Entry  Tue Dec 26 17:24:24 2017, Steve, Update, General, power outage powerOutage.png
    Reply  Thu Dec 28 17:22:02 2017, gautam, Update, General, power outage - CDS recovery 28.png
       Reply  Thu Jan 4 14:39:50 2018, gautam, Update, General, power outage - timing error 
          Reply  Fri Jan 5 21:54:28 2018, rana, Update, General, power outage - timing error huh.png
             Reply  Fri Jan 5 22:19:53 2018, gautam, Update, General, power outage - timing error 
                Reply  Sat Jan 6 18:27:37 2018, gautam, Update, General, power outage - IFO recovery EX_QPD_Quad1_Faulty.pdfTrillium_faulty.pdf
                   Reply  Mon Apr 16 22:09:53 2018, Kevin, Update, General, power outage - BLRM recovery AA.jpgADC.jpg
                      Reply  Tue Apr 17 09:57:09 2018, Steve, Update, General, seismometer interfaces BS_Tril_Intrf-1X5.jpgGurs_Intf-1X1.jpg
                         Reply  Wed Apr 18 20:33:19 2018, Kevin, Update, General, seismometer interfaces front.jpgback.jpgconnectors.jpg
                            Reply  Fri Apr 20 23:36:28 2018, Kevin, Update, PEM, Seismometer BLRMs front.jpgback.jpgdetail.jpg
                               Reply  Tue Apr 24 21:19:08 2018, Kevin, Update, PEM, Seismometer BLRMs modified_schematic.pdftop.jpgbottom.jpgBS_Seis_PSD.pdf
                                  Reply  Wed Apr 25 17:44:39 2018, Arnold, Update, PEM, PEM Anti-Alias wiring 
                                     Reply  Thu Apr 26 09:35:49 2018, Kevin, Update, PEM, PEM Anti-Alias wiring board.jpgSeismometerPSD.pdf
                                        Reply  Thu Apr 26 20:22:21 2018, Kevin, Update, PEM, ADC common mode rejection with new seismometer connections setup.pdfseismometerASD.pdf
                                           Reply  Wed May 16 21:02:22 2018, Kevin, Update, PEM, ADC common mode rejection with new seismometer connections ADC_noise.pdf
                                        Reply  Thu Jun 14 15:24:32 2018, Steve, Update, PEM, ADC DAC In Line Test Boards are in ADC_DAC_in_(1).JPG
    Reply  Tue Jan 2 15:43:35 2018, Steve, Update, VAC, pumpdown after power outage pumpdown_from_44_mTorr.png
       Reply  Wed Feb 7 15:50:42 2018, Steve, Update, VAC, IFO pressure monitoring CC_analog.png
Message ID: 13507     Entry time: Fri Jan 5 22:19:53 2018     In reply to: 13506     Reply to this: 13510
Author: gautam 
Type: Update 
Category: General 
Subject: power outage - timing error 

Just putting the relevant line from email from Rolf which at least identifies the problem here:

Looks like FB time is actually off by 1 year, as your timing system does not get year info.

There still seems to be something funky with the X arm transmission PDs - I can't seem to get the triggering to switch between the QPD and the Thorlabs PD, and the QPD signal seems to be wildly fluctuating by several orders of magnitude from 0.01-100. The c1iscex FE was pulled out, and it seemed to me like someone was doing some cable re-arrangement at the X end.

I will look into this tomorrow. 

Quote:

Rolf came here in the morning, but not sure what he did or if Jamie remotely did something. But the screen is green.

 

ELOG V3.1.3-