ID |
Date |
Author |
Type |
Category |
Subject |
4070
|
Sat Dec 18 01:17:04 2010 |
kiwamu | Update | IOO | some more alignments |
[Koji and Kiwamu]
We did some more vacuum works today. It is getting ready to pump down.
(what we did)
- alignment of the POY mirrors. Now the beam is coming out from the ITMY chamber successfully
- leveling of the tables (except for the IOO and OMC chamber)
- realigned the beam axis down to the Y arm because the leveling of the BS table changed the alignments.
- installed IP_POS mirrors
- aligned the green beam and made it overlap with IR beam path.
- repositioned green steering mirrors since one of them are too close to the dark beam path
- aligned everything.
|
4071
|
Sat Dec 18 06:24:49 2010 |
rana | Update | elog | restarted |
The process was taking up 100% of the CPU and not responding via web. The .log file showed the last action was somebody reading/editing one of Jenne's entries from August regarding TT ECD. The restart script didn't work, so I had to do a 'kill -9' to get it to die. |
4072
|
Sat Dec 18 23:33:06 2010 |
Koji | Update | elog | restarted |
Did the same.
Quote: |
The process was taking up 100% of the CPU and not responding via web. The .log file showed the last action was somebody reading/editing one of Jenne's entries from August regarding TT ECD. The restart script didn't work, so I had to do a 'kill -9' to get it to die.
|
|
4073
|
Sun Dec 19 11:19:42 2010 |
Koji | Update | elog | restarted |
Did it again. It seemed that Google bot came to the elog and tried to obtain "http://nodus.ligo.caltech.edu:8080/robots.txt". That was the last of the log.
Bot came from the AJW's homepage. Also Google FeedFecther came to the elog. |
4074
|
Sun Dec 19 22:45:28 2010 |
rana | Update | elog | restarted |
I deleted the yellow box which showed up by default when making an elog entry. Would be nice if we could make it so that you have to click a button to 'opt-in' for the yellow box rather than get it by default.
I added a 'robots.txt' file to the /users/public_html/ area using Google's instructions (it only works with robot compliant crawlers), but am not sure how to put robots.txt into the elog port. |
4075
|
Mon Dec 20 10:06:36 2010 |
kiwamu | Update | CDS | ETMY damped |
Last Saturday I succeeded in damping the ETMY suspension eventually. 
This means now ALL the suspensions are happily damped.
It looked like some combination of gains and control filters had made unstabie conditions.

I actually was playing with the on/off switches of the control filters and the gain values just for fun.
Then finally I found it worked when the chebyshev filters were off. This is the same situation as Yuta told me about two months before.
Other things like the input and the output matrix looked nothing is wrong, except for the sign flips at ULSEN and SDSEN as I mentioned in the last entry (see here).
So we still should take a look at the analog filters in order to make sure why the signs are flipped. |
4076
|
Mon Dec 20 10:47:29 2010 |
Koji | Update | IOO | Plan for closing the vacuum chambers |
Monday
- Place the bars on the in-vac tables to mark the positions of the test mass suspensions. (ITMX/ITMY/ETMX/ETMY)
- Check the table leveling again (ITMX/ITMY/ETMX/ETMY/BSC)
- Align the whole interferometer.
- Check the OPLEV spots by either QPDs or apertures
- Check the OSEM values (MC1/2/3, BS, PRM, SRM, ITMX, ITMY, ETMX, ETMY)
- Energize OMC PZTs.
- We have removed the cards at the back of the HV driver.
- Insert the card and check the connection.
- Adjust the DC values at the middle of the range.
-> They have an internal bias circuit to provide +75V at the outputs. (D060287).
The actual voltages confirmed.
- Adjust the physical knobs of the PZTs such that we can see the spots at the OMCR cam
- If everything is fine, attach the access connector.
- If still everythig is fine, put the BS heavy door.
Tuesday
- Do the following list for all of the testmass chambers.
- Check if the OSEMs and the OPLEV are still fine.
- Inspect the surface of the mirror with a laser pointer or a fiber coupled halogen light.
- Blow the mirrors by the ionization gun.
- Inspect the mirror surface again.
- Move the suspension tower close to the door.
- Make a single drag-wipe with iso
- Move the SOS tower at the original place.
- Check the OSEMs and the OPLEVs. Adjust the alignment.
- Put the heavy door.
- Start slow pumping |
4077
|
Mon Dec 20 16:57:58 2010 |
steve | Update | IOO | checking out & closing the vacuum chambers |
- Check EQ-stops
- clamp down counter weights
- check other components are clamped
- remove all tools
- check cabling is not is not shorting out seismic stack or blocking beam
- confirm well centered spots on mirrors
|
4078
|
Mon Dec 20 22:56:20 2010 |
Jenne | Update | IOO | Plan for closing the vacuum chambers |
Tuesday
- If still everythig is fine, put the BS heavy door.
- Do the following list for all of the testmass chambers.
- Check if the OSEMs and the OPLEV are still fine. (ITMX and ITMY were not done on Monday, so need extra care.)
- Inspect the surface of the mirror with a laser pointer or a fiber coupled halogen light.
- Blow the mirrors by the ionization gun.
- Inspect the mirror surface again.
- Move the suspension tower close to the door.
- Make a single drag-wipe with iso
- Move the SOS tower at the original place.
- Check the OSEMs and the OPLEVs. Adjust the alignment.
- Put the heavy door.
- Start slow pumping |
4079
|
Mon Dec 20 23:10:25 2010 |
Jenne | Update | SUS | Pretty much ready for pump-down. A few final things.... |
[Kiwamu, Jenne, Koji, Osamu]
We have mostly prepared the IFO for pump down.
After lunch [Steve, Bob, Koji, Kiwamu, Jenne, Joe, Joon Ho, Vladimir, Osamu] put the access connector back in place. Hooray! Steve still has to check the Jam Nuts before we pump down. Kiwamu checked the leveling of the IOO table, and fixed all of the weights to the table.
For all 4 test masses, bars (upside-down dog clamps) were placed to mark the alignment of 2 sides of the suspension tower. All test mass tables were re-leveled, and the weights fixed to the tables.
For ETMY, PRM, BS, SRM, we confirmed that the OSEMs were close to their half-range. ETMX was already fine. ITMY (the screens and the optics wiki are still old-convention, so this is listed as ITMX! No good!) OSEMs are pretty much fine, but ITMX desperately needs to be adjusted. Unfortunately, no one can find the standard screwdriver (looks like a minus), to adjust the ITM OSEMs. All the other towers had hex-key set screws, but the ITMs need a screwdriver. We will ask Bob to sonicate a screwdriver in the morning.
|
4080
|
Mon Dec 20 23:32:58 2010 |
kiwamu | Update | IOO | Re:checking out & closing the vacuum chambers |
|
4081
|
Tue Dec 21 08:26:08 2010 |
rana | Update | elog | elogd is getting killed by Suresh |
Suresh killed the elogd again from India. This was the log file:
Accept-Charset: ISO-8859-1,utf-8;q=0.7,*;q=0.7
Keep-Alive: 115
Referer: http://www.ligo.caltech.edu/~ajw/40m_upgrade.html
Cookie: elmode=threaded; __utma=65601905.411937803.1291369887.1291369887.1291369887.1; __utmz=65601905.1291369887.1.1.utmcsr=(direct)|utmccn=(direct)|utmcmd=(none); SITESERVER=ID=4981c5fd42ae53c9c9e0980f2072be4f
Via: 1.1 sfire5.du.ac.in:3128 (squid/2.6.STABLE6)
X-Forwarded-For: 10.11.1.120
Cache-Control: max-age=259200
Connection: keep-alive
Stop killing our elog! |
4082
|
Tue Dec 21 11:52:58 2010 |
josephb | Update | Computers | RGA scripts fixed, c0rga fixed |
c0rga apparently had a full hard drive. There was 1 Gig log file in /var/log directory, called Xorg.0.log.old which I deleted which freed up about 20% of the hard drive. This let me then modify the crontab file (which previously had been complaining about no room on disk to make edits).
I updated the crontab to look at the new scripts location, updated the RGA script itself to write to the new log location, and then created a soft link in the /opt directory to /cvs/cds/rtcds on c0rga.
The RGA script should now be running again once a day. |
4085
|
Wed Dec 22 06:50:19 2010 |
rana | Update | elog | elogd is getting killed by Suresh |
After another elog crash, I've blacklisted the domain that Suresh is using by editing the apache httpd.conf. Let's see what happens now. |
4086
|
Wed Dec 22 11:24:23 2010 |
haixing | Update | SUS | measurement of imbalance in quadrant maglev protope |
Yesterday, a sequence of force and gain measurement was made to determine the imbalance in the
quadrant, magnetic-levitation prototype. This was the reason why it failed to achieve a stable levitation.
The configuration is shown schematically by the figure below:

Specifically, the following measurements have been made:
(1) DC force measurement among four pairs of magnets at fixed distance with current of the coils on and off
From this measurement, the DC force between pair of magnets is determined and is around 1.6 N at with a
separation of 1 cm. This measurement also lets us know the gain from voltage to force near the working point.
The force between pair "2" is about 13% stronger than other pairs which are nearly identical. The force by the
coil is around 0.017 N per Volt (levitation of 5 g per 3 Volt); therefore, we need around 12 volt DC compensation
of pair "2" in order to counterbalance such an imbalance. Given the resistence of the coil equal to 26 Om, this
requires almost 500 mA DC compensation. Koji suggested that we need a high-current buffer, instead of what
has been used now.
(2) DC force measurement among four pairs of magnets (with current of the coils off) as a function of distance
From this measurement, we can determine the stiffness of the system. In this case, the stiffness or the
effective spring constant is negative, and we need to compensate it by using a feedback control. This is
one of the most important parameters for designing the feedback control. The data is still in processing.
(3) Gain measurement of the OSEM from the displacement to voltage.
This measurement is a little bit tricky due to the difficulty to determine the displacement of the flag.
After several measurements, it gave approximately 2 V/cm.
Plan for the next few days:
From the those measurements, all the parameters for the plant and sensor that need to determine the
feedback control are known. They should be plugged into the simulink model and to see whether the
old design is appropriate or not. Concerning the experimental part, we will first try to levitate the configuration
with 2 pairs of magnets, instead of 4 pairs, as the first step, which is easier to control but still interesting.
|
4087
|
Wed Dec 22 15:30:47 2010 |
Osamu | Update | ASC | ETMY oplev fixed |
According to c1scy.mdl, OL signals should be connected to adc_0_24 to adc_0_27 but they were connected to adc_0_16 to adc_0_19 which are assigned to QPD signals.
Actually cable connections were messed up. One ribbon cable was connected from QPD driver and ADC ports assigned for OL, and another ribbon cable was connected from the board combining the signals of oplev and QPD to ADC port assigned for QPD.
Now ETMY oplev is working well and aligned to center. |
4088
|
Wed Dec 22 15:47:22 2010 |
Koji | Update | VAC | Tank closing procedure |
[Jenne Kiwamu Joe Osamu Steve Koji]
Yesterday (21st), we closed the BSC and the four testmass chambers.
We splitted the team into three.
- Wiping team (Jenne/Kiwamu)
- Suspension team (Osamu/Koji)
- Door closing team (Joe/Steve)
While the wiping team was working, the suspension team prepared the next suspension.
Once the mirror was wiped, the suspension team restored that suspension at the position of the markings on the table.
After the wipe of the first mirror, the wiping team got experienced and they were the fastest among the teams.
So the wiping team worked as the second suspension team when necessary.
All of us became the closing team after the last suspension has been restored.
We checked that we still have the Michelson fringes and the oplev pointings.
In total, the work was very efficient such that we only took four hours for the entire process.
We left the suspension marking on the optical tables because they are quite useful. |
4091
|
Thu Dec 23 03:15:11 2010 |
Koji | Update | elog | elogd is getting killed by Suresh |
ELOG has crashed and I restarted it.
Actually the filtering is not effective so far as elog is not using apache but has its own web server inside.
So this just block the access to port 30889 (=SVN, Dokuwiki, etc).
Quote: |
After another elog crash, I've blacklisted the domain that Suresh is using by editing the apache httpd.conf. Let's see what happens now.
|
|
4092
|
Thu Dec 23 08:54:32 2010 |
Suresh | Update | elog | the delhi univ syndrome |
Sorry folks! I couldnt get to the elog and didnt know that the elog was crashing every time I tried to access it.
But have found other means to access it and the elog is safe for now! |
4093
|
Thu Dec 23 12:19:43 2010 |
kiwamu | Update | Green Locking | installed doubling oven base at PSL table |
I gave a christmas present to a doubling oven who has been sitting on the PSL table.
The below is a picture of the present I gave. It's a base plate for the doubling oven, made from a block of aluminum, and black-anodized.
The size and the shape are nicely tailored for the combination of the Newfocus kinematic mount and the Covesion oven.
The design had been done by using Solid Works 2010

Here is a picture before he got the present.

Now he looks pretty happy.

|
4095
|
Thu Dec 23 18:51:37 2010 |
rana | Update | Green Locking | installed doubling oven base at PSL table |
This is not such a bad base design, but remember that we have to get a couple of parts with the purple anodize to see if there is a difference between black and purple in terms of the 532 nm reflectivity. |
4096
|
Thu Dec 23 22:13:50 2010 |
Koji | Update | General | PZT HV turned on |
The four IOO PZTs have been turned on in order to confirm the alignment of the IFO.
Once they are turned on, the spots (ITMX/ITMY/PRM/SRM) on the REFL CCD have been easily found.
When the X-arm was aligned to the green beam, it is easily locked to TEM00. Also some LG modes were visible.
i.e. There is some room to improve the mode matching.
The transmitted green at the PSL table is a bit too high and clipped by the first mirror on the table.
No IR flashes were found in either arms.
------------------
The below are the range and the set values of the strain gauge readback for the PZTs.
When the closed loop buttons are activated the PZTs are fixed at those values, if no one touches the set point dials.
Min Max SetP | Display on the module
PZT1 Yaw 2.20 9.95 6.08 | Broken
PZT1 Pitch -0.011 8.89 4.40 | 1.58
PZT2 Yaw 0.737 9.94 5.37 | 2.17
PZT2 Pitch 0.010 9.42 4.71 | 1.89 |
4097
|
Fri Dec 24 09:01:33 2010 |
josephb | Update | CDS | Borrowed ADC |
Osamu has borrowed an ADC card from the LSC IO chassis (which currently has a flaky generation 2 Host interface board). He has used it to get his temporary Dell test stand running daqd successfully as of yesterday.
This is mostly a note to myself so I remember this in the new year, assuming Osamu hasn't replaced the evidence by January 7th. |
4099
|
Fri Dec 31 12:41:02 2010 |
rana | Update | General | IR flashes |
I came in today to check up on the StripTool and burn the Ubuntu LTS (new CDS OS) DVD. I was pretty excited to see the PRM flashes on Mon1.
I waggled the PRM/BS alignments and got a good contrast MICH and then bright flashes in the PRM that totally overload Mon1's CCD.
Now I can see flashes of some IR junk in the X Arm; its way off on the left edge of the mirror, but there's a beam.
For the short term, we can hook up the IO PZTs to some old EPICS channels (like one of the AUX guys in the LSC area), but eventually it has to get hooked up to the new ASC or ASS. We have to bug Joe to see where this shows up in his master diagram.
**Note: if you get lost sometimes when doing the alignments, remember that you can use time_machine_conlog.
Ex:
rossa:general>./time_machine_conlog 2010/12/31,11:00:00 PDT C1:SUS-ITMX_PIT_COMM
Issuing the conlog command:
/cvs/cds/caltech/conlog/bin/conlog +epics -interp at 2010/12/31,11:00:00 PDT "C1:SUS-ITMX_PIT_COMM"
Conlog Replied:
LIGO controls: values at 2010 12/31 11:00:00 pst
__Epics_Channel_Name______ __value_____
C1:SUS-ITMX_PIT_COMM 0.406100
Restoring now...
Restoration Successful
Attached is the last 8 days of Vacuum Pressure trend which includes the pumpdown.
|
Attachment 1: Untitled.png
|
|
4101
|
Sat Jan 1 19:13:40 2011 |
rana | Update | CDS | c1pem now recording data |
I found that there was no PEM data nor any other data (no SUS or otherwise. No testpoints, no DAQ).
I went through the procedure that Jenne has detailed in the Wiki but it didn't work.
1) Firstly, the 'telnet fb 8088' step doesn't work. It says "Connected to fb.martian" but then just hangs. To replicate the effect of this step I tried ssh'ing to fb and doing a 'pkill daqd'. That works to restart the daqd process.
2) The wiki instructions had a problem. In the GUI step, it should say 'Save' after the Acquire bit has been set to 1. Even so, this works to get the .ini file right and the DTT can see the correct channel list, but none of the channels are available. There are just 'Unable to obtain measurement data'.
3) I tried running 'startc1pem', but no luck. I also tried rebooting c1sus from the command line. That worked so far as to come back up with all the right processes running, but still no data. The actual /frames directory shows that there are frames, but we just can't see the data. I also tried to get data usind the DTT-NDS2 method, but still no luck. (*** ITMX and ITMY both came back with all their filters off; worth checking if their BURTs are working correctly.)
Using DataViewer, however, I AM able to see the data (although the channel name is RED). In fact, I am able to see the trend data ever since I changed the Acquire bit to 1. Plot attached as evidence. Why does DTT not work anymore??? |
Attachment 1: Untitled.png
|
|
4103
|
Tue Jan 4 02:58:53 2011 |
Jenne | Update | IOO | Power into Mode Cleaner increased |
What was the point:
I twiddled with several different things this evening to increase the power into the Mode Cleaner. The goal was to have enough power to be able to see the arm cavity flashes on the CCD cameras, since it's going to be a total pain to lock the IFO if we can't see what the mode structure looks like.
Summed-up list of what I did:
* Found the MC nicely aligned. Did not ever adjust the MC suspensions.
* Optimized MC Refl DC, using the old "DMM hooked up to DC out" method.
* Removed the temporary BS1-1064-33-1025-45S that was in the MC refl path, and replaced it with the old BS1-1064-IF-2037-C-45S that used to be there. This undoes the temporary change from elog 3878. Note however, that Yuta's elog 3892 says that the original mirror was a 1%, not 10% as the sticker indicates. The temporary mirror was in place to get enough light to MC Refl while the laser power was low, but now we don't want to fry the PD.
* Noticed that the MCWFS path is totally wrong. Someone (Yuta?) wanted to use the MCWFS as a reference, but the steering mirror in front of WFS1 was switched out, and now no beam goes to WFS2 (it's blocked by part of the mount of the new mirror). I have not yet fixed this, since I wasn't using the WFS tonight, and had other things to get done. We will need to fix this.
* Realigned the MC Refl path to optimize MC Refl again, with the new mirror.
* Replaced the last steering mirror on the PSL table before the beam goes into the chamber from a BS1-1064-33-1025-45S to a Y1-45S. I would have liked a Y1-0deg mirror, since the angle is closer to 0 than 45, but I couldn't find one. According to Mott's elog 2392 the CVI Y1-45S is pretty much equally good all the way down to 0deg, so I went with it. This undoes the change of keeping the laser power in the chambers to a nice safe ~50mW max while we were at atmosphere.
* Put the HWP in front of the laser back to 267deg, from its temporary place of 240deg. The rotation was to keep the laser power down while we were at atmosphere. I put the HWP back to the place that Kevin had determined was best in his elog 3818.
* Tried to quickly align the Xarm by touching the BS, ITMX and ETMX. I might be seeing IR flashes (I blocked the green beam on the ETMX table so I wouldn't be confused. I unblocked it before finishing for the night) on the CCD for the Xarm, but that might also be wishful thinking. There's definitely something lighting up / flashing in the ~center of ETMX on the camera, but I can't decide if it's scatter off of a part of the suspension tower, or if it's really the resonance. Note to self: Rana reminds me that the ITM should be misaligned while using BS to get beam on ETM, and then using ETM to get beam on ITM. Only then should I have realigned the ITM. I had the ITM aligned (just left where it had been) the whole time, so I was making my life way harder than it should have been. I'll work on it again more today (Tuesday).
What happened in the end:
The MC Trans signal on the MC Lock screen went up by almost an order of magnitude (from ~3500 to ~32,000). When the count was near ~20,000 I could barely see the spot on a card, so I'm not worried about the QPD. I do wonder, however, if we are saturating the ADC. Suresh changed the transimpedance of the MC Trans QPD a while ago (Suresh's elog 3882), and maybe that was a bad idea?
Xarm not yet locked.
Can't really see flashes on the Test Mass cameras. |
4104
|
Tue Jan 4 11:06:32 2011 |
Koji | Update | IOO | Power into Mode Cleaner increased |
- Previously MC TRANS was 9000~10000 when the alignment was good. This means that the MC TRANS PD is saturated if the full power is given.
==> Transimpedance must be changed again.
- Y1-45S has 4% of transmission. Definitively we like to use Y1-0 or anything else. There must be the replaced mirror.
I think Suresh replaced it. So he must remember wher it is.
- We must confirm the beam pointing on the MC mirrors with A2L.
- We must check the MCWFS path alignment and configuration.
- We should take the picture of the new PSL setup in order to update the photo on wiki.
Quote: |
What was the point:
I twiddled with several different things this evening to increase the power into the Mode Cleaner. The goal was to have enough power to be able to see the arm cavity flashes on the CCD cameras, since it's going to be a total pain to lock the IFO if we can't see what the mode structure looks like.
Summed-up list of what I did:
* Found the MC nicely aligned. Did not ever adjust the MC suspensions.
* Optimized MC Refl DC, using the old "DMM hooked up to DC out" method.
* Removed the temporary BS1-1064-33-1025-45S that was in the MC refl path, and replaced it with the old BS1-1064-IF-2037-C-45S that used to be there. This undoes the temporary change from elog 3878. Note however, that Yuta's elog 3892 says that the original mirror was a 1%, not 10% as the sticker indicates. The temporary mirror was in place to get enough light to MC Refl while the laser power was low, but now we don't want to fry the PD.
* Noticed that the MCWFS path is totally wrong. Someone (Yuta?) wanted to use the MCWFS as a reference, but the steering mirror in front of WFS1 was switched out, and now no beam goes to WFS2 (it's blocked by part of the mount of the new mirror). I have not yet fixed this, since I wasn't using the WFS tonight, and had other things to get done. We will need to fix this.
* Realigned the MC Refl path to optimize MC Refl again, with the new mirror.
* Replaced the last steering mirror on the PSL table before the beam goes into the chamber from a BS1-1064-33-1025-45S to a Y1-45S. I would have liked a Y1-0deg mirror, since the angle is closer to 0 than 45, but I couldn't find one. According to Mott's elog 2392 the CVI Y1-45S is pretty much equally good all the way down to 0deg, so I went with it. This undoes the change of keeping the laser power in the chambers to a nice safe ~50mW max while we were at atmosphere.
* Put the HWP in front of the laser back to 267deg, from its temporary place of 240deg. The rotation was to keep the laser power down while we were at atmosphere. I put the HWP back to the place that Kevin had determined was best in his elog 3818.
* Tried to quickly align the Xarm by touching the BS, ITMX and ETMX. I might be seeing IR flashes (I blocked the green beam on the ETMX table so I wouldn't be confused. I unblocked it before finishing for the night) on the CCD for the Xarm, but that might also be wishful thinking. There's definitely something lighting up / flashing in the ~center of ETMX on the camera, but I can't decide if it's scatter off of a part of the suspension tower, or if it's really the resonance.
What happened in the end:
The MC Trans signal on the MC Lock screen went up by almost an order of magnitude (from ~3500 to ~32,000). When the count was near ~20,000 I could barely see the spot on a card, so I'm not worried about the QPD. I do wonder, however, if we are saturating the ADC. Suresh changed the transimpedance of the MC Trans QPD a while ago (Suresh's elog 3882), and maybe that was a bad idea?
Xarm not yet locked.
Can't really see flashes on the Test Mass cameras.
|
|
4105
|
Tue Jan 4 13:57:48 2011 |
kiwamu | Update | IOO | incident mirror changed from 45deg to 0 deg |
I replaced the final steering mirror (Y1-1037-45-S) in the zig-zag path on the PSL table by a 0 deg mirror Y1-1037-0.
With a sensor card I confirmed the transmission reduced a lot after the replacement.
As we expected, the replacement of the mirror caused a mis-alignment of the incident beam axis to the MC, so I compensated it by touching the angle of the mirror a little bit.
After the alignment of the mirror, the MC is still resonating at TEM00.
We will check the spot positions more accurately by A2L technique.
Quote: |
- Y1-45S has 4% of transmission. Definitively we like to use Y1-0 or anything else. There must be the replaced mirror.
I think Suresh replaced it. So he must remember wher it is.
|
|
4106
|
Tue Jan 4 15:12:33 2011 |
Suresh | Update | IOO | MC Trans Mon QPD gain decreased by 10 |
Decreased the gain of MC-Trans-Mon QPD ckt
The resistors R1, R2, R3, R4 are now 49.9 kOhm. The previous elog on this subject 3882 has the ckt details. |
4107
|
Tue Jan 4 18:37:18 2011 |
Jenne | Update | IOO | MCWFS aligned |
I undid Yuta's temporary setup, and put beam back on both WFS. Since Koji had just aligned the Mode Cleaner, I centered the beam on the WFS using the WFS QPD screen, while watching the WFS Head screen, to make sure that the beam was actually hitting the QPD, and not off in lala land.
Quote from Koji: |
- We must check the MCWFS path alignment and configuration.
Quote from Jenne: |
* Noticed that the MCWFS path is totally wrong. Someone (Yuta?) wanted to use the MCWFS as a reference, but the steering mirror in front of WFS1 was switched out, and now no beam goes to WFS2 (it's blocked by part of the mount of the new mirror). I have not yet fixed this, since I wasn't using the WFS tonight, and had other things to get done. We will need to fix this.
|
|
|
4108
|
Tue Jan 4 21:21:57 2011 |
kiwamu | Update | IOO | PZTs are connected to c1iscaux |
I connected PZT1 and PZT2 to a slow front end machine c1iscaux.
Now we are able to align these PZTs from the control room via epics.
Since we removed C1ASC that was controlling the voltage applied on the PZTs, we didn't have the controls for them for a long time.
So Rana and I decided to hook them up to an existing slow front end machine temporarily.
(probably the best solution is to connect them to C1LSC, which is fast enough to dither them.)
We actually found that c1iscaux is the proper machine, because it looked like it used to control the PZTs a long long time ago.
Moreover, c1iscaux still has DAC channels named like C1:LSC-PZT1_X, and so on.
Below shows a screen shot of the medm screen for controlling the PZTs, invoked from a button on sitemap.adl ( pointed by a black arrow in the picture below)
The current default values are all zero at the right top sliders.

|
4110
|
Wed Jan 5 03:06:02 2011 |
kiwamu | Update | IOO | beam spots on MC mirrors |
I checked the spot positions on MC1 and MC3 by running Yuta's A2L script.
The amounts of the off-centering were good except for YAW of MC1.
So we have to adjust the YAW alignment of the beam axis by steering the mirrors at the PSL table.
- - - (measured off-centering) - - -
MC1_PIT = -0.711 mm
MC1_YAW = 1.62 mm
MC3_PIT = -0.0797 mm
MC3_YAW = - 0.223 mm
Quote: |
We will check the spot positions more accurately by A2L technique.
|
|
4111
|
Wed Jan 5 10:45:51 2011 |
Koji | Update | elog | restarted |
Google bot crashed the elog again. Then, I found that Google bot (and I) can crash elogd by trying to show the threaded view.
There looks similar issue reported to the elog forum, the author did not think this is a true bag.
Note: This happens only for the 40m elog. The other elogs (ATF/PSL/TCS/SUS/Cryo) are OK for the threaded view.
Quote: |
Did it again. It seemed that Google bot came to the elog and tried to obtain "http://nodus.ligo.caltech.edu:8080/robots.txt". That was the last of the log.
Bot came from the AJW's homepage. Also Google FeedFecther came to the elog.
|
|
4114
|
Wed Jan 5 21:19:29 2011 |
Zach | Update | elog | restarted |
Restarted the elog with the script |
4116
|
Wed Jan 5 23:22:00 2011 |
Jenne | Update | Cameras | Aligned the Xarm, no big deal |
[Kiwamu, Jenne]
We successfully aligned the X arm. No big deal. Nothing to write in giant colorful letters about. If we thought it was tricky, we'd be excited. But since we're rockstar grad students, we can do this anytime, with one hand behind our back.
The details:
Earlier this evening, Kiwamu put a PD at the dark port. After starting with the usual steering beams around and approximately centering them by finding the beam on the SUS tower, we saw that we could see the fringes on a 'scope hooked up to the dark port's new PD. We could make the dip in the scope trace go away by misaligning the ETM, so we were confident that it was due to some kind of resonance in the arm. We then fine-tuned our beam centering by moving the optics in either pitch or yaw until the fringe went away, wrote down the number, then moved the other direction until the fringe went away, and then put the optic back in the middle of those two numbers. We did the ETM first, then the ITM (because the beam on the PD is sensitive to the ITM pointing, so we didn't want to have to move the ITM very far). We saw that the cavity had a visibility of ~56% when we had finished with this method.
We then went to look for the flashes transmitted through the ETM. We were not able to see them on a card, but when we looked with an IR viewer at the back face of the ETM, we could see the flashes. We stole a spare CCD camera found on the PSL table, and the camera power supply from the RefCav Refl camera, and set up a CCD camera with telephoto lens on the ETMX Trans table, looking directly at the back of the ETM. We hooked the camera up to the regular ETMX camera cable, so we can see the flashes in the control room. You can see them here:

While the cavity was aligned, here were the slider positions:

|
4117
|
Wed Jan 5 23:37:12 2011 |
rana | Update | Cameras | Aligned the Xarm, no big deal |
Pretty fancy work actually...I wouldn't have guessed that you need to look at the back of the ETM. Does this mean that we can't see the flashes from inside the arm cavity? If so, its a pretty remarkeable statement about the wide angle scatter of the new mirrors. Do we really have 1W going into the MC? |
4118
|
Wed Jan 5 23:45:33 2011 |
Jenne | Update | Cameras | Aligned the Xarm, no big deal |
Correct. We can see the flashes clearly on our new ETM camera, but we see absolutely nothing on the ITM.
Unfortunately, the camera is in the path of the green beam, so we'll have to figure out a more permanent plan. Right now the laser at the end is shuttered.
Measuring the power now....
Quote: |
Pretty fancy work actually...I wouldn't have guessed that you need to look at the back of the ETM. Does this mean that we can't see the flashes from inside the arm cavity? If so, its a pretty remarkeable statement about the wide angle scatter of the new mirrors. Do we really have 1W going into the MC?
|
|
4119
|
Thu Jan 6 00:03:05 2011 |
Koji | Update | Cameras | Aligned the Xarm, no big deal |
Nice, nice! 
The power budget for the FPMI is here. The expected Intracavity power and the transmission are at most ~8W and 100uW, respectively.
|
4120
|
Thu Jan 6 00:06:01 2011 |
Jenne | Update | IOO | Magical absorbing PZT mirror |
[Kiwamu, Jenne]
We have a measely 465mW going into the MC. We lose a boatload of power on the PZT mirror that is part of the last zigzag for steering into the MC. Just before this mirror, we measure 1.21W . Just after this mirror, we measure ~475mW. Then a teeny bit gets picked off for the PSL POS/ANG. But we're losing a factor of 3 on this one mirror. Need to fix!!!!!!!!! |
4121
|
Thu Jan 6 10:47:11 2011 |
Koji | Update | elog | ELOG fixed (re: restarted) |
Fixed the 40m elog crashing with the threaded display.
This morning I found that Google bot crashed the elog again. I started the investigation and found the threaded mode is fine if we use the recent 10 entries.
I gradually copied the old entries to a temporary elog and found that a deleted elog entry on August 6 had a corrupted remnant in the elog file. This kept crashed the threaded mode.
Once this entry has been eliminated again, the threaded mode got functional.
I hope this eliminates those frequent elog crashing.
Quote: |
Google bot crashed the elog again. Then, I found that Google bot (and I) can crash elogd by trying to show the threaded view.
There looks similar issue reported to the elog forum, the author did not think this is a true bag.
Note: This happens only for the 40m elog. The other elogs (ATF/PSL/TCS/SUS/Cryo) are OK for the threaded view.
Quote: |
Did it again. It seemed that Google bot came to the elog and tried to obtain "http://nodus.ligo.caltech.edu:8080/robots.txt". That was the last of the log.
Bot came from the AJW's homepage. Also Google FeedFecther came to the elog.
|
|
|
4122
|
Fri Jan 7 00:14:36 2011 |
kiwamu | Update | IOO | EOM triple resonant box is working |
I checked the triple resonant box for the broadband EOM this afternoon, and found it was healthy.
So I installed it again together with a power combiner and succeeded in locking the MC.
Since the box has a non-50 Ohm input impedance at 29.5 MHz, so it maybe needed to adjust the phase of the LO for the demodulation of the PDH signal.
A good thing is that now we are able to impose the other sidebands (i.e. 11 MHz and 55MHz) via the power combiner. |
4123
|
Fri Jan 7 00:49:16 2011 |
Jenne | Update | Green Locking | Recovered Xarm Green Lock, Preparation for Beat Note Measurement |
[Kiwamu, Jenne]
We went this evening in search of a beat note signal between the Xarm transmitted green light and the PSL doubled green light.
First, we removed our new ETMX camera (we left the mount so it should be easy to put back) from the other day. We left the test masses exactly where they had been while flashing for IR, so even though we can no longer confirm, we expect that the IR beam axis hasn't changed. We used the steering mirror on the end table to align the green beam to the cavity. We turned on the loop to lock the end laser to the cavity, and achieved green lock of the arm.
Then we went to the PSL table to overlap the arm transmitted light with the PSL doubled light. We made a few changes to the optics that take the arm transmitted light over to the PD. We found that the arm transmitted light was very high, so we changed from having one steering mirror to having 3 (for table space / geometry reasons we needed 3, not just 2) in order to lower the beam axis. We also found that the spot size of the arm transmitted beam was ~2x too small, so we changed the mode matching telescope from a 4x reducer to a 2x reducer by changing the 2nd lens from f=50mm to f=100mm (the first lens is f=200mm). We made the arm transmitted beam and the PSL green beam overlap, but we saw no peak on the spectrum analyzer.
We checked the temperature of the PSL and end lasers, and determined that we needed to adjust the set temp of the end laser. However, we still didn't find any beat note.
We then tweaked the temperature of the doubling oven at the end station, to maximize the power transmitted, since Kiwamu said that that had worked in the past. Alas, no success tonight.
We're stopping for the evening, with the success of reacquiring green lock of the Xarm. |
4124
|
Fri Jan 7 12:01:39 2011 |
Osamu | Update | Computers | c1lsc running |
I got a new adapter board for expansion chassis from CDS and exchanged the existing adapter board which was laid on the floor around ETMX to new one.
Then I connected the chassis to c1lcs, c1lsc seems to be running now. I will return the old board to CDS since Rolf says he wants to return it to manufacture.
I found an interface box from ADC to D-SUB37pin and a cable to connect them.
I needed to make cables to connect the interface box to existing LSC whitening filters that has a 37 pin female D-SUB connector on one end and a 40pin female flat connector on the other end. We should use shielded cables for them, but unfortunately CDS did not have right one. Temporarily I made one cable for 1-8ch using a ribbon twist cable like Joe did.
I found a saturation at ch5 of ADC0 on c1lsc. I did not check carefully but it seemed to come from the LSC whitening board. Input of ch5 of the whitening board was not terminated and had a huge output voltage, but also ch6 was not terminated and had no big output. I guess something wrong on the LSC whitening board. Needs to be checked. Anyway I unplugged the small ribbon cable between the whitening board and the next LSC AA filter board.
Finally I realized that fiber connection of RFM did not exist. What I saw was the fiber cable of Dolphin. We need a RFM PCIe interface board, and a long fiber cable between c1lsc and RFM hub. |
4125
|
Fri Jan 7 15:17:37 2011 |
steve | Update | Cameras | ITMX video monitor has tower wide view |
The Watec 902, 1/2" CCD camera got new Tamron lens: 1/2" 10-40mm F/1.4 manual iris. IR corrective lens. It is designed to have the same focal point in the IR as
in the visible light range. However, as the depth of field in the IR range is very narrow, focus adjustment should be done carefully in the IR.
Now you can see the sus tower that will make alignment easier.
|
4126
|
Sat Jan 8 21:12:12 2011 |
rana | Update | CDS | Megatron is back |
I started reverting Megatron into a standard Ubuntu workstation after Joe/Osamu's attempt to steal it for their real time mumbo jumbo.
First, I installed a hard drive that was sitting around on top of it. That whole area is still a mess; I'm not surprised that we have so many CDS problems in such a chaotic state. There's another drive sitting around there called 'RT Linux' which I didn't use yet.
Second, I removed the ethernet cables and installed a monitor/keyboard/mouse on it.
Then I popped in the Ubuntu 10.04 LTS DVD, wiped the existing CentOS install and started the standard graphical installation of Ubuntu.

Megatron's specs attached: |
Attachment 2: sysinfo.text
|
4127
|
Sat Jan 8 23:18:03 2011 |
rana | Update | Computers | network table |
There's, as usual, a disconnect between the real martian host table and the one displayed on the Wiki. Basically, the point is: DO NOT TRUST THE WIKI, because people who update the actual host table only randomly update the wiki table.
The only thing worth trusting is the file
/var/named/chroot/var/named/martian.zone
on linux 1.
You will need to have 'root' or 'sudo' to get into that directory to read the file. |
4129
|
Mon Jan 10 16:39:36 2011 |
josephb, alex, rolf | Update | CDS | New Time server for frame builder and 1PPS |
Alex and Rolf came over today with a Tempus LX GPS network timing server. This has an IRIG-B output and a 1PPS output. It can also be setup to act as an NTP server (although we did not set that up).
This was placed at waist height in the 1X7 rack. We took the cable running to the presumably roof mounted antenna from the VME timing board and connected it to this new timing server. We also moved the source of the 1PPS signal going to the master timer sequencer (big blue box in 1X7 with fibers going to all the front ends) to this new time server. This system is currently working, although it took about 5 minutes to actually acquire a timing signal from the GPS satellites. Alex says this system should be more stable, with no time jumps.
I asked Rolf about the new timing system for the front ends, he had no idea when that hardware would be available to the 40m.
Currently, all the front ends and the frame builder agree on the time. Front ends are running so the 1 PPS signal appears to be working as well. |
4130
|
Mon Jan 10 16:47:08 2011 |
josephb, alex, rolf | Update | CDS | Fixed c1lsc dolphin reflected memory |
While Alex and Rolf were visiting, I pointed out that the Dolphin card was not sending any data, not even a time stamp, from the c1lsc machine.
After some poking around, we realized the IOP (input/output processor) was coming up before the Dolphin driver had even finished loading.
We uncommented the line
#/etc/dolphin_wait
in the /diskless/root/etc/rc.local file on the frame builder. This waits until the dolphin module is fully loaded, so it can hand off a correct pointer to the memory location that the Dolphin card reads and writes to. Previously, the IOP had been receiving a bad pointer since the Dolphin driver had not finished loading.
So now the c1lsc machine can communicate with c1sus via Dolphin and from there the rest of the network via the traditional Ge Fanuc RFM. |
4131
|
Tue Jan 11 01:05:29 2011 |
kiwamu | Update | LSC | obtained Xarm PDH signal |
[Jenne, Zach, Kiwamu]
We made some efforts to lock the X arm cavity with the infrared beam.
We eventually obtained the PDH signal from a photo diode at AS port, we are still in the mid way of the lock.
The PDH signal now is going into c1lsc's ADC.
We have to make sure which digital channel corresponds to our PDH signal,
(what we did)
- split the LO signal, which comes from a Marconi, just before the EOM into two path.
One is going to the EOM and the other is going to the AP table for the demodulation, The driving frequency we are using is 11MHz.
- put RF amplifiers to make the RF signal bigger. The raw signal was small, it was about ~-50 dBm in the spectrum analyzer.
So we connected two ZLN amplifiers. Now the RF signal is at about 0 dBm
- connected the LO and RF signals to a mixer. Additionally we put a 9.5-11.5 MHz bandpass filter at the LO path since there was some amounts of 29.5MHz due to the RF reflection at the EOM resonant box.
After a low pass filter by SR560 the signal shows typical PDH behaviors.
- strung a BNC cable which connects the demodulated signal and c1lsc.
In order to connect the signal to the current working ADC, we disconnected AS166_I from a whitening board and plug our cable on it.
- tried checking the digital signal but we somehow couldn't configure DAQ setting, So actually we couldn't make sure which channel corresponds to our signal.
|
4133
|
Tue Jan 11 11:39:45 2011 |
steve | Update | VAC | RGA is turned on |
Joe updated the rga procedure in the wiki and we turned on the filament. It will take a few days to reach thermal equilibrium.
TP2 dry fore pump was replaced at 910mTorr |
Attachment 1: pd70d22.jpg
|
|