Message ID: 16484     Entry time: Wed Nov 24 14:34:15 2021
Author: Yehonathan 
Type: Update 
Category: BHD 
Subject: Saving on SUSAUX slow channels 

Koji found out that the stock for BIO Acromag modules is very low and that the lead time for ordering new ones is ~ 1-year X-o.

We figure we might need to minimize the number of modules but still keep the Acromag chassis functional.

 

Looking at the new C1AUXEY feed-throughs spreadsheet one can see that we actually normally need only 1 BIO (not 2) module since there are 16 suspensions related bios + 1 green shutter which is unrelated to SUSAUX so there is no room to cut back here.

 

There are 16 analog input channels, 5 for PDMONs and 5 VMONs, and 6 spares which require 2 ADCs. Removing the spares and 2 monitoring channels will be enough to get us to 1 ADC.