Wed Jul 27 15:03:02 2016, sisyphus, Metaphysics, SUS, Broken wire
|
Wed Jul 27 16:56:47 2016, rana, Metaphysics, SUS, Broken wire
|
Thu Jul 28 08:42:36 2016, Steve, Update, SUS, wire clamp
|
Fri Jul 29 15:17:23 2016, Steve, Update, SUS, wire and clamping test
|
Fri Jul 29 20:12:54 2016, gautam, Update, SUS, third time - no luck
|
Mon Aug 1 14:09:20 2016, Steve, Update, SUS, third time - no luck
|
Tue Aug 9 16:19:27 2016, Steve, Update, SUS, torque driver for wire clamp
|
Wed Aug 10 15:34:24 2016, Steve, Update, SUS, 6 in-lbs torque driver for wire clamp screw
|
Wed Aug 3 00:15:39 2016, gautam, Update, SUS, ETMX suspended
|
Wed Aug 3 09:26:54 2016, Lydia, Update, SUS, ETMX suspended: photos 8x
|
Thu Aug 4 03:14:39 2016, gautam, Update, SUS, ETMX suspended
|
Fri Aug 5 02:17:10 2016, gautam, Update, SUS, ETMX Ruby Wire Standoff Ready for Gluing 8x
|
Fri Aug 5 04:43:09 2016, Koji, Update, SUS, ETMX Ruby Wire Standoff Ready for Gluing
|
Fri Aug 5 18:21:28 2016, gautam, Update, SUS, ETMX Ruby Wire Standoff GLUED 11x
|
Sun Aug 7 14:53:39 2016, ericq , Update, SUS, ETMX Standoff gluing was successful 
|
Tue Aug 9 00:44:43 2016, gautam , Update, SUS, ETMY patch-up
|
Tue Aug 9 15:27:57 2016, gautam , Update, SUS, ETMY patch-up 
|
Wed Aug 10 03:08:03 2016, gautam , Update, SUS, ETMY patch-up
|
Wed Aug 10 23:45:03 2016, gautam , Update, SUS, ETMY re-suspended 7x
|
Thu Aug 11 00:20:41 2016, Koji, Update, SUS, ETMY re-suspended
|
Thu Aug 11 11:56:40 2016, gautam, Update, SUS, ETMY re-suspended
|
Mon Aug 15 18:28:15 2016, gautam, Update, SUS, Air-bake preparation
|
Tue Aug 16 08:04:49 2016, Steve, Update, SUS, ETMY had Aluminum bridge
|
Tue Aug 16 21:54:27 2016, gautam, Update, SUS, Air-bake - IN PROGRESS
|
Wed Aug 17 08:47:43 2016, ericq, Update, SUS, Air-bake finished
|
Wed Aug 17 23:00:57 2016, gautam, Update, SUS, Air-bake of towers
|
Thu Aug 18 08:17:16 2016, Steve, Update, SUS, wire clamping preparation
|
Thu Aug 18 14:14:20 2016, gautam, Update, SUS, Air-bake of towers - finished
|
Fri Aug 19 22:51:12 2016, gautam, Update, SUS, ETMs first-contacted
|
Sun Aug 21 16:23:05 2016, gautam, Update, SUS, ETMX suspended
|
Mon Aug 22 13:06:11 2016, gautam, Update, SUS, ETMY suspended
|
Mon Aug 22 18:04:24 2016, gautam, Update, SUS, ETMY OSEMs inserted
|
Tue Aug 23 19:35:38 2016, gautam, Update, SUS, ETMY back in IFO 10x
|
Thu Aug 25 21:11:43 2016, gautam, Update, SUS, ETMY back in IFO
|
Fri Aug 26 11:35:44 2016, gautam, Update, SUS, ETMY UL sensor problematic  
|
Fri Aug 26 14:05:38 2016, Steve, Update, SUS, ETMY UL sensor problematic
|
Fri Aug 26 14:09:46 2016, ericq, Update, SUS, ETMY UL sensor problematic
|
Sun Aug 28 21:40:11 2016, gautam, Update, SUS, ETMY UL sensor problematic
|
Mon Aug 29 09:37:05 2016, gautam, Update, SUS, ETMY UL sensor problematic
|
Mon Aug 29 14:42:06 2016, gautam, Update, SUS, ETMY Satellite box diagnostics 
|
Fri Aug 26 17:48:14 2016, gautam, Update, SUS, bounce mode coupling reduction
|
Mon Aug 29 21:53:14 2016, Lydia, Update, SUS, ETMY bounce mode coupling 
|
Tue Aug 30 20:26:36 2016, gautam, Update, SUS, ITMY installed  
|
Wed Aug 31 18:07:43 2016, Johannes, Update, SUS, ITMY free swinging
|
Wed Aug 31 22:09:18 2016, gautam, Update, SUS, Y arm locked to Green
|
Thu Sep 1 08:30:24 2016, Steve, Update, SUS, ITMY_UL is sick 
|
Tue Sep 6 20:30:56 2016, rana, Update, SUS, ITMY_UL is sick
|
Tue Sep 13 11:00:59 2016, Lydia, Update, SUS, ETMY UL glitch returned
|
Thu Sep 1 19:59:22 2016, Johannes, Update, SUS, IR mode flashes in Y arm
|
Fri Sep 2 21:09:08 2016, gautam, Update, SUS, Y arm locked in air 
|
Tue Sep 6 20:45:14 2016, gautam, Update, SUS, X arm test masses back in chamber   
|
Thu Sep 8 22:12:36 2016, gautam, Update, SUS, X arm in place, locked to green, IR flashes visible
|
Fri Sep 9 17:50:02 2016, gautam, Update, SUS, Heavy doors on BS-PRM, ETMY chambers
|
Sat Sep 10 14:26:01 2016, rana, Update, General, PRM SRM alignment
|
Mon Sep 12 17:15:22 2016, Johannes, Update, General, PRM SRM alignment 
|
Thu Sep 1 19:18:14 2016, Johannes, Update, SUS, ITMX and ETMX preemptive table leveling 8x
|
Fri Sep 2 21:15:53 2016, gautam, Update, SUS, ITMX and ETMX preemptive table leveling
|
Thu Sep 1 15:43:16 2016, rana, Update, SUS, OSEM adjustments
|
Mon Sep 5 19:57:24 2016, Osamu, Update, SUS, OSEM adjustments
|
|
Message ID: 12370
Entry time: Thu Aug 4 03:14:39 2016
In reply to: 12362
Reply to this: 12377
|
Author: |
gautam |
Type: |
Update |
Category: |
SUS |
Subject: |
ETMX suspended |
|
|
Quote: |
[lydia, steve, ericq, gautam]
Summary:
- ETMX is now suspended by wire clamps (winches have been removed)
- Unfortunately, in the process of doing the pitch balancing, the position of the magnets relative to the OSEM coils have moved. Now the UR magnet looks a little high relative to the coil, but perhaps after any sag has set in, we should be alright. Else, we can probably get away by inserting one of the little metal shim pieces, the adjustment required is small
|
[lydia, ericq, gautam]
- Turns out setting the height of the optic with the OSEMs isn't quite reliable. We were indeed too high, for all the OSEMs
- Related to the above - we observed no sag (which is one of the reasons we winched a little bit extra in the first place)
- Eric and I re-did the suspension in the afternoon. We found no wire grooves in the primary (or secondary) clamps, so we just reused them (is this a red flag? should we be using more torque?)
- This time we set the height using the traveling microscope - double checked the height to which the microscope was levelled = 5.5"
- Having checked the height of both scribe lines, we proceeded to clamp the suspension, with ~1.35Nm of torque (since 1.25Nm seemed a little low, no wire grooves were made in the clamps) - clamping was successful
- In the evening, Lydia and I attempted to do the fine pitch balancing
- Both left side magnets (as viewed from the AR side) are low (within 0.5mm of the teflon). Right side magnets are pretty well centered. But left side ones seemed usable so we went ahead and tried to turn the damping on.
- Damping worked reasonably well
- Tried to do fine pitch balancing with PZT buzzer. Reduced voltage from Fn generator to 0.4Vrms (down from 1.7Vrms) but had limited success.
- I was able to do much better with just the teflon tipped tweezers. So gave up on the PZT buzzer
- After ~3hours of a random walk between two pretty-close-to-ideal positions, we have now realized a fine pitch balancing of ~1mrad (~3mm off the ideal height of 5.5" over a lever arm of ~1.5m, but the mirror tilt is half of this angle)
- Actually, I was able to do much better - at one point, we even had the reflected beam dead center on the iris 1.5m away. But adjusting the OSEM positions even a little bit (say from oscillating around 40% to 50% of the maximum value) has a BIG effect on the pitch balance (it caused a misalignment of 4mrad)
- I think gluing the standoff without destroying the fine pitch balancing is going to be very challenging, judging by how gently I had to touch the standoff to destroy the fine pitch balance completely. Perhaps we want to consider using some 3 axis stage to bring the needle with glue in and perturb the standoff as little as possible
Lydia also briefly played around with the IR camera to inspect the OSEMs. A more thorough investigation will be done once the cage is in for air baking. From our initial survey, we feel that the beams are pretty well aligned along the straight line between PD and LED - we estimate the upper bound on any misalignment to be ~10 degrees.
|