Bertine Robby, Bertin and Jerry completed the installation by pouring concrete yesterday and cleaning up today.
Atm1-2, steel bars, grouted feet and side forms are ready
Atm3, bounding agent is applied for better bounding
Atm4, pumping concrete
Atm5, shaker is used to fill-all
Atm6, late after noon the forms- sides were removed, NOTE: actual table to concrete distance is 12.75"
Atm7, construction people left and the tile man is on the way
The tile patching should complete today so tomorrow we can remove plastic covers.
|