Subject: Cable removal from the control room 

[Alberto, Kiwamu, and Koji]

We removed the BNC cables from the control room.
The work was as hard as the one I had when I swept a 300m tunnel with a vacuum...

If we could remove the video cables, that would be a real epoch.

We found that the cabling behind the AP table is still quite ugly....grurrrh