Message ID: 14372
Entry time: Thu Dec 20 08:38:27 2018
In reply to: 14370
|
Author: |
Jon |
Type: |
Update |
Category: |
VAC |
Subject: |
Pumpdown tomorrow |
|
|
Linked is the pumpdown procedure, contained in the old 40m documentation. The relevant procedure is "All Off --> Vacuum Normal" on page 11.
Quote: |
I just spoke to Jon who asked me to make this elog - we will be ready to test one or more parts of the pumpdown procedure tomorrow (12/20), so we should proceed as planned to put the heavy doors back on EY and OMC chambers at 9am tomorrow morning. Jon will circulate a more detailed procedure about the pumpdown steps later today evening.
|
|