Wed Jan 24 13:55:04 2018, Kira, Summary, PEM, Seismometer can insulation test 6x
|
Thu Jan 25 12:41:18 2018, Kira, Update, PEM, Seismometer can insulation test
|
Thu Jan 25 14:58:20 2018, Kira, Update, PEM, Seismometer can insulation test
|
Thu Jan 25 16:39:09 2018, Kira, Update, PEM, Seismometer can insulation test
|
Thu Feb 1 16:09:13 2018, Kira, Update, PEM, Seismometer can insulation test
|
Mon Feb 5 12:12:41 2018, Kira, Update, PEM, Seismometer can insulation test
|
Wed Feb 7 12:35:56 2018, Kira, Update, PEM, Seismometer can insulation test
|
Wed Feb 7 17:01:25 2018, gautam, Update, PEM, PID test plan    
|
Wed Feb 7 19:14:19 2018, rana, Update, PEM, PID test plan
|
Thu Feb 8 12:24:37 2018, Kira, Update, PEM, PID test plan
|
Thu Feb 8 17:32:44 2018, Kira, Update, PEM, PID test plan   
|
Fri Feb 9 15:29:32 2018, Kira, Update, PEM, PID test plan
|
Thu Feb 15 16:03:57 2018, Kira, Update, PEM, PID test plan
|
Thu Feb 22 16:16:43 2018, Kira, Update, PEM, temp sensor input
|
Mon Feb 26 16:22:10 2018, Kira, Update, PEM, temp sensor input  
|
Wed Feb 28 12:31:28 2018, Kira, Update, PEM, temp sensor input
|
Fri Mar 9 12:59:53 2018, Kira, Update, PEM, ADC noise measurement 
|
Mon Mar 26 16:10:33 2018, Kira, Update, PEM, final setup sketch   
|
Wed Apr 18 12:18:39 2018, Kira, Update, PEM, final setup sketch 7x
|
Wed Apr 18 16:59:35 2018, rana, Update, PEM, final setup sketch: EX Seis
|
Thu Apr 19 11:29:11 2018, rana, Update, PEM, PID tune
|
Mon Apr 23 20:06:35 2018, rana, Update, PEM, PID tune
|
Thu Apr 26 19:46:26 2018, rana, Update, PEM, PID Quixote
|
Tue May 1 11:15:19 2018, Kira, Update, PEM, PID Quixote
|
Tue May 1 15:23:18 2018, Kira, Update, PEM, new ADC channel setup issue
|
Thu Apr 19 12:23:30 2018, Kira, Update, PEM, final setup sketch update 
|
Thu Apr 19 18:23:51 2018, Kira, Update, PEM, final setup sketch update
|
Fri Apr 20 15:07:45 2018, Kira, Update, PEM, final setup sketch update
|
Thu May 24 16:08:12 2018, Kira, Update, PEM, parts list
|
Tue May 29 16:22:43 2018, Kira, Update, PEM, parts list  
|
Wed Jun 6 15:12:29 2018, Kira, Update, PEM, parts from lab  
|
Mon Jun 18 11:12:23 2018, Kira, Summary, PEM, finishing up work at the lab  
|
Tue Apr 24 09:10:20 2018, Kira, Update, PEM, final setup sketch
|
Mon Apr 30 15:36:18 2018, Kira, Update, PEM, final setup sketch
|
Tue May 8 10:24:10 2018, Kira, Summary, PEM, plan for this week
|
Fri May 11 11:47:33 2018, johannes, Summary, PEM, Acromag issues
|
Tue May 15 15:13:23 2018, Kira, Summary, PEM, Acromag issues
|
Thu Mar 15 17:33:56 2018, Kira, Update, PEM, test setup
|
Tue Mar 20 16:56:01 2018, Kira, Update, PEM, test setup 
|
Tue Mar 20 19:48:10 2018, gautam, Update, PEM, test setup
|
Fri Mar 23 12:00:20 2018, rana, Update, PEM, test setup
|
Fri Mar 23 12:45:08 2018, Kira, Update, PEM, test setup
|
Thu May 17 15:38:19 2018, Kira, Update, PEM, test setup with seismometer   
|
Fri May 18 14:33:34 2018, Kira, Update, PEM, test setup with seismometer
|
Mon May 21 14:17:28 2018, Kira, Update, PEM, test setup with seismometer
|
Tue May 22 14:49:03 2018, Kira, Update, PEM, test setup with seismometer
|
Wed May 23 14:50:33 2018, Kira, Update, PEM, test setup with seismometer 
|
Thu May 24 15:18:12 2018, Kira, Update, PEM, PID loop restarted
|
Thu May 31 15:48:16 2018, Kira, Update, PEM, running PID script with seismometer
|
Mon May 21 10:15:35 2018, gautam, Update, PEM, test setup with seismometer
|
Wed Feb 28 21:14:34 2018, gautam, Summary, PEM, Channel admin
|
Tue Mar 27 11:11:16 2018, Kira, Update, PEM, Channel setup
|
Thu Mar 29 17:14:42 2018, Kira, Update, PEM, PID test
|
Fri Mar 30 06:16:45 2018, rana, Update, PEM, PID test
|
Fri Mar 30 16:10:46 2018, Kira, Update, PEM, PID test
|
Wed Apr 4 16:23:10 2018, Kira, Update, PEM, PID test  
|
Fri Apr 6 16:17:20 2018, Kira, Update, PEM, PID tuning
|
Fri Apr 6 18:28:57 2018, rana, Update, PEM, PID tuning
|
Mon Apr 9 16:30:21 2018, Kira, Update, PEM, MEDM setup
|
Tue Apr 10 15:42:08 2018, Kira, Update, PEM, MEDM setup
|
Thu Apr 12 10:15:33 2018, Kira, Update, PEM, MEDM setup
|
Fri Apr 13 00:20:46 2018, rana, Update, PEM, MEDM setup
|
|
Message ID: 13656
Entry time: Mon Feb 26 16:22:10 2018
In reply to: 13651
Reply to this: 13660
|
Author: |
Kira |
Type: |
Update |
Category: |
PEM |
Subject: |
temp sensor input |
|
|
[Kira, Gautam]
We began the setup for the lab temperature sensor today. First, we needed to add in a DIN fuse for both temperature sensors, which required us to shut down everything else first. To avoid having to do that next time, we made three instead of two spaces where we have + and - 15V. Attachment 1 shows the new fuses we installed, along with the fuses they connect to. Attachment 2 shows the wiring that we used to connect all the fuses. Attachment 3 shows the labeled long wires that are attached to the lab temperature sensor. The other end is labeled as well. I measured the voltage at the other end of the long cables, and while the -15V one looks good, the +15V one shows only about 13.5V.
-----
edit (Tuesday) - I set up the other set of cables that will eventually lead to the sensor in the can, but neither of them are showing any voltage on the other end. I'll work on this issue tomorrow.
gautam: some additional remarks about the procedure followed:
- Wires were tinned with solder to facilitate easier insertion into DIN fuse blocks.
- ETMX watchdog was shutdown. I then unplugged the satellite box at the X end to avoid any sort of electrical impulse being sent to the optic.
- Shut down all the sorensens in the EX rack.
- Tapped new +15VDC and -15 VDC outputs at the EX rack in the locations Kira indicated.
- Turned Sorensens back on. Checked that all voltages as reported by front panel monitor points were as they were expected to be.
- Had some trouble getting the modbus IOC going after this work. Kept throwing an error that modbus couldn't be initialized by procserv. Ended up having to reboot c1auxex2, after which it worked fine.
|
|
|
|
|
|
|