : opticshutdownJust FYI.
There is a useful script for this
particular job : shutting down all the suspensions
  
  4595   Mon May 2 12:51:52 2011 kiwamuUpdateLSCPRMI locking : planToday we will try to
lock the PRMI. 
  
  4596   Mon May 2 13:30:13 2011 kiwamuUpdateSUSPRMI locking prep: PRM oplevI had a quick look at PRM optical lever.
The He-Ne beam is still successfully
coming out from the chamber and I could guide
  
  4598   Mon May 2 15:53:27 2011 kiwamuUpdateLSCPRMI locking prep : demodulation boardsI swapped the name of two demodulation
boards (AS55 and REFL55).
Now
 RF_Work_Status.png 
  4599   Mon May 2 17:10:55 2011 steveUpdateSUSPRM oplevThe returning spot diameter on the qpd
~10 mm. In order to reduce the spot size
I moved the f 1145 mm lens toward the PRM
  
  4600   Mon May 2 18:16:24 2011 kiwamuUpdateLSCPRMI locking : status update(done)
- AS55 RFPD
  With a help from Jamie the
  
  4601   Mon May 2 21:14:55 2011 kiwamuUpdateElectronicstoo loose Heliax connectors on 1Y2 rackI found that
all the Heliax cables landing on the bottom
 DSC_2982_ss.jpgDSC_2984_ss.jpg 
  4602   Mon May 2 23:29:57 2011 SureshUpdateElectronicstoo loose Heliax connectors on 1Y2 rackThe countersink
gives rise to another problem when we mount
the N-type-to-SMA bulkhead adaptor. 
  
  4604   Tue May 3 03:53:20 2011 kiwamuUpdateLSCPRMI locking : doneThe PRMI has been successfully
locked 
 PRMI_locking.png 
  4605   Tue May 3 04:09:53 2011 KojiUpdateLSCREFL55 PD update[Rana, Koji]
REFL55 was modified. The noise level
confirmed. The PD is now ready to be installed.
 REFL55.pdf 
  4606   Tue May 3 05:32:04 2011 kiwamuUpdateLSCdaytime tasksDaytime tasks : 
 - PRM & BS oplev (Steve)
  
  4607   Tue May 3 10:21:25 2011 KojiUpdateLSCdaytime tasksI think the installation of the PD DC
signals are quite important. What to do
1) Connect the DC signals to the right
  
  4608   Tue May 3 10:41:35 2011 josephbUpdateCDSMorning maintenance1) Filled in the C1SUS_BS_OLMATRIX properly
so as to make the BS oplev work for Steve.
2) Turned on the ITMX damping. 
  
  4609   Tue May 3 10:59:31 2011 josephbUpdateCDS1Y2 binary output adapter board now poweredI temporarily turned off the power to the
1Y2 rack this morning while wiring in the
binary output adapter board power (+/- 15V)
  
  4610   Tue May 3 11:49:03 2011 KojiUpdateLSCdaytime tasksDone. C1:PSL-PMC_PMCTRANSPD was improved
from ~0.75 to 0.87.

  
  4611   Tue May 3 13:22:13 2011 LeoUpdateSUSRe: DRMI prep : suspension diagnosticHere are the free-swinging spectra for
the BS, ETMX, ETMY, ITMX, ITMY, MC1, MC2,
MC3, and PRM chambers.  Kiwamu left
 10x 
  4613   Tue May 3 15:04:20 2011 kiwamuUpdateSUSRe: DRMI prep : suspension diagnosticJenne went through all the suspension racks
and pushed all the connectors.
After pushing them, we had a quick
  
  4614   Tue May 3 15:48:26 2011 Larisa ThorneUpdateElectronicslaser temperature control LPF, final version!This is a continuation of this
 The low pass filter is finally
acceptable, and its Bode graph is below (on
 LPF100k.2.jpg 
  4616   Tue May 3 16:20:13 2011 steveUpdateSUSPRM & BS oplevs are ready

    

       
            
 P1070630.JPGP1070632.JPG 
  4617   Tue May 3 16:47:55 2011 kiwamuUpdateLSCPRMI locking : detailsHere
are some details about the PRMI locking done
last night.
 APtable.png 
  4618   Tue May 3 17:19:25 2011 kiwamuUpdateElectronicsHeliax connectors on 1Y2 rack : tightenedMy observation wasn't accurate enough.
The
looseness came from the fact that the N-SMA
  
  4620   Tue May 3 18:46:06 2011 ranaUpdateIOOMC Locking not workingI found that the MC autolocker was OFF.
Kiwamu says he turned it off because its
slow. Suresh says that he has some feelings
 Untitled.pngUntitled.png 
  4621   Wed May 4 11:48:01 2011 SureshUpdateIOOMC Locking not working[Valera, Suresh]
The first time I noticed that the
MC was not locking was after I had finished
  
  4622   Wed May 4 12:07:48 2011 SureshUpdateRF SystemREFL55 installed on the AP tableREFL55
has been installed on the AP table. 
REFL11 has been moved to make space for a
  
  4623   Wed May 4 13:45:56 2011 kiwamuUpdateLSClocking last nightLast night I was trying to calibrate the
MICH error signal and the actuators on BS
and ITMs.
  
  4626   Wed May 4 13:57:04 2011 kiwamuUpdateSUSmechanical resonances updated[Leo  w/ a little help from Kiwamu]
Leo
summarized the mechanical resonances of all
  
  4627   Wed May 4 15:22:39 2011 kiwamuUpdate Re: Intermittent MC3 UL PD signalI
went push all the possible connectors for
the MC3 shadow sensors including the SCSIs,
  
  4628   Wed May 4 15:39:32 2011 SureshUpdateRF SystemRF Source Harmonics

I have measured the RF source harmonics in
 RF_Harmonics_Sheet1.pdf 
  4631   Thu May 5 00:08:59 2011 JenneUpdateLSC(Almost) New Screens for RFPDsI modified C1LSC.mdl to use the CDSphase
blocks, which automatically calculate the
R and D phase rotation for us.  Now
  
  4633   Thu May 5 10:19:22 2011 steveUpdatePSLPSL-FSS_RMTEMP is backValera and I installed the the temp sensor
and the interface box that Rana fixed. This
may help with diagnosing the PSL drift.
 P1070637.JPG 
  4635   Thu May 5 13:12:06 2011 JenneUpdatePSLTemperature drift, trying to shield PMC with foileeek.  I've been running around
all day, so this is an incomplete elog. 
I'll fill in more stuff in the next hour
 PSL_Temp_drift_5May2011.pngP5050092small.jpg 
  4636   Thu May 5 13:13:32 2011 JenneUpdateLSCNew RFPD screens are inJoe helped me compile the lsc simulink
model, and now we have R&D phase rotation.
Right
  
  4637   Thu May 5 13:14:15 2011 kiwamuUpdateLSCchans file for LSCFoton
doesn't correctly display the LSC filter
bank file : C1LSC.txt.
  
  4638   Thu May 5 13:55:08 2011 kiwamuUpdateLSCMI locking : calibration of BS and ITMs actuatorsEDIT by
KI on 15/5/2011:
 MICH_OL.png 
  4639   Thu May 5 14:40:14 2011 KojiUpdateLSCMI locking : calibration of BS and ITMs actuatorsI've got confused
1) Are these the DC responses of
the coils? If that is true, we need to specify
  
  4640   Thu May 5 14:50:30 2011 JenneUpdateLSCchans file for LSC


   
        
            
  
  4641   Thu May 5 15:05:06 2011 steveUpdatePSLPSL-FSS_RMTEMP is not back

    
        
 rtnfxd.jpg 
  4643   Thu May 5 15:28:23 2011 kiwamuUpdateLSCRe: MI locking : calibration of BS and ITMs actuatorsThey are the DC responses.
I put the resonant frequencies that
  
  4645   Thu May 5 16:11:22 2011 JamieUpdateLSCchans file for LSC


   
        
            
  
  4648   Thu May 5 20:47:41 2011 KojiUpdatePSLPMC alignedThe PMC exhibited the reduction of the
transmission, so it was aligned.
The misalignment was not the angle
  
  4650   Fri May 6 06:36:18 2011 SureshUpdateRF SystemPD DC signals at each port connectedWe now
have the DC signal from three PDs available
in the ADC channels 14,15 and 16.  The
  
  4654   Fri May 6 15:59:40 2011 steveUpdateVACTP3 fore pump replacedDry fore pump of TP3 replaced by brand
new Varian SH-110  at  1.1 Torr_75,208
hrs
  
  4655   Fri May 6 17:11:55 2011 steveUpdateSUSSRM-oplev cable The SRM qpd cable was removed from the
BS-table. It's path was changed from 1x4
to ITMY-table following the inner cable tray.
  
  4656   Sat May 7 02:52:53 2011 kiwamuUpdateLSCTRY photo diode installed[Suresh / Kiwamu]
 We
installed the TRY photo diode (Thorlabs one)
  