40m QIL Cryo_Lab CTN SUS_Lab TCS_Lab OMC_Lab CRIME_Lab FEA ENG_Labs OptContFac Mariner WBEEShop
  40m Log  Not logged in ELOG logo
Entry  Sun Dec 7 13:11:57 2014, manasa, Summary, General, Frequency Offset Locking - To Do List FOLtodolist.pdf
    Reply  Mon Dec 8 15:54:39 2014, manasa, Summary, General, Dec 8 - Check Frequency Counter module 
       Reply  Mon Dec 8 20:53:51 2014, diego, Summary, General, Dec 8 - Check Frequency Counter module 
          Reply  Tue Dec 9 16:06:46 2014, diego, Summary, General, Dec 8 - Check Frequency Counter module 
    Reply  Tue Dec 9 00:30:27 2014, manasa, Summary, General, Dec 9 - Elaborate to do list FOL_FiberChassis.pdf
       Reply  Tue Dec 9 16:07:16 2014, manasa, Summary, General, Dec 9 - FC module and fiber chassis FCmodule.png
    Reply  Wed Dec 10 16:12:29 2014, manasa, Summary, General, Dec 10 - PSL table FiberMod_front.jpgFOL_fiber.jpg
       Reply  Thu Dec 11 12:50:12 2014, manasa, Summary, General, PSL table optical layout 
          Reply  Thu Dec 11 23:34:06 2014, manasa, Summary, General, PSL table optical layout 
             Reply  Fri Dec 12 02:30:25 2014, Jenne, Summary, General, PSL table optical layout 
    Reply  Fri Dec 12 14:38:39 2014, manasa, Summary, General, Frequency Offset Locking - To Do List (Revised) FOLtodolist.pdf
       Reply  Fri Dec 12 15:19:04 2014, manasa, Summary, General, Dec 12 - PSL table PSLtoFiber.pngPSLfiberChassis.pngPSLfiberChassis.png
       Reply  Wed Dec 17 11:57:56 2014, manasa, Summary, General, Y arm optical layout 58.png
Message ID: 10767     Entry time: Tue Dec 9 00:30:27 2014     In reply to: 10760     Reply to this: 10771
Author: manasa 
Type: Summary 
Category: General 
Subject: Dec 9 - Elaborate to do list 

Quote:

Attached is the timeline for Frequency Offset Locking related activities. All activities will be done mostly in morning and early afternoon hours.

Elaborate to do list:

1. The FC module should be mounted on the IOO rack. Domenica has to be powered up appropriately to the rack power supply.

2. The fiber chassis needs to be built. This will hold all the fiber components and will sit inside the PSL enclosure.
Fiber connectors and fiber couplers need to be installed in the chassis. Attached is the cartoon sketch of layout in the chassis.

3. User guide for FC module (work in progress)

Attachment 1: FOL_FiberChassis.pdf  69 kB  | Hide | Hide all
FOL_FiberChassis.pdf