June 22-June 24:
1.Coupling light into fibre at the ETMY.
2.Routing of the fibre to the PSL table.
June 27-June 30:
1.PSL optical table layout sketching.
2.Combining the PSL beam with fibre output onto a BS and then superpose them on a New Focus 1611 PD.
July 5-July 8:
1.Conversion of the PD output to voltage using MFD(Mixer Frequency Discriminator).
2. Report writing.
July 7: 5:00 pm: 1st Report Due.
July 11-July 22:
1.Locking Y-arm to PSL.
2.Setting up the feedback loop using the MFD output as the error signal and acting on the AUX laser frequency.
July 25-Aug 5:
1.Y-Arm cavity characterisation.
Measurement of the transmission of IR and green light through the cavity.
2.Analysis.
To obtain FSR, Finesse,Loss of the Cavity, Visibility, Transverse Modes(g-factor, astigmatism), Reflectivity, Q-factor.
3.Report and abstract writing.
Aug 1: 5:00 pm: 2nd Report and absract due.
Aug 8-11:
Preparation for talk and seminar. |