Thu Mar 10 16:29:32 2016, gautam, Update, endtable upgrade, Inventory check 
|
Thu Mar 10 16:32:45 2016, rana, Update, endtable upgrade, Inventory check
|
Mon Mar 14 22:42:23 2016, gautam, Update, endtable upgrade, Inventory check
|
Mon Mar 28 10:43:18 2016, Steve, Update, endtable upgrade, ETMX 4'x2' optical table pictures  
|
Wed Mar 30 17:38:52 2016, gautam, Update, endtable upgrade, X end table proposed layout  
|
Thu Mar 31 09:38:41 2016, Steve, Update, endtable upgrade, Y end 4x3 existing layout
|
Thu Mar 31 19:49:31 2016, gautam, Update, endtable upgrade, proposed layout v2
|
Mon Apr 4 10:59:12 2016, gautam, Update, endtable upgrade, proposed layout v3    
|
Mon Apr 4 15:04:14 2016, gautam, Update, endtable upgrade, COMPONENT REMOVAL
|
Tue Apr 5 11:42:17 2016, gaericqutam, Update, endtable upgrade, TABLE REMOVAL
|
Wed Apr 6 17:52:21 2016, gautam, Update, endtable upgrade, First contact cleaning commenced
|
Thu Apr 7 12:51:24 2016, gautam, Update, endtable upgrade, Beam height differences
|
Thu Apr 7 14:30:58 2016, Steve, Update, endtable upgrade, ETMX table height    
|
Fri Apr 8 09:13:20 2016, Steve, Update, endtable upgrade, ETMX-T beam height 
|
|
Message ID: 12030
Entry time: Thu Mar 10 16:32:45 2016
In reply to: 12029
Reply to this: 12033
12051
|
Author: |
rana |
Type: |
Update |
Category: |
endtable upgrade |
Subject: |
Inventory check |
|
|
Its not a good idea to use green mounts with green lasers. Steve should be able to get another copy of the EY doubler mount made up if we really don't have another one sitting in the Manasa end table box which Koji mentioned. |