Wed Jan 25 15:41:29 2017, Lydia, Update, IMC, 29.5 MHz modulation depth measurement plan
|
Wed Jan 25 17:30:03 2017, Koji, Update, IMC, 29.5 MHz modulation depth measurement plan
|
Wed Jan 25 19:39:07 2017, gautam , Update, IMC, 29.5 MHz modulation depth measurement plan
|
Fri Jan 27 21:25:11 2017, Lydia, Update, IMC, 29.5 MHz modulation depth
|
Sat Jan 28 01:25:51 2017, gautam, Update, IMC, 29.5 MHz modulation depth 
|
Mon Jan 30 19:07:48 2017, gautam, Update, IMC, RF AM stabilization box pulled out
|
Tue Jan 31 01:07:20 2017, Lydia, Update, IMC, RF AM stabilization box pulled out
|
Tue Jan 31 13:46:34 2017, rana, Update, IMC, RF AM stabilization box pulled out
|
Tue Jan 31 14:17:48 2017, gautam, Update, IMC, RF AM stabilization box pulled out
|
Tue Jan 31 22:07:13 2017, gautam, Update, IMC, RF AM stabilization box revamp
|
Tue Jan 31 22:28:39 2017, Lydia, Update, IMC, RF AM stabilization box pulled out
|
Wed Feb 1 11:51:19 2017, Koji, Update, IMC, RF AM stabilization box pulled out
|
Wed Feb 1 16:45:56 2017, Lydia, Update, IMC, RF AM stabilizer box Modification Plan
|
Wed Feb 1 20:49:34 2017, rana, Update, IMC, RF AM stabilizer box Modification Plan
|
Wed Feb 1 23:13:30 2017, Lydia, Update, IMC, RF AM stabilizer box Modification Plan
|
Sun Feb 5 21:56:50 2017, Lydia, Update, IMC, 29.5 MHz stabilizer box replacement
|
Tue Feb 7 12:01:10 2017, Lydia, Update, IMC, 29.5 MHz stabilizer box replacement
|
Tue Feb 7 17:00:55 2017, Lydia, Update, IMC, 29.5 MHz stabilizer box replacement
|
Fri Feb 10 02:14:10 2017, gautam, Update, IMC, 29.5 MHz stabilizer box replacement
|
Fri Feb 10 11:41:43 2017, Lydia, Update, IMC, 29.5 MHz stabilizer box replacement
|
Fri Feb 10 13:24:28 2017, rana, Update, IMC, 29.5 MHz stabilizer box replacement
|
Fri Feb 10 18:21:21 2017, gautam, Update, IMC, IMC Demod board
|
Fri Feb 10 19:32:15 2017, Koji, Update, IMC, IMC Demod board
|
Sun Feb 12 01:16:57 2017, gautam, Update, IMC, IMC length loop - summary of changes    
|
Mon Feb 13 11:55:14 2017, rana, Update, IMC, IMC length loop - summary of changes
|
Mon Feb 13 13:34:44 2017, gautam, Update, IMC, IMC length loop - bad SMA cable replaced
|
Mon Feb 13 19:44:55 2017, Lydia, Update, IMC, Front panel for 29.5 MHz amplifier box
|
Wed Mar 1 21:15:40 2017, Lydia, Update, IMC, Front panel for 29.5 MHz amplifier box
|
Wed Mar 1 23:56:09 2017, gautam, Update, IMC, Front panel for 29.5 MHz amplifier box
|
Thu Mar 2 20:32:18 2017, Lydia, Update, IMC, Front panel for 29.5 MHz amplifier box
|
Wed Feb 15 23:54:13 2017, gautam, Update, IMC, IMC saga continues... 
|
Fri Feb 17 20:10:18 2017, gautam, Update, IMC, WFS servos turned back on
|
Sat Feb 18 14:09:06 2017, rana, Update, IMC, WFS servos turned back on
|
Sat Feb 18 21:50:48 2017, gautam, Update, IMC, WFS servos turned back on
|
Sun Mar 5 12:41:23 2017, gautam, Update, IMC, WFS servo-steppin  
|
|
Message ID: 12755
Entry time: Wed Jan 25 15:41:29 2017
Reply to this: 12756
|
Author: |
Lydia |
Type: |
Update |
Category: |
IMC |
Subject: |
29.5 MHz modulation depth measurement plan |
|
|
[Lydia, gautam]
To measure the modulation depth of the 29.5 MHz sideband, we plan to connect a bidirectional coupler between the EOM and the triple resonant circuit box. This will let us measure the power going into the EOM and the power in the reflection. According to the manual for the EOM (Newport 4064), the modulation depth is 13 mrad/V at a wavelength of 1000 nm. Before disconnecting these we will turn off the Marconi.
Hopefully we can be gentle enough that the EOM can be realigned without too much trouble. Before touching anything we'll measure the beam power before and after the EOM so we know what to match after.
If anyone has an objection to this plan, speak now or we will proceed tomorrow morning. |