Entry  Sat May 5 01:24:07 2012, Den, Update, PSL, PMC whitening.jpgmcf_v.png
    Reply  Sat May 5 09:13:02 2012, Koji, Update, PSL, PMC 
       Reply  Sat May 5 10:20:21 2012, Den, Update, PSL, PMC 
          Reply  Sat May 5 12:23:38 2012, Koji, Update, PSL, PMC 
Message ID: 6605     Entry time: Sat May 5 09:13:02 2012     In reply to: 6604     Reply to this: 6606
Author: Koji 
Type: Update 
Category: PSL 
Subject: PMC 

I suspect that it was just unlocked when you had disconnected the cable.

There is not reflection now. It seems that it is now misaligned after the alignment work.

So what you need is "align while scanning PZT -> lock -> align".

Quote:

Unfortunately, after the measurement when I unplugged BNS connector from the laser, I misaligned PMC. For several hours I adjusted the mirrors but could not significantly improve transmitted signal. I'll return to this issue tomorrow.

 