Entry  Wed Feb 5 15:39:41 2014, manasa, Update, General, We are pumping down pre_pump_down.png
    Reply  Wed Feb 5 19:36:50 2014, Steve, Update, VAC, pumpdown at 25 Torr pd77at3.5h.png
       Reply  Wed Feb 5 19:53:51 2014, Steve, Update, VAC, pumpdown stops for the day at 14 Torr stopHere.png
          Reply  Thu Feb 6 11:14:07 2014, Steve, Update, VAC, pumpdown completed pd77.png
             Reply  Mon Feb 10 09:45:53 2014, Steve, Update, VAC, vacuum normal is reached pd77m5d.png13daysAtm.png
                Reply  Tue Feb 11 10:44:15 2014, Steve, Update, VAC, RGA scan at day 6 pd77m6d.png
                   Reply  Tue Feb 18 10:38:55 2014, Steve, Update, VAC, RGA scan at day 13 pd77m13d.pngRGAscan13d.png
                      Reply  Wed Mar 12 08:40:42 2014, Steve, Update, VAC, RGA scan at day 35 pd77m35d.png
                         Reply  Mon Mar 24 10:41:46 2014, Steve, Update, VAC, RGA scan at day 50 pd77m50dRGA.png
                Reply  Fri Mar 7 16:13:03 2014, Steve, Update, VAC, pumping speed is recovered pumpingSpeed.png
Message ID: 9604     Entry time: Wed Feb 5 19:36:50 2014     In reply to: 9602     Reply to this: 9605
Author: Steve 
Type: Update 
Category: VAC 
Subject: pumpdown at 25 Torr 

Quote:

[Steve, Manasa]

I checked the alignment one last time. The arms locked, PRM aligned, oplevs centered.

We went ahead and put the heavy doors ON. Steve is pumping down now!

 The ion pumps were vented just before pumpdown and their gate valves were opened.

This is an effort to minimize a possible leak through their gates.

Is there a volunteer who goes home late and would close off the roughing? tonight

Attachment 1: pd77at3.5h.png  205 kB  | Hide | Hide all
pd77at3.5h.png
ELOG V3.1.3-