Entry  Tue Jul 23 22:55:13 2013, Jenne, Update, VAC, BS, ITMY doors to be opened in the morning 
    Reply  Wed Jul 24 10:35:41 2013, Steve, Update, VAC, BS, ITMY doors are removed beforeDoorsOff.pngparticlecount10d.png
       Reply  Mon Jul 29 16:04:40 2013, Steve, Update, VAC, AC removed acout.pngAlAcACa.jpgAlAcACb.jpg
          Reply  Mon Jul 29 16:15:13 2013, Koji, Update, VAC, AC removed 
          Reply  Mon Aug 5 10:50:48 2013, Steve, Update, VAC, RGA background v75bgMd12.png
             Reply  Tue Aug 6 10:06:29 2013, Steve, Update, VAC, Pumpdown is at 500Torr befPd.png
                Reply  Tue Aug 6 16:45:31 2013, Steve, Update, VAC, Pumpdown is completed 8hrPd76.png1mT.png
                   Reply  Wed Aug 7 10:51:49 2013, Steve, Update, VAC, Pumpdown at 26hrs 26hr.png14datm.png
                      Reply  Wed Aug 7 15:36:29 2013, Steve, Update, VAC, TP2 drypump replaced forelinesPs.jpg
                         Reply  Thu Aug 8 07:57:23 2013, Steve, Update, VAC, pumpdown at 48 hrs 48hrsPd76.png
                            Reply  Thu Aug 8 10:31:28 2013, Steve, Update, VAC, few reminders of this vent GROUND!.jpgbad_Folding.jpgtoomuchred.jpgBETTERholder.jpg
                               Reply  Wed Aug 28 11:23:41 2013, Steve, Update, VAC, crane repair sheduled 
                               Reply  Thu Sep 5 10:47:58 2013, Steve, Update, VAC, vertex crane folding issue 5mmLess.jpg
                                  Reply  Mon Sep 9 15:33:06 2013, Steve, Update, VAC, vertex crane repair is scheduled 
                                  Reply  Wed Sep 18 14:57:12 2013, Steve, Update, VAC, vertex crane folding arm removed manPower.jpgrotatingHinge.jpgsupportingHinge.jpggullingPin.jpg
                                     Reply  Fri Sep 20 16:37:30 2013, Steve, Update, VAC, vertex crane folding arm is back on bushingBottom.jpgfoldingI.jpgnoLoadGap.jpgtrollyway.jpgtrollySee.jpg
                                        Reply  Mon Sep 30 08:53:22 2013, Steve, Update, VAC, vertex crane repair schedule has changed 
                                        Reply  Wed Oct 2 14:25:39 2013, Steve, Update, VAC, vertex crane is still out of order grindingIbeam.jpgcableMoved.jpg500lbs@end.jpg
                                           Reply  Thu Nov 7 11:19:04 2013, Steve, Update, VAC, crane work POSTPONED to Monday 
                                           Reply  Wed Nov 13 08:46:03 2013, Steve, Update, VAC, vertex crane repair completed 
                            Reply  Wed Aug 14 08:24:20 2013, Steve, Update, VAC, pumpdown at day 8 pd76md8.png
                               Reply  Mon Aug 19 11:12:54 2013, Steve, Update, VAC, RGA scan at day 13 rgaScan13d.png
                                  Reply  Wed Aug 28 15:41:42 2013, Steve, Update, VAC, RGA scan at day 23 pd75md23.png
                                     Reply  Fri Sep 6 09:27:10 2013, Steve, Update, VAC, 31 days after pumpdown day31vac.png
                                        Reply  Tue Sep 10 09:18:22 2013, Steve, Update, VAC, dry pump is getting loud 
                                           Reply  Tue Sep 10 15:43:01 2013, Steve, Update, VAC, TP3' dry pump is replaced 
                                     Reply  Mon Sep 16 10:57:11 2013, Steve, Update, VAC, RGA scan at day 41 pd76m41dRGA.pngpd76m41d.png
                                        Reply  Wed Oct 9 11:48:10 2013, Steve, Update, VAC, RGA scan at day 65 scanRGApd76m65d.pngpd76m65d.png
                                           Reply  Fri Nov 22 16:32:08 2013, Steve, Update, VAC, RGA scan at day 108 RGAscanVacNormal108d.pngday108.pngpd76m110d.png
                         Reply  Tue Apr 29 16:42:29 2014, Steve, Update, VAC, TP2 drypump replaced dryforepumpreplaced.png
                            Reply  Tue Dec 23 15:37:32 2014, Steve, Update, VAC, TP3 drypump replaced 
                               Reply  Mon Sep 14 10:41:03 2015, Steve, Update, VAC, TP2 dry pump replaced TP2_dry_pump_replaced.png
                                  Reply  Mon Sep 21 11:12:14 2015, Steve, Update, VAC, cold cathode is flaky cc4jumps.png
                                     Reply  Tue Sep 22 08:58:38 2015, Steve, Update, VAC, cold cathode is flaky 4and80days.png
                                        Reply  Fri Sep 25 17:00:38 2015, Steve, Update, VAC, cold cathode is flaky flakyCC4.png
Message ID: 9011     Entry time: Wed Aug 14 08:24:20 2013     In reply to: 8984     Reply to this: 9029
Author: Steve 
Type: Update 
Category: VAC 
Subject: pumpdown at day 8 

 

 

Attachment 1: pd76md8.png  112 kB  | Show | Show all
ELOG V3.1.3-