Mon Jul 22 16:30:31 2013, Koji, Update, General, Vent preparation
|
Mon Jul 22 16:56:14 2013, Jenne, Update, General, Vent preparation - In progress
|
Mon Jul 22 17:03:25 2013, Jenne, Update, General, MC spot positions
|
Tue Jul 23 04:26:54 2013, Jenne, Update, General, MC spot positions
|
Mon Jul 22 18:49:16 2013, Jenne, Update, General, Vent preparation - In progress
|
Mon Jul 22 21:23:04 2013, manasa, Update, General, Vent preparation - In progress
|
Tue Jul 23 03:10:57 2013, Koji, Update, General, Vent preparation - In progress 
|
Tue Jul 23 03:43:32 2013, manasa, Update, General, Vent preparation - In progress
|
Tue Jul 23 04:22:03 2013, Koji, Update, General, Vent preparation - In progress
|
Tue Jul 23 04:31:36 2013, Jenne, Update, General, Vent preparation - Ready for Vent
|
Tue Jul 23 08:21:31 2013, Steve, Update, VAC, Vent has started 
|
Tue Jul 23 14:00:03 2013, Steve, Update, VAC, the vent is completed  
|
|
Message ID: 8898
Entry time: Tue Jul 23 03:10:57 2013
In reply to: 8894
|
Author: |
Koji |
Type: |
Update |
Category: |
General |
Subject: |
Vent preparation - In progress |
|
|
Centering of the oplev beams: done
Recording the OSEM values: done |
|
|
|
|