40m QIL Cryo_Lab CTN SUS_Lab TCS_Lab OMC_Lab CRIME_Lab FEA ENG_Labs OptContFac Mariner WBEEShop
  40m Log  Not logged in ELOG logo
Entry  Wed Oct 12 22:51:26 2016, Koji, Update, General, Clipping could not be improved by the PZTs - NEED ANOTHER VENT 
    Reply  Thu Oct 13 00:23:54 2016, ericq, Update, VAC, Pre-vent prep 
       Reply  Thu Oct 13 09:30:38 2016, Steve, Update, General, vent 79 is happening vent79precond.pngventing.png
          Reply  Thu Oct 13 16:48:34 2016, Steve, Update, VAC, vent 79 is completed vent_79.png
             Reply  Thu Oct 13 19:28:14 2016, gautam, Update, General, in-air alignment 
                Reply  Fri Oct 14 10:31:53 2016, gautam, Update, General, doors are off ITMY and BS/PRM chambers 
                   Reply  Fri Oct 14 18:33:55 2016, gautam, Update, General, AS clipping investigations 7x
                      Reply  Mon Oct 17 22:45:16 2016, gautam, Update, General, AS beam centered on all OMs 7x
                         Reply  Tue Oct 18 18:56:57 2016, gautam, Update, General, OM5 rotated to bypass OMC, green scatter is from window to PSL table OMCchamber.pdfgreenGhosts.JPGIMG_3322.JPGIMG_3326.JPG
                            Reply  Wed Oct 19 16:41:55 2016, gautam, Update, General, Heavy doors back on 8x
             Reply  Thu Oct 20 09:17:08 2016, Steve, Update, VAC, Pumpdown 80 has started readyPd80.pngbeforePd80.pngpd80at1h.png7d_atm.png
                Reply  Thu Oct 20 15:59:52 2016, Steve, Update, VAC, Pumpdown 80 has completed 7hPd80.png8hPd80.png9hPd80.png
                   Reply  Fri Oct 21 02:06:20 2016, gautam, Update, General, IFO recovery 
                      Reply  Mon Oct 24 11:39:13 2016, gautam, Update, General, ALS recovered ALSOutOfLoop20161024.pdfXendPDHOLTF20161024.pdf
                   Reply  Fri Oct 21 09:28:21 2016, Steve, Update, VAC, Vac Normal reached VacNormal.png
                      Reply  Wed Nov 23 11:32:13 2016, Steve, Update, VAC, TP3 drypump replaced again 
                         Reply  Fri Nov 10 08:52:21 2017, Steve, Update, VAC, TP3 drypump replaced 
                            Reply  Fri Feb 16 15:57:58 2018, Steve, Update, VAC, TP3 drypump replaced 
                Reply  Thu Jul 12 16:18:22 2018, Steve, Update, VAC, Vent preparations before_Vent.pngbefore_Vent_cond.png
                   Reply  Thu Jul 12 23:59:14 2018, gautam, Update, General, Vent objectives and prep 
                      Reply  Fri Jul 13 02:52:11 2018, gautam, Update, General, Vent objectives and prep preVentStatus.png
                         Reply  Fri Jul 13 17:13:45 2018, Koji, Update, General, Vent objectives and prep P_20180713_020603.jpg
                         Reply  Fri Jul 13 18:01:13 2018, gautam, Update, General, Low power MC 
Message ID: 12636     Entry time: Wed Nov 23 11:32:13 2016     In reply to: 12577     Reply to this: 13423
Author: Steve 
Type: Update 
Category: VAC 
Subject: TP3 drypump replaced again 

TP3 drypump replaced at 655 mTorr, no load, tp3 0.3A 

This seal lasted only for 33 days at  123,840 hrs

The replacement is performing well: TP3 foreline pressure is 55 mTorr, no load, tp3 0.15A at 15 min  [ 13.1 mTorr at d5 ]

 

Valve configuration: Vacuum Normal, ITcc 8.5E-6 Torr

Quote:

Dry pump of TP3 replaced after 9.5 months of operation.[ 45 mTorr d3 ]

The annulosses are pumped.

Valve configuration: vac normal, IFO pressure 4.5E-5 Torr [1.6E-5 Torr d3 ] on new ITcc gauge, RGA is not installed yet.

Note how fast the pressure is dropping when the vent is short.

Quote:

IFO pressure 1.7E-4 Torr on new not logged cold cathode gauge. P1 <7E-4 Torr

Valve configuration: vac.normal with anunulossess closed off.

TP3 was turned off with a failing drypump. It will be replaced tomorrow.

All time stamps are blank on the MEDM screens.

 