40m QIL Cryo_Lab CTN SUS_Lab CAML OMC_Lab CRIME_Lab FEA ENG_Labs OptContFac Mariner WBEEShop
  40m elog, Page 128 of 357  Not logged in ELOG logo
ID Date Author Type Categoryup Subject
  3461   Tue Aug 24 06:34:01 2010 AlastairUpdateGeneralElog...

...was down.  Have restarted it.

  3475   Fri Aug 27 07:21:13 2010 AlastairUpdateGeneralelog...

 was down.  I restarted the version in the 2.7.5 folder.  It went down again almost immediately but stayed up after the second restart.

  3567   Mon Sep 13 12:09:42 2010 kiwamuSummaryGeneralelog restarted

 Elog didn't respond, so I restarted it with the script.

Before killing the process somehow two elog daemons were running at the same time. I killed those two manually. 

  3605   Fri Sep 24 16:31:35 2010 steveConfigurationGeneralopen frame- rack is moved

The squeezing open frame rack was moved from the south side of the PSL enclosure to the north side of the SP table.

AC power breaker is PC-2  #1

 

Attachment 1: P1060881.JPG
P1060881.JPG
  3616   Tue Sep 28 14:12:14 2010 steveUpdateGeneralvertex crane drive is out of order

The vertex crane drive is overheating, it stopped functioning. Service man will be here tomorrow morning.

I crane was just turned  on for for may be  about 5 minutes. The vertical drive was fine for a while, but the horizontal did not worked at all.

The crane is tagged out again and the controller box is cooling down.

  3621   Wed Sep 29 15:34:46 2010 kiwamuUpdateGeneralfixing vertex crane
From Vertex crane -- fixing


Quote:

The vertex crane drive is overheating, it stopped functioning. Service man will be here tomorrow morning.

I crane was just turned  on for for may be  about 5 minutes. The vertical drive was fine for a while, but the horizontal did not worked at all.

The crane is tagged out again and the controller box is cooling down.

 

  3624   Thu Sep 30 09:34:58 2010 steveUpdateGeneralvertex crane trolly drive fixed

Quote:

The vertex crane drive is overheating, it stopped functioning. Service man will be here tomorrow morning.

I crane was just turned  on for for may be  about 5 minutes. The vertical drive was fine for a while, but the horizontal did not worked at all.

The crane is tagged out again and the controller box is cooling down.

 Atm1, Vertex crane controller unit on horizontal I-beam.

            Module CCES-407 1HP 2.3A 460V/3 phase on the right was replaced. Speed was increased  to 30 Hz

Atm2, See burned insulation on black wire that was shorting to the large suppressor resistor on Atm3 One can see the pit marks on the right end of it.

        This large power dissipater resistor got hot as the malfunctioning controller 407 broke down.   Touching black power wire insulation melted and made a short.

          So the heat was created and finally the fuses were blown. The unnecessary large fuses were replaced by small ones.

Fortunately we had one spare controller on hand that made this repair to be done fast.

We used the new Crane Safety Check list  from LIGO-E1000379-v1 the first time yesterday before doors were removed.

Attachment 1: P1060891.JPG
P1060891.JPG
Attachment 2: P1060887.JPG
P1060887.JPG
Attachment 3: P1060889.JPG
P1060889.JPG
Attachment 4: P1060893.JPG
P1060893.JPG
  3733   Mon Oct 18 09:01:48 2010 steveHowToGeneralHow not to

This BNC cable is crying for help. Please do not do this to me.  It should be reported  to the  abused center.Throw this cable into the garbage now.

Attachment 1: P1060926.JPG
P1060926.JPG
  3745   Wed Oct 20 16:41:41 2010 steveOmnistructureGeneral laser chiller leaving for MIT
Attachment 1: P1060929.JPG
P1060929.JPG
  3832   Mon Nov 1 10:17:55 2010 steveUpdateGeneralbreakers relabelled

Pedro of the electrical shop helped to retrace wires from the racks to the breakers. Many wrong labels were replaced. These labels are  still representing                          the south arm as Y and  the east arm as X.

Racks: 1X1,2,3,4 and 1Y3,4,5,6,7 and 9 are connected through manual disconnect swithes to  AC power breaker PC-1 on the west wall of IFO room 104.

             This panel PC-1 is connected to T1 isolation transformer in room 101 Panel L - # 38, 40, 42

Racks: 1Y1 & 2  psl and mc are connected through manual disconnect switches to AC power breaker PC-2 just west of the psl enclosure.

             This panel is connected to T2 isolation transformer in room 101 Panel L - # 32, 34, 36

Attachment 1: P1060970.JPG
P1060970.JPG
Attachment 2: P1060972.JPG
P1060972.JPG
Attachment 3: P1060975.JPG
P1060975.JPG
  3854   Wed Nov 3 16:49:31 2010 steveUpdateGeneralstorage cabinet is in place

The south end of IFO room 104 was reshuffled. The flow bench was moved all the way to the south end to create more room for the crane reach. The old  large drawing cabinet  was moved under the vacuum tube.

The new clear view through  Acrylic-plexyglass cabinet is anchored. It has powder finished coating so it will not out-gas too much.The back side shelf mounting holes are sealed off with kapton tape. The doors still needs some gaskit seals.

Attachment 1: P1070018.JPG
P1070018.JPG
  3862   Thu Nov 4 17:24:49 2010 steveUpdateGeneralconflat flanges for MIT

8 pieces of 10" CF blanks were shipped to MIT

Attachment 1: P1070020.JPG
P1070020.JPG
  3864   Thu Nov 4 17:57:27 2010 steveUpdateGeneralBeamScanner is working again

Koji, Suresh and Steve,

The beam scanner is back from repair.  Koji and Suresh helped to move the I/O address jumpers on the interface card from default position  300 to 320

It is working again.

Attachment 1: P1070024.JPG
P1070024.JPG
  3914   Sun Nov 14 02:59:31 2010 ranaConfigurationGeneralMEDM snapshots web page

Since Nodus is a Solaris machine it can barely handle doing the ImageMagick commands (such as convert and import). I removed the auto MEDM snapshot routine from it

awhile ago and I think the rate of ELOGD crashes has decreased, although its not definitive.

The snapshots have now been re-actived to run on MAFALDA, after I fixed the absolute pathnames in the scripts and installed (via yum) the packages that mafalda

needed to run this (Xvfb, openmotif, compat, etc.). The snapshots web page is now refreshing by itself and the statScreen/cronjob.sh is running on mafalda 5x per hour.

https://nodus.ligo.caltech.edu:30889/medm/screenshot.html

  4096   Thu Dec 23 22:13:50 2010 KojiUpdateGeneralPZT HV turned on

The four IOO PZTs have been turned on in order to confirm the alignment of the IFO.

Once they are turned on, the spots (ITMX/ITMY/PRM/SRM) on the REFL CCD have been easily found.

When the X-arm was aligned to the green beam, it is easily locked to TEM00. Also some LG modes were visible.
i.e. There is some room to improve the mode matching.
The transmitted green at the PSL table is a bit too high and clipped by the first mirror on the table.

No IR flashes were found in either arms.

------------------

The below are the range and the set values of the strain gauge readback for the PZTs.
When the closed loop buttons are activated the PZTs are fixed at those values, if no one touches the set point dials.

            Min   Max   SetP | Display on the module
PZT1 Yaw    2.20  9.95  6.08 | Broken
PZT1 Pitch -0.011 8.89  4.40 | 1.58

PZT2 Yaw    0.737 9.94  5.37 | 2.17
PZT2 Pitch  0.010 9.42  4.71 | 1.89

  4099   Fri Dec 31 12:41:02 2010 ranaUpdateGeneralIR flashes

I came in today to check up on the StripTool and burn the Ubuntu LTS (new CDS OS) DVD. I was pretty excited to see the PRM flashes on Mon1.

I waggled the PRM/BS alignments and got a good contrast MICH and then bright flashes in the PRM that totally overload Mon1's CCD.

Now I can see flashes of some IR junk in the X Arm; its way off on the left edge of the mirror, but there's a beam.

For the short term, we can hook up the IO PZTs to some old EPICS channels (like one of the AUX guys in the LSC area), but eventually it has to get hooked up to the new ASC or ASS. We have to bug Joe to see where this shows up in his master diagram.

**Note: if you get lost sometimes when doing the alignments, remember that you can use time_machine_conlog.

Ex:

rossa:general>./time_machine_conlog 2010/12/31,11:00:00 PDT C1:SUS-ITMX_PIT_COMM
Issuing the conlog command:
/cvs/cds/caltech/conlog/bin/conlog +epics -interp at 2010/12/31,11:00:00 PDT "C1:SUS-ITMX_PIT_COMM"


Conlog Replied:

LIGO controls: values at 2010 12/31 11:00:00 pst
 __Epics_Channel_Name______   __value_____
 C1:SUS-ITMX_PIT_COMM         0.406100



Restoring now...

Restoration Successful

Attached is the last 8 days of Vacuum Pressure trend which includes the pumpdown.

Attachment 1: Untitled.png
Untitled.png
  4142   Wed Jan 12 02:41:19 2011 kiwamuUpdateGeneraldaytime tasks for tomorrow

[Rana, Kiwamu]

Here is the list for the daytime tasks of tomorrow, Jan. 12th.

The daytime task is a work basically to be done or quitted before the sun goes down.

Along with the tasks, we roughly assigned the people who are responsible for it.

The tasks below are basically separated from each other, so we can work in parallel.

 

 

--- 1.  LSC analog interface check (Joe/Koji)

   * check whitening filter

   * demodulation board check

    * check ADC connections

 

--- 2.  MC2 coil Dewhitening (Joe)

    * fix binary outputs.

    * FM9 must be the trigger of the binary outputs instead of FM10.

 

--- 3. 11MHz modulation depth (Kiwamu)

   * investigate why the depth is so low

 

--- 4. PEM DAQ name issue (Jenne)

   * change the name of seismic channels properly so that we can deal with the calibrated stuff

 

--- 5. phase adjustment for MC-PDH locking (Suresh)

 

--- 6. medm screens for C1LSC ()

    * make screens

 

 

 

  4158   Fri Jan 14 17:58:50 2011 OsamuConfigurationGeneralStandalone RT setup

 I'll be gone to Hanford site next week and come back to Caltech on 24th's week.

I setup a standalone RT system at the desk around circuit stock in the 40m.

Please leave this setup until I come back. I'll keep working when I come back.

 

  4197   Tue Jan 25 00:09:54 2011 KojiUpdateGeneralJenne laser is at PSL Lab

I found Tara's elog entry that Jenne laser is at PSL Lab.
Since we recently use it frequently, we should be aware where it is now.

  4225   Sat Jan 29 00:31:05 2011 SureshUpdateGeneralVertex crane upgrade completed

The Vertex crane is smarter and safer now.  This upgrade ensures that the two sections of I-beam (8ft, 4ft) remain firmly latched to form a straight member till the latch is released.

In specific, it ensures that problems such as this one do not occur in the future.

 

The new safety features are:

When the I-beam sections are latched together, a pneumatic piston ensures that the latch is secure. 

If the latch is not engaged the trolley does not move outward beyond the end of the 8-foot section of the I beam.

If the trolley is out on the 4-foot section of the beam then we cannot disengage the latch.

 

How does it work?

 

 Vertex_Crane-2.png Vertex_Crane-4.png

 

The state of the Limit Switch 1 changes when the trolly goes past it.    The Limit Switch 2 gets pressed when the two sections are latched together.

The pneumatic piston raises or lowers the latch.  The Pneumatic Latch Switch operates a pneumatic valve controlling the state of the piston.

 

 

Vertex_Crane-3.png P1280545.JPG

The new controller now has Pneumatic Latch Switch in addition to the usual Start, Stop, Up, Down, In and Out buttons. 

Each of the Up, Down, In and Out buttons have two operational states:  Half pressed (low speed) and Full pressed (High Speed).  Their functions remain the same as before.

 

The new Pneumatic Switch:

When this switch is 'Engaged' and the 4 ft section is swung in-line with the 8 ft section, the two sections get latched together.

To unlatch them we have to throw the switch into the 'Disengage' state.  This makes the piston push the latch open and a spring rotates the 4 ft section about its pivot.

Limit Switch 2 is not pressed (I-beams not aligned straight) ==> Limit Switch 1 will prevent the trolley from out going beyond the 8 ft section.

While Limit Switch 2 is pressed we cannot disengage the latch.

 

Note: 

   The pneumatic piston requires 80psi of pressure to operate.  However we have only 40psi in the lab and the piston seems to operate quite well at this pressure as well.  I believe a request has been made to get an 80psi line laid just for this application.

 

Attachment 1: Vertex_Crane-2.png
Vertex_Crane-2.png
Attachment 2: Vertex_Crane-4.png
Vertex_Crane-4.png
  4235   Tue Feb 1 15:09:41 2011 KojiOmnistructureGeneralProjector - fixed

The projector in the controls room has been fixed the orange blinking of the status LED.

What we needed was to push "Volume -" and "Menu" for 5 sec.
This resets the timer of the lamp. When the timer reaches 2500 hours, it automatically start sabotaging.

We've got the spare lamp. It is in the top drawer of the computer cabinet on which the label makers are.

  4290   Mon Feb 14 17:16:47 2011 steveUpdateGeneralracks, breakers labeled

The south arm labels were changed from y to x to reflect reality.

So racks, manual disconnects and breakers now have their actual name. The east arm will be changed over tomorrow.

Please remove incorrect labels if you see any !

I can not find 1X4 breaker so it will be  traced.

  4297   Tue Feb 15 06:59:57 2011 Suresh, JenneOmnistructureGeneralX end enclosure left open

[Jenne, Suresh]

 Jenne found the X-end table enclosure had been left open.  She replaced the lid on it.

 

  4299   Tue Feb 15 11:53:02 2011 kiwamuSummaryGeneraltoday's missions

I think this week is going to be an "alignment week".

The goal is to get a good alignment on X arm for both the green and the IR beam in order to reduce a2l couplings.

 

Today's missions are :

 - fixing the oplev channel names (see here)

 - fixing the oplev gain issue (see here)

 - engage the oplev servos

 - f2p adjustment

 - make a realtime lockin model for the f2p measurement and the dithering technique

 - alignment of the MC incident beam  (because we installed a new PMC this morning)

 - manual alignment of the IR beam by steering PZT1 and PZT2 (this procedure will be replaced by an automatic way soon)

 - bounce roll filters (see here)

 

  4310   Thu Feb 17 00:43:13 2011 kiwamuSummaryGeneralto do list for tomorrow

Let's share our tasks !

 

==== daytime ===

 . mode matching for MC  (Jenne/Koji)

 . mode matching for doubling crystal on PSL table (Suresh/Koji)

 . f2p adjustment (Kiwamu)

 . fix daq and CDS issues (Joe)

 . increase oplev gain (low priority)

 . make ITMY camera nicer (Steve)

 . c1ass simlink model (Valera/Joe)

 . Bounce Roll notches (Suresh)

 

==== nighttime (after 7pm) ====

 . align everything   (at first green beam, then X arm cavity and finally IR beam)

 . update the noise spectrum of the green locking

 . estimate the noise from angle to length coupling

  4322   Fri Feb 18 00:35:21 2011 kiwamuSummaryGeneralto do list for Feb. 18th

DAYTIME

  -  more precise F2P measurement and modify lockin simlink model (Kiwamu)

  -  run  C1ASS to check it (Valera)

  -  take care of CDS (Joe)

  -  MC mode matching (Jenne/Koji)

   -  RF stuff  (Suresh)

  -  mode matching for doubling crystal at PSL table (low priority)

  -  OPLEV (low priority)

NIGHITTIME

 -  update the noise spectra of green locking

 -  make noise budgets

  4357   Fri Feb 25 13:28:14 2011 kiwamuSummaryGeneralto do list
 Because it maybe useful to share this kind of information among us, I just put a to-do-list which has been continuously noted in my laptop.
 I guess those items can be applied for the coming two months (i.e. March and April). Anything else ?

-- Alignment

     - C1ASS

           * finalize the model and make user friendly scripts and medm screens
           * adjustment of phase rotations
           * cavity auto alignment for green

     - MC WFS 

          * put sensing matrices
          * whitening ?

    - OPLEVs

        * binary output for OPLEV whitening
        * calibration of OPLEVs  [rad/count]
        * characterization of OPLEV servos
        * bigger trans impedance gains to have reasonable readouts


-- Optimization of Suspended Optics

  - diagonalizations

         * input matrices
         * f2p with higher precision

  - damping control

        * fix ETMY damping
         * Bounce Roll notches
         * Q adjustment for damping

  - upgrading of electronics

        * bigger trans impedance gain for OSEMs
        * widen the voltage range of AA filter boards
   

   - weekly check

       * a routine script for measuring free swinging spectra


-- Input Optics

   - PMC

         * mode matching
         * epics LO HI values

   - FSS and ISS

        * recover FSS
        * make ISS working

   - EOM

       * AM minimization
       * triple resonant box

   - doubling and RFPD for green

        * mode matching to doubling crystal
        * connect RFPD_DC_MON to ADC
        * string +/-150 V and +/-15power cables from 1X1 rack to RFPDs
        * visibility check and loss investigations for the beat RFPD
        * rearrange RF amplifiers (ZLN series) for the RFPD
        * realgin Jenne's DCPD

 

-- Length Sensing and Control

   - digital system and electronics

       * characterization of RFPDs ==> SUresh/UG
       * installation of RF generation box and distribution box ==> Suresh/U
       * new LSC model and start making useful scripts (csh ? perl ? python ?)
       * binary outputs for PD whitening
       * make item lists for ordering (?)
       * draw cool diagrams for RF cable distribution and map of LSC rack.


-- Green Locking

    - X end station

           * eliminate undesired multiple spots on RFPD
           *  connect REFLPD_DCMON to ADC
           *  remote local boost
           * demodulation phase adjustment
           *  look for a high voltage amp. (bipoler)
           * installation of a mechanical shutter
           *  ETMX_TRANS CCD camera
           * analog low pass filter for temperature control

    - Y arm green locking ==> Suresh/Bryan

        * item lists
        * preparation of base mounts
        * mode matching estimation
        * mode measurement of input beam from Lightwave
        * temeperature scanning for beat location finding with IR beam
        * Installation
       * modification of PDH box

    - digital control systems

           * user friendly medm screens
           * apply proper filters for AC-DC whitened signal blending
           * add MC2 feedback path

      - noise budget

          * in-loop and out-of-loop evaluation
          * shot noise  
          * RFPD noise modeling
          * how intensity noise couples through MFD
          * electrical noise
          * frequency noise contribution from end laser and PSL
          * calibration of arm PDH signal

   - cavity scan and handing off

         * optimization of open loop transfer function for ALS
         * auto scripts   

-- misc.

   - CCD camera
        * color filters to separate IR and green (?)
   - lab laptops
        * a laptop for each end station (?)
    - dichroic TT (?)
        * large wegded and AR coated for 532nm (?)
    - epics for RS232C      
        * RS232C for doubling oven temperature

 

  4359   Fri Feb 25 14:50:16 2011 KojiSummaryGeneralto do list

- Put priority on the list

- Put names on the items

- Where is the CDS TO DO ==> Joe

-

- Remote disconnection of the greeen PDH 

- What is the situation of the PD DC for the LSC PDs?

- SUS Satelite box Resister replacement ==> Jamie

- IMC mode matching ==> Jamie/Larisa 

- Mechanical shutters everywhere

- SRM OPLEV Connection

- MC OAF

- Better LSC whitening boards

- DAFI 

Quote:
 Anything else ?

  4364   Mon Feb 28 11:22:40 2011 josephbSummaryGeneralto do list
Quote:

- Where is the CDS TO DO ==> Joe

CDS To Do:

1) Get ETMY working - figure out why signals are not getting past the AI board (D000186) to the coils.

2) Get TDS and command line AWG stuff working

3) Get c1ass and new c1lsc (with Koji) fully integrated with the rest of the system.

4) Get CDS software instructions up to date and well organized.

5) Redo cabling  and generally make it a permanent installation instead of hack job:

   a) Measure cable lengths, check connectors, wire with good routes and ensure strain relief.  Ensure proper labeling

   b) Get correct length fiber for c1sus RFM and timing.

   c) Fix up final BO adapter box and DAC boxes.

   d) Make boxes for the AA filter adapters which are currently just hanging.

   e) Get two "faceplates" for the cards in the back of the ETMY IO chassis so they can screwed down properly.

   f) Remove and properly store old, unused cables, boards, and anything else.

6) Create new documentation detailing the current 40m setup, both DCC documents and interactive wiki.

7)  Setup an Ubuntu work station using Keith's wiki instructions

 

Simulated Plant To Do:

1)Create simulated plant to interface with current end mass controls (say scx).

2) Create proper filters for pendulum and noise generation, test suspension.

3) Propagate to all other suspensions.

4) Working on simulated IFO plant to connect to LSC.  Create filters for near locked (assume initial green control perhaps) state.

5) Test LSC controls on simulated IFO.

6) Fix c code so there's seamless switching between simulated and real controls.

CDS Status:

MC damp dataviewer diaggui AWG c1lsc c1ioo c1sus c1iscex c1iscey RFM The Dolphins Sim.Plant Frame builder TDS Cabling
                             
  4371   Wed Mar 2 22:57:57 2011 sureshSummaryGeneralStuff from LLO

Here is a partial list of stuff which is being packed at LLO to be shipped to CIT.  The electronics ckt boards are yet to be added to this list.  Will do that tomorrow.

 

 

Attachment 1: eLIGO_items_from_LLO_for_Caltech.xls
  4381   Mon Mar 7 17:58:14 2011 sureshSummaryGeneralStuff from LLO

Here is the updated list. These lists were used as packing lists and therefore are organised by Box #.
Attachment 1: eLIGO_items_from_LLO_for_Caltech_Sheet1.pdf
eLIGO_items_from_LLO_for_Caltech_Sheet1.pdf eLIGO_items_from_LLO_for_Caltech_Sheet1.pdf eLIGO_items_from_LLO_for_Caltech_Sheet1.pdf eLIGO_items_from_LLO_for_Caltech_Sheet1.pdf eLIGO_items_from_LLO_for_Caltech_Sheet1.pdf eLIGO_items_from_LLO_for_Caltech_Sheet1.pdf
  4405   Fri Mar 11 16:30:42 2011 steveUpdateGeneralhigh speed servo unit is here

New Focus Servo Controller has just arrived. We have 25 days to evaluate this product.

It will have to be shipped back to the vendor on April 4, 2011 the latest in order to get full refund.

Attachment 1: P1070462.JPG
P1070462.JPG
  4412   Fri Mar 18 14:18:00 2011 kiwamuSummaryGeneralnew laser pointers

Just for a record. We got 4 new laser pointers (2 greens, 1 blue, and 1 green and red combination). Don't lose them.

They reside in a bucket on the SP table, where IR viewers and sensor cards also reside.

DSC_2883_ss.jpg

  4433   Wed Mar 23 14:19:35 2011 KojiSummaryGeneralGrand Plan

This is the grand plan we talked about in the beginning of the meeting.

  • (Kiwamu) X-end Green cleaning up / Prep for DRMI
  • (Bryan) Y-end Green
  • (Suresh) Help Bryan / RF (w. Kevin)
  • (Jenne) MC WFS / Y-arm IR alignment / MC adaptive feedforward (incl. CDS)
  • (Koji) LSC
  • (Joe) CDS cleaning up
  • (Jamie) Help Joe / Noise Budget
  • (Larisa) PMC scan / PSL photo&diagram
  • (Barbarela) ASS
  4458   Tue Mar 29 22:29:16 2011 kiwamuUpdateGeneralsome tasks tomorrow

 *  Temporary strain relief for the heliax cables on 1X2 (Steve)

 *  RF diagrams and check lists (Suresh)

      => In the lunch meeting we will discuss the details about what we will do for the RF installation.

 *  Electronics design and plan for Green locking (Aidan / Kiwamu)

      => In the lunch meeting we will discuss the details.

 *  LSC model (Koji)

 *  Video cable session (team)

 * LPF for the laser temperature control (Larisa)

  4461   Wed Mar 30 16:57:13 2011 kiwamuUpdateGeneralturned off c1aux

[Steve / Kiwamu]

 As a part of the video cable session, we reconnected some power cords on 1Y1 rack.

During the work we momentarily turned off c1aux, which handles DMF, Illumintators, mechanical shutters and the old video epics.

I think it automatically reverted the things, but we may need to check them.

  4475   Thu Mar 31 11:30:51 2011 steveConfigurationGeneralstrain relieved rf cables

I strain relieved RF cables labeled 33 MHZ LO and 166 MHZ to EOM at 1X2  This is a temporary setup for the 11 MHZ

The coax N  bulkheads connectors are mounted on the plastic front panel now.

Attachment 1: P1070491.JPG
P1070491.JPG
  4488   Tue Apr 5 17:31:59 2011 steveSummaryGeneralnew laser pointers

Quote:

Just for a record. We got 4 new laser pointers (2 greens, 1 blue, and 1 green and red combination). Don't lose them.

They reside in a bucket on the SP table, where IR viewers and sensor cards also reside.

DSC_2883_ss.jpg

 Low power green-red laser pointers are in. High power green, red and blue pointers are confiscated.

Attachment 1: P1070530.JPG
P1070530.JPG
  4515   Tue Apr 12 12:01:30 2011 josephbUpdateGeneralIFO controls, now with 10% less lying (ITMX/ITMY controls swapped)

The ITMX/ITMY control swap is complete.

The steps from this elog were followed.

In addition, I did a burt restore of c1sus, c1mcs.

I then swapped all the gain settings from ITMX to ITMY, and reenabled the watchdogs.

I did some basic kick tests (1000 counts into UL coil) and confirmed channels like C1:SUS-ITMX_ULPD_VAR (watchdogs mV readback) corresponded to the correct optic.  I also checked that the POS, PIT, YAW, SIDE produced reasonable damping when engaged.

  4516   Tue Apr 12 16:01:33 2011 josephbUpdateGeneralRFM errors

Problem:

Currently the c1scy, c1mcs, and c1rfm models are reporting an error with receiving some data sent over the GE Fanuc Reflected memory cards.

To be more exact, the C1:SUS-ETMY_ALS signal from the c1gcv FE code on the c1ioo computer going too the Y end is not being received However, the C1:SUS-ETMY_LSC signal is.  So the physical RFM card seems to be working.

Similarly, the TRY signal is being sent correctly from the Y end computer.  The X end is working fine and receiving both LSC and ALS signals.

The c1mcs and c1rfm models also receive data from the c1ioo computer and reporting receiving errors.

Theory:

Because the RFM cards are transmitting and receiving at least some channels, I'm guessing there was changes made to the C1.ipc file, which defines the memory locations of these various channels on the RFM network, and that when a model was rebuilt, a different one using the previous IPC file was not, and thus one of the computer is going to the wrong place to either read or write data.

Tomorrow, I'm planning on the  following:

1) Clean out the C1.ipc file (/opt/rtcds/caltech/c1/chans/ipc/)

2) Rebuild all models

3) Run activate_daq.py script

4) Restart models via script

If this doesn't clear up the problem, I'll continue  to bug hunt.

  4629   Wed May 4 15:56:09 2011 valeraSummaryGeneralPSL and MC trends

The attached plot shows 2 day trends of the PMC and MC reflected and transmitted power, the PSL POS/ANG QPD signals, and the temperature measured by the dust counter.

The power step in the middle of the plot corresponds to Koji/Jenne PMC realignment yesterday.

It looks like everything is following the day/night temperature changes.

Attachment 1: pslmcdrift.pdf
pslmcdrift.pdf
  4649   Fri May 6 01:27:12 2011 KojiSummaryGeneralaLIGO BBPD / Green PD investigation

Minicircuits ERA-5SM was used for the RF amp of the BBPD. This amp is promising as a replacement of Teledyne Cougar AP389
as ERA-5SM gave us the best performance so far among the BBPDs I have ever tested for the aLIGO BBPD/Green.

The -3dB bandwidth of ~200MHz and the noise floor at the shotnoise level of 0.7mA DC current were obtained.


1. Introduction

The aLIGO BBPD candidate (LIGO Document D1002969-v7) employs Teledyne Cougar AP389 as an RF amplifier.
This PD design utilizes the 50Ohm termination of the RF amp as a transimpedance resistance at RF freq.

However, it turned out that the bandwidth of the transimpedance gets rather low when we use AP389, as seen in the attachment2.
The amplifier itself is broadband upto 250MHz (the transfer function was confirmed with 50Ohm source).
The reason is not understood but AP389 seems dislike current source. Rich suggested use of S-parameter measurement
to construct better model of the curcuit.

On the other hand, the RF amplifiers from Minicircuits (coaxial type like ZFL-1000LN+), in general, exhibit better compatibility with PDs.
If you open the amplifier case, you find ERA or MAR type monolithic amplifiers are used.

So the question is if we can replace AP389 by any of ERA or MAR.

2. Requirement for the RF amp

- The large gain of the RF amp is preffered as far as the output does not get saturated.

- The amplifier should be low noise so that we can detect shot noise (~1mA).

- The freq range of the useful signal is from 9MHz to 160MHz.

The advanced LIGO BBPD is supposed to be able to receive 50mW of IR or 15mW of 532nm. This approximately corresponds to
5mA of DC photocurrent if we assume FFD-100 for the photodiode. At the best (or worst) case, this 5mA has 100% intensity modulation.
If this current is converted to the votage through the 50Ohm input termination of the RF amp, we receive -2dBm of RF signal at maximum.

This gives us a dilemma. if the amp is low noise but the maximum output power is small, we can not put large amount of light
on the PD. If the amp has a high max output power (and a high gain), but the amp is not low noise, the PD has narrow power range
where we can observe the shotnoise above the electronics noise.

What we need is powerful, high gain, and low noise RF amplifier!

Teledyne Cougar AP389 was almost an ideal candidate before it shows unideal behavior with the PD.
Among Minicircuits ERA and MAR series, ERA-5 (or ERA-5SM) is the most compatible amplifier.


AP389 ERA-5
Freq Range 10-250MHz DC-4GHz
Gain >24.5dB 20dBtyp
Output power (1dB compression)
23dBm 18.4dBm
IP3 36dBm 33dBm
Noise Figure <3.3dB 3.5dB

Considering the difference of the gain, they are quite similar for our purpose. Both can handle upto -2dBm,
which is just the right amount for the possible maximum power we get from the 5mA of photocurrent.

3. Test circuit with ERA-5SM

A test circuit has been built (p.1 attachment #1) on a single sided prototype board. 

First, the transfer function was measured with FFD-100. With the bias 100V (max) the -3dB bandwidth of ~200MHz was observed.
This decreases down to 75MHz if the bias is 25V, which is the voltage supplied by the aLIGO BBPD circuit. The transimpedance
at the plateau was ~400Ohm.

Next, S3399 was tested with the circuit. With the bias 25V and 30V (max) the -3dB bandwidth of ~200MHz was obtained although
the responsivity of S3399 (i.e. A/W) at 1064nm is about factor of 2 smaller than that of FFD-100.

The noise levels were measured. There are many sprious peaks (possibly by unideal hand made board and insufficient power supply bypassing?).
Othewise, the floor level shows 0.7mA shotnoise level.

Attachment 1: PD_response.pdf
PD_response.pdf PD_response.pdf PD_response.pdf PD_response.pdf
Attachment 2: FFD-100_AP389_MCL.pdf
FFD-100_AP389_MCL.pdf
  4658   Sat May 7 12:57:54 2011 KojiSummaryGeneralaLIGO BBPD / Green PD investigation

The RF amplifier of the prototype BBPD has been replaced from ERA-5SM to MAR-6SM.
The bandwidth is kept (~200MHz for S3399 with 30V_bias), and the noise level got better
while the maximum handling power was reduced.

MAR-6SM is a monolithic amplifier from Minicircuits. It is similar to ERA-5SM but has lower noise
and the lower output power.


AP389 ERA-5 MAR-6
Freq Range 10-250MHz DC-4GHz DC-2GHz
Gain >24.5dB 20dBtyp 21.8dBtyp
Output power (1dB comp.)
+23dBm +18.4dBm +3.7dBm
IP3 36dBm 33dBm 18.1dBm
Noise Figure <3.3dB 3.5dB 2.3dB

The noise floor corresponds to the shotnoise of the 0.4mA DC current.
Now the mess below 50MHz and between 90-110MHz should be cleaned up.
They are consistently present no matter how I change the PD/RF amp (ERA<->MAR)/bias voltage.

I should test the circuit with a different board and enhanced power/bias supply bypassing.


Discussion on the RF power (with M. Evans)

- Assume 5mA is the maximum RF (~50mW for 1064nm, ~15mW for 532nm). This is already plenty in terms of the amount of the light.

- 100% intenisty modulation for 5mA across 50Ohm induces -2dBm RF power input for the amplifier.

- Assume if we use MAR-6 for the preamplifier. The max input power is about -18dBm.
  This corresponds to 16% intensity modulation. It may be OK, if we have too strong intensity modulation, we can limit the power
  down to 0.8mA in the worst case. The shot noise will still be above the noise level.

- In the most of the applications, the RF power is rather small. (i.e. 40m green beat note would expected to be -31dBm on the RF amp input at the higherst, -50dBm in practice)
So probably we need more gain. If we can add 10-12dB more gain, that would be useful.

- What is the requirement for the power amplifier?

  • Gain: 10~12dB
  • Output (1dBcomp): +3dBm +Gain (13dBm~15dBm)
  • Noise level / Noise Figure: 3nV/rtHz or NF=14dB
    The output of MAR-6 has the votage level of ~7nV/rtHz. If we bring the power amplifier with input noise of ~3nV/rtHz,
    we can surppress the degradation of the input equivalent noise to the level of 10%. This corresponds to N.F. of 14dB.

Search result for Freq Range 10-200MHz / Max Gain 14dB / Max NF 15dB / Min Power Out 13dBm
GVA-81 is available at the 40m. ERA-4SM, ERA-6SM, HELA-10D are available at Downs.

Model Name Frequency [MHz] DC Power Case Style Price
[$]
Low High Current [mA] Volt [V]
SORT
 
ERA-4 DC 4000 65 4.5 VV105
ERA-4SM DC 4000 65 4.5 WW107
ERA-4XSM DC 4000 65 4.5 WW107
ERA-6 DC 4000 70 5 VV105
ERA-6SM DC 4000 70 5 WW107
GALI-6 DC 4000 70 5 DF782
GVA-81+ DC 7000 112 5 DF782
HELA-10C 5 450 525 12 CM624
HELA-10D 8 300 525 12 CM624

GVA-81 ERA-4SM ERA-6SM GALI-6
Freq Range DC-6GHz DC-4GHz DC-4GHz DC-4GHz
Gain 10.5dB 13.7dB 12.6dB 12.2dB
Output power (1dB comp.)
+19dBm +17.5dBm +17.1dBm +18.2dBm
IP3 42dBm 36dBm 36.5dBm 35.5dBm
Noise Figure 7.3dB 4dB 4.4dB 4.5dB

 


Conversion between nV/rtHz and NF (in the 50Ohm system)

SN1: Connect signal source (50Ohm output) to a 50Ohm load.
Power ratio between the noise and the signal

SN1 = (4 k T (R/2)) / (S/2)^2

SN2: Connect signal source (50Ohm output) to an RF amp.
Only the voltage noise was considered.

SN2 = (4 k T (R/2) + Vn^2) / (S/2)^2

10 Log10(SN2/SN1) = 10. Log10(1 + 2.42 (Vn / 1nVrtHz)^2)

e.g.
Vn: 0 nVrtHz ==> 0dB
Vn: 0.5 nVrtHz ==> 2dB
Vn: 1 nVrtHz ==> 5dB
Vn: 2 nVrtHz ==> 10dB
Vn: 3 nVrtHz ==> 13.5dB

Attachment 1: PD_response.pdf
PD_response.pdf PD_response.pdf PD_response.pdf
  4676   Tue May 10 09:05:49 2011 KojiUpdateGeneralaLIGO BBPD / Green PD investigation

BBPD update

- The BBPD circuit has been constructed on the aLIGO BBPD board

- It still keeps 200MHz BW with FDD-100 Si PD for the 100V bias.

- The noise spectrum has been cleaned up a lot more. It shows the noise level of the 0.4mA shotnoise between 9-85MHz.
The noise at 160MHz is the noise level of the 1mA shotnoise.

Some of the noise peaks at around 97MHz came from the bias voltage.

What to do next

- Confirmation of the performance with the original aLIGO BB PD configuration.

- Notch filter for 9MHz (for aLIGO).

- Implementation of a power amplifier. (issues: power supply and heat removal)

Attachment 1: PD_response.pdf
PD_response.pdf PD_response.pdf PD_response.pdf
  4701   Thu May 12 09:00:23 2011 steveUpdateGeneraloptical table covers must be used

I found ITMX-ISCT and BS-ISCT ( IFO sensing-control table)  not covered this morning. Please do not leave tables open.

  4727   Mon May 16 15:46:05 2011 KojiUpdateGeneraloptical layout viewable on the online version of autocad

I have made my own AutoCAD WS account and put the latest 40m layout.
AutoCAD WS is a free cloud service which enable us to browse/edit the DWG files.

You can view/play/print it from the following link even without making the account.

https://www.autocadws.com/main/publish?link=RVFmNEtOd3EzNVFtRXcx

If you make your account you can actually save it although the editing capability is somewhat limited.

Notes:
- It needs the Flash plug-in and Internet connection.
- I think Safari is the most stable platform on Mac. (i.e. I had some malfunctions with Firefox and Chrome)

  4778   Wed Jun 1 21:56:43 2011 KojiUpdateGeneralaLIGO BBPD / Green PD final result

Here is the conclusive result for the circuit configuration for aLIGO BBPD and 40m Green PD.

- Use Mini-circuits MAR-6SM for the RF preamplifier. The 50Ohm input impedance is used for the RF transimpedance.
  The maximum output is ~4dBm.

- Use Mini-circuits GALI-6 for the RF middle power amp. The gain is 12dB and the amplifier is linear up to +17dBm. i.e. This is still linear at the maximum output level of MAR-6SM.

- The total RF transimpedance is ~2k. The DC transimpedance is also 2k.

- The bandwidth is 80MHz with FFD100 and internal 25V bias. When S3399 is used, the bandwdith goes up to 180MHz
although the responsivity of FFD100 at 1064nm is better than S3399 by a factor of 1.5. At the 40m we will use S3399 for the green BB PD.

- By adding an LC network next to the PD, one of the unnecessary signal can be notched out.
As an example, 9MHz notch was placed for the FFD100 case.

- Noise level: ~10pA/rtHz as a floor noise level at around 30MHz. This corresponds to the equivalent dark current of 0.4mA.


Matt has finished the PCB layout. We will order small first batches, and stuff it for the test. Some of these will be the 40m green PD.

Attachment 1: PD_response.pdf
PD_response.pdf PD_response.pdf PD_response.pdf PD_response.pdf PD_response.pdf PD_response.pdf
Attachment 2: linearity_GALI_6.pdf
linearity_GALI_6.pdf
  4824   Wed Jun 15 15:18:01 2011 kiwamuUpdateGeneralWednesday cleaning

[Jenne / Kiwamu]

We spent approximately an hour for the weekly Wednesday cleaning.

This time we moved onto an area where a desk and optics shelf reside along the Y arm.

We will continue cleaning up there in the next time too.

  4835   Mon Jun 20 00:59:02 2011 kiwamuSummaryGeneralWeekly report
This is a summary for the week ending June 19th. Feel free to edit this entry.
(Number of elog entries = 27)

* Refinement of LSC screen
    -> Kissel buttons and some indicators were newly installed
    -> A script to autonatically generate kissel buttons was made

* New BIO installed on ETMY

* LightWave for ABSL
    -> taken out from the MOPA box and put on the AP table with temporary use of the Y end laser controller
 
* Shipping 2 RFPDs to LLO
 
* LEDs on the BIO for the vertex suspensions were blown
    -> fixed and re-installed. A test script will be prepared
 
* PEM AA board was fixed
 
* A plot of the MICH noise was produced for the first time
 
* Schnupp asymmetry measurement : Las = 3.64+/-0.32cm
 
* The photo diode on WFS2 has been replaced by YAG-444-4A
 
* SUS binary IO crates were taken out
 
* Fiber died
     ->C1LSC was unable to communicate to C1SUS. Installing a new copper Dolphine fixed the issue.
 
* SURF students came
  4856   Wed Jun 22 17:35:35 2011 IshwitaUpdateGeneralHot air station

This is the new hot air station for the 40m lab.........

 

Attachment 1: P6220212.JPG
P6220212.JPG
Attachment 2: P6220213.JPG
P6220213.JPG
ELOG V3.1.3-