Entry  Wed Jan 24 13:55:04 2018, Kira, Summary, PEM, Seismometer can insulation test 6x
    Reply  Thu Jan 25 12:41:18 2018, Kira, Update, PEM, Seismometer can insulation test 
       Reply  Thu Jan 25 14:58:20 2018, Kira, Update, PEM, Seismometer can insulation test 
          Reply  Thu Jan 25 16:39:09 2018, Kira, Update, PEM, Seismometer can insulation test HeaterTest.png
             Reply  Thu Feb 1 16:09:13 2018, Kira, Update, PEM, Seismometer can insulation test cooling_fit.png
                Reply  Mon Feb 5 12:12:41 2018, Kira, Update, PEM, Seismometer can insulation test temp_data.py
                   Reply  Wed Feb 7 12:35:56 2018, Kira, Update, PEM, Seismometer can insulation test fit_1.png
                      Reply  Wed Feb 7 17:01:25 2018, gautam, Update, PEM, PID test plan ADC_EX.pngDAC_EX.pngIMG_20180207_170628.jpgdac_adc.jpgIMG_20180207_165833.jpg
                         Reply  Wed Feb 7 19:14:19 2018, rana, Update, PEM, PID test plan 
                            Reply  Thu Feb 8 12:24:37 2018, Kira, Update, PEM, PID test plan 
                               Reply  Thu Feb 8 17:32:44 2018, Kira, Update, PEM, PID test plan IMG_20180208_171423.jpgIMG_20180208_172107.jpgIMG_20180208_171853.jpgIMG_20180208_171932.jpg
                                  Reply  Fri Feb 9 15:29:32 2018, Kira, Update, PEM, PID test plan IMG_20180209_152158.jpg
                               Reply  Thu Feb 15 16:03:57 2018, Kira, Update, PEM, PID test plan 
                               Reply  Thu Feb 22 16:16:43 2018, Kira, Update, PEM, temp sensor input IMG_20180222_160602.jpg
                                  Reply  Mon Feb 26 16:22:10 2018, Kira, Update, PEM, temp sensor input 1.jpgIMG_20180226_154649.jpgIMG_20180226_154720.jpg
                                     Reply  Wed Feb 28 12:31:28 2018, Kira, Update, PEM, temp sensor input 
                                        Reply  Fri Mar 9 12:59:53 2018, Kira, Update, PEM, ADC noise measurement IMG_20180309_114345.jpgIMG_20180309_125153.jpg
                               Reply  Mon Mar 26 16:10:33 2018, Kira, Update, PEM, final setup sketch heater_1_new.pngheater_2_new.pngHeaterCircuit.pdftemp_sensor.png
                                  Reply  Wed Apr 18 12:18:39 2018, Kira, Update, PEM, final setup sketch 7x
                                     Reply  Wed Apr 18 16:59:35 2018, rana, Update, PEM, final setup sketch: EX Seis Screen_Shot_2018-04-18_at_5.20.53_PM.png
                                        Reply  Thu Apr 19 11:29:11 2018, rana, Update, PEM, PID tune Screen_Shot_2018-04-19_at_11.27.08_AM.png
                                           Reply  Mon Apr 23 20:06:35 2018, rana, Update, PEM, PID tune HeaterTest.png
                                              Reply  Thu Apr 26 19:46:26 2018, rana, Update, PEM, PID Quixote dv.pdf
                                                 Reply  Tue May 1 11:15:19 2018, Kira, Update, PEM, PID Quixote IMG_20180501_154826.jpg
                                                    Reply  Tue May 1 15:23:18 2018, Kira, Update, PEM, new ADC channel setup issue IMG_20180501_152014.jpg
                                        Reply  Thu Apr 19 12:23:30 2018, Kira, Update, PEM, final setup sketch update heater_1_new.pngheater_2_new.png
                                           Reply  Thu Apr 19 18:23:51 2018, Kira, Update, PEM, final setup sketch update 
                                              Reply  Fri Apr 20 15:07:45 2018, Kira, Update, PEM, final setup sketch update 
                                           Reply  Thu May 24 16:08:12 2018, Kira, Update, PEM, parts list front_panels.zip
                                              Reply  Tue May 29 16:22:43 2018, Kira, Update, PEM, parts list parts_list_-_Sheet1.pdf1U-panel-2.fpdEX-can-panel.fpd
                                                 Reply  Wed Jun 6 15:12:29 2018, Kira, Update, PEM, parts from lab IMG_20180606_141149.jpgIMG_20180606_141851.jpgIMG_20180606_141912.jpg
                                                    Reply  Mon Jun 18 11:12:23 2018, Kira, Summary, PEM, finishing up work at the lab IMG_20180618_101640.jpgIMG_20180618_093920.jpgIMG_20180618_093932.jpg
                                     Reply  Tue Apr 24 09:10:20 2018, Kira, Update, PEM, final setup sketch EX-can-panel_1.pdf
                                        Reply  Mon Apr 30 15:36:18 2018, Kira, Update, PEM, final setup sketch mount.png
                                           Reply  Tue May 8 10:24:10 2018, Kira, Summary, PEM, plan for this week 
                                              Reply  Fri May 11 11:47:33 2018, johannes, Summary, PEM, Acromag issues 
                                                 Reply  Tue May 15 15:13:23 2018, Kira, Summary, PEM, Acromag issues 
                         Reply  Thu Mar 15 17:33:56 2018, Kira, Update, PEM, test setup IMG_20180315_172512.jpg
                            Reply  Tue Mar 20 16:56:01 2018, Kira, Update, PEM, test setup IMG_20180320_154516.jpgIMG_20180320_145957.jpg
                               Reply  Tue Mar 20 19:48:10 2018, gautam, Update, PEM, test setup 
                               Reply  Fri Mar 23 12:00:20 2018, rana, Update, PEM, test setup 
                               Reply  Fri Mar 23 12:45:08 2018, Kira, Update, PEM, test setup seis_fit.png
                            Reply  Thu May 17 15:38:19 2018, Kira, Update, PEM, test setup with seismometer IMG_20180517_144420.jpgIMG_20180517_145754.jpgIMG_20180517_151956.jpgIMG_20180517_145121.jpg
                               Reply  Fri May 18 14:33:34 2018, Kira, Update, PEM, test setup with seismometer seis_temp_can_on.png
                                  Reply  Mon May 21 14:17:28 2018, Kira, Update, PEM, test setup with seismometer seis-temp.png
                                     Reply  Tue May 22 14:49:03 2018, Kira, Update, PEM, test setup with seismometer seis-temp-2.png
                                        Reply  Wed May 23 14:50:33 2018, Kira, Update, PEM, test setup with seismometer seis-temp-3.pngseis-temp-full-2.png
                                           Reply  Thu May 24 15:18:12 2018, Kira, Update, PEM, PID loop restarted 
                                           Reply  Thu May 31 15:48:16 2018, Kira, Update, PEM, running PID script with seismometer can-on-pid.png
                               Reply  Mon May 21 10:15:35 2018, gautam, Update, PEM, test setup with seismometer 
    Reply  Wed Feb 28 21:14:34 2018, gautam, Summary, PEM, Channel admin tempSensData.png
       Reply  Tue Mar 27 11:11:16 2018, Kira, Update, PEM, Channel setup 
          Reply  Thu Mar 29 17:14:42 2018, Kira, Update, PEM, PID test PID_test.png
             Reply  Fri Mar 30 06:16:45 2018, rana, Update, PEM, PID test 
                Reply  Fri Mar 30 16:10:46 2018, Kira, Update, PEM, PID test 
                   Reply  Wed Apr 4 16:23:10 2018, Kira, Update, PEM, PID test step_response.pngcapacitor.jpgIMG_20180412_120427.jpg
                      Reply  Fri Apr 6 16:17:20 2018, Kira, Update, PEM, PID tuning PID_tuning_progress.png
                         Reply  Fri Apr 6 18:28:57 2018, rana, Update, PEM, PID tuning HeaterTest.png
          Reply  Mon Apr 9 16:30:21 2018, Kira, Update, PEM, MEDM setup MEDM_screen.png
             Reply  Tue Apr 10 15:42:08 2018, Kira, Update, PEM, MEDM setup MEDM_2.png
                Reply  Thu Apr 12 10:15:33 2018, Kira, Update, PEM, MEDM setup MEDM_3.png
                   Reply  Fri Apr 13 00:20:46 2018, rana, Update, PEM, MEDM setup 
Message ID: 13626     Entry time: Thu Feb 8 17:32:44 2018     In reply to: 13624     Reply to this: 13629
Author: Kira 
Type: Update 
Category: PEM 
Subject: PID test plan 

[Kira, Steve]

We set up a new rail for the Sorensens (attachment 1) and placed one of them down on this new rail (attachment 2). Unfortunately the older rail that had been used to support the other Sorensens (the top one in attachment 1) is thick and does not allow another one of the Sorensens to slide in between the current ones. So we will have to support all the ones on top with a temporary support, take out the old rail, and then insert the new ones before letting the new bottom rail carry the weight of all of the Sorensens. We will do that tomorrow.

In addition, we have to figure out how to lead all the cables to the can, but there are no holders on the side of the lab to do so. So, we decided that we would have a new one installed on the side shown in attachment 3 so that we wouldn't have to place the wires along the floor.

Also, there has been some space made for the can along with the new insulation. The stuff mounted on the wall was removed and will be reattached tomorrow so that it doesn't get in the way of the can anymore.

Attachment 1: IMG_20180208_171423.jpg  3.451 MB  | Hide | Hide all
IMG_20180208_171423.jpg
Attachment 2: IMG_20180208_172107.jpg  3.835 MB  | Hide | Hide all
IMG_20180208_172107.jpg
Attachment 3: IMG_20180208_171853.jpg  4.723 MB  | Hide | Hide all
IMG_20180208_171853.jpg
Attachment 4: IMG_20180208_171932.jpg  4.416 MB  | Hide | Hide all
IMG_20180208_171932.jpg
ELOG V3.1.3-