Entry  Tue Aug 17 14:09:15 2010, steve, Update, PEM, PSL optical table schedule  
    Reply  Wed Aug 18 16:42:14 2010, steve, Update, PEM, PSL optical table legs load balanced P1060671.JPGP1060674.JPGP1060670.JPGP1060676.JPG
Message ID: 3430     Entry time: Tue Aug 17 14:09:15 2010     Reply to this: 3435
Author: steve 
Type: Update 
Category: PEM 
Subject: PSL optical table schedule  

Tuesday, 17 August : fill tunnel, set table height, level table and balance load

Wednesday : grout tripod legs and leave it alone

Thursday : built  guide-form for concrete

Friday :  pour concrete

Monday, 23 August : remove guide forms and clean up