Mon Mar 25 18:34:25 2013, Koji, General, General, OMC building plan / procedure ~ Mar 25 Mon
|
Mon Mar 25 19:31:16 2013, Koji, Optics, General, OMC Top-side gluing   
|
Tue Mar 26 22:33:07 2013, Koji, General, General, Loan for the OMC building
|
Wed Mar 27 20:54:45 2013, Koji, General, General, OMC building plan / procedure ~ Mar 26 Mon
|
Wed Mar 27 20:54:54 2013, Koji, General, General, OMC building plan / procedure ~ Mar 27 Wed
|
Wed Mar 27 20:55:10 2013, Koji, General, General, OMC building plan / procedure ~ Mar 28 Thu
|
Mon Apr 1 03:13:41 2013, Koji, Optics, General, Failure of PZT-glass joints
|
Mon Apr 1 03:23:48 2013, Koji, Optics, General, UV power calibration
|
Mon Apr 1 10:28:03 2013, Koji, Mechanics, General, Additional UV blast for the top surface  
|
Mon Apr 1 18:17:01 2013, Koji, Optics, General, Mirror curvature center test 6x
|
Wed Apr 3 18:42:45 2013, Koji, Optics, General, EP30-2 gluing test
|
Mon Apr 8 21:11:14 2013, Koji, Optics, General, PZT assembly gluing
|
Tue Apr 9 13:56:09 2013, Koji, Optics, General, PZT assembly post gluing / pre baking pictures
|
Thu Apr 11 15:10:22 2013, Koji, General, General, OMC Progress
|
Sat Apr 13 21:06:02 2013, Koji, Optics, General, OMC Bottom-side: cavity glued 
|
Tue Apr 16 00:40:45 2013, Koji, Optics, General, PD/QPD path gluing ~ preparation
|
Wed Apr 17 07:30:04 2013, Koji, Optics, General, QPD path glued
|
Thu Apr 18 11:43:59 2013, Koji, General, General, Mounting Glass Bracket Failure
|
Thu Apr 18 11:59:02 2013, Koji, General, General, DCPD path gluing
|
Fri May 3 21:09:08 2013, Koji, General, General, OMC is back
|
Wed May 8 15:36:50 2013, Koji, General, General, Latest OMC schedule
|
Fri May 10 09:33:22 2013, Koji, Supply, General, COMSOL simulation on the glass bracket stress
|
Mon May 13 14:59:16 2013, Koji, Mechanics, General, Invar shim gluing
|
Mon May 13 15:00:23 2013, Koji, General, General, Current most reliable OMC schedule
|
Tue May 14 19:06:00 2013, Koji, Clean, General, OMC Baking
|
Mon May 20 14:59:21 2013, Koji, General, General, OMC is out from the oven
|
Tue May 21 18:28:08 2013, Koji, General, General, Current most reliable OMC schedule
|
Thu May 23 23:41:48 2013, Koji, Mechanics, General, DCPD/QPD Mount
|
Thu May 30 14:38:42 2013, Koji, Electronics, General, Cable fitting
|
Thu May 30 15:00:28 2013, Koji, Optics, General, QPD alignment
|
Fri May 31 05:46:54 2013, Koji, Optics, General, QPD alignment  
|
Mon Jun 3 21:19:03 2013, Koji, General, General, Planning
|
Wed Jun 5 18:19:51 2013, Koji, General, General, Some recent photos from the OMC final test at CIT
|
Wed Jun 5 18:51:31 2013, Koji, General, General, L1 OMC shipped out 
|
Fri Jun 7 16:04:44 2013, Koji, General, General, [LLO] OMC arrived
|
Mon Jun 10 10:04:37 2013, Koji, General, General, [LLO] OMC Test  
|
Thu Jun 13 12:04:57 2013, Koji, General, General, [LLO] OMC Optical Test - completed
|
Thu Jun 13 12:12:20 2013, Zach, General, General, [LLO] OMC and OMCS in LVEA
|
Fri Jun 14 06:35:21 2013, Jeff, General, General, [LLO] L1 OMC status
|
Tue Jun 18 15:45:38 2013, Koji, General, General, [LLO] OMC installation in HAM6
|
Fri Jun 28 12:20:49 2013, Koji, General, General, Dmass's loan of Thorlabs HV amp
|
Fri Aug 9 10:09:56 2013, Koji, General, General, PZT Assembly #3/#4
|
Mon Aug 12 20:22:19 2013, Koji, General, General, PZT Assembly #5/#6
|
Fri Aug 16 16:36:19 2013, Koji, Optics, General, Optics List
|
Fri Aug 16 17:21:38 2013, Koji, General, General, [OMC002] Build started
|
Thu Aug 22 15:34:03 2013, Koji, Optics, General, OMC Cavity side gluing
|
Thu Aug 29 18:55:36 2013, Koji, Mechanics, General, I1 OMC top side gluing (UV)
|
Fri Aug 30 12:14:50 2013, Koji, Optics, General, H1 OMC Cavity length adjustment 
|
Fri Aug 30 12:22:56 2013, Koji, Optics, General, H1 OMC Cavity side UV gluing
|
Fri Aug 30 12:25:29 2013, Koji, General, General, H1 OMC Invar mount gluing 
|
|