40m QIL Cryo_Lab CTN SUS_Lab TCS_Lab OMC_Lab CRIME_Lab FEA ENG_Labs OptContFac Mariner WBEEShop
  OMC elog, Page 10 of 10  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
ID Date Author Type Categoryup Subject Text Attachments
  445   Wed Aug 24 11:29:47 2022 KojiGeneralGeneralOMC #002 ready for shipment[Stephen Koji]

The OMC #002 is ready for
shipment.
 IMG_1207.JPGPXL_20220825_004259850.jpgPXL_20220825_004307204.jpgPXL_20220825_005423342.jpgPXL_20220825_005549985.jpg 
  446   Thu Aug 25 14:22:08 2022 KojiGeneralGeneralLLO OMC #001 Ballast Mass investigationInspected the past LLO add-on mass configuration.

There are unknown masses at the
DCPD side. It looks like a small SS mass
 DSCN0917.JPGDSCN0922.JPGP6108705.JPGP6108707.JPGP6108706.JPG 
  447   Thu Aug 25 20:05:00 2022 KojiGeneralGeneralLLO OMC #001 Ballast Mass investigationHere is the balance mass info for the LLO
OMC#001 analyzed from the photographs


Added masses are: 50+10g,
 balance_mass_config_LLO.pdf 
  448   Fri Aug 26 22:29:02 2022 KojiGeneralGeneralTool Shipping PrepShipping preparation for the LLO
trip

Started
July 15, 2022 and finished Aug 30. So it
 PXL_20220831_025623318.jpgPXL_20220831_024518032.jpgPXL_20220831_030234581.jpg 
  449   Tue Sep 20 08:54:33 2022 KojiGeneralGeneralPD cage arrangementUpon the LLO work, the current PD arrangement
in the cages are:
CAGE B
  
  450   Mon Sep 26 14:27:49 2022 KojiGeneralGeneralLLO OMC ICS workOMC
#001


ICS Link: https://ics.ligo-la.caltech.edu/JIRA/browse/ASSY-D1201439-1
Already
  
  453   Fri Nov 11 19:07:48 2022 KojiSupplyGeneralSupply OrderClean Supply Ordered


TexWipe TX8410 AlphaSat
Vectra Alpha 10 50 sheets x 12 pk  (VWR
  
  456   Tue Nov 15 07:46:58 2022 Camille MakaremOpticsGeneralcleaning OMC #1Monday, November 14, 2022

Camille and Koji did a "deep
cleaning" of OMC#1:
  
  457   Tue Nov 15 10:58:53 2022 KojiOpticsGeneralOMC #1 damaged black glass removal[Camille, Koji]

The damaged black glass was removed
from the OMC breadboard leaving the glass
 PXL_20221114_222641455.jpgPXL_20221114_222544330.jpgPXL_20221114_222555849.jpgPXL_20221114_233748631.jpg 
  458   Tue Nov 15 11:12:24 2022 KojiOpticsGeneralOMC #1 fogging on the AR side of BS1 cleaned[Camille, Koji]

Photo of the BS1 AR cleaning process

Attachment 1: Before cleaning.
 PXL_20221114_225338114.jpgPXL_20221114_232824245.jpgPXL_20221114_233714774.jpgPXL_20221114_233748631.jpg 
  459   Thu Nov 17 18:56:22 2022 KojiOpticsGeneral Transmission measurements of OMC #1 after deep cleaning[Camille, Koji]

- Removed the first contact we
left on Monday.
 PXL_20221117_232145418.jpgScreen_Shot_2022-11-17_at_19.02.31.png 
  461   Fri Nov 18 18:41:05 2022 Camille MakaremGeneralGeneral2nd deep cleaning of OMC #1The four cavity mirrors in OMC #1 were
each scrubbed using acetone and a cotton
swab.
 PXL_20221118_213955948.jpg 
  462   Mon Nov 21 19:13:35 2022 KojiGeneralGeneralTransmission measurement (2nd deep cleaning of OMC #1)OMC Transmission measurement after
the 2nd deep cleaning

The 2nd deep cleaning didn't
 PXL_20221122_030736513.jpgOMC_loss.pdf 
  467   Mon Dec 5 20:09:39 2022 KojiOpticsGeneral(re)starting the OMC #4 build[Camille Koji]

We started buikding the
OMC #4. 
 PXL_20221205_233712211.jpg 
  471   Thu Jan 19 23:45:44 2023 KojiOpticsGeneralOMC #4: cavity mirror bonding[Koji, Camille]

We worked on the bonding of the
flat mirrors for the OMC cavity with UV epoxy.
  
  472   Mon Jan 23 19:51:20 2023 KojiOpticsGeneralOMC #4: cavity mirror bonding[Camille, Koji]

We continued to bond two CM mirrors
and the other two steering mirrors for QPD2.
 HOM_plot_PZT0_0.pdfPXL_20230124_032358482.MP.jpgPXL_20230124_032452805.MP.jpgPXL_20230124_032425638.jpg 
  473   Wed Jan 25 23:51:04 2023 KojiGeneralGeneralThe items packed for DownsQty1 1/2 mounts
Qty2 prism mounts
Qty6 gluing fixures
 PXL_20230127_055920944.jpg 
  474   Thu Jan 26 22:57:19 2023 KojiOpticsGeneralOMC #4: One Invar block bonded with tilt[Camille, Koji]

The bottom side template was separated
into two pieces and successfully removed
 PXL_20230126_221425695.jpgPXL_20230126_221522416.jpg 
  475   Thu Jan 26 23:07:14 2023 KojiOpticsGeneralOMC #4: Input beam dump bonding[Camille, Koji]

During the second UV epoxy session,
we did not bond the input beam dump. This
 PXL_20230126_221556977.jpg 
  477   Thu Jan 26 23:46:13 2023 KojiOpticsGeneralOMC #1 input beam dump bondingA beam dump was stacked on the base of
the previous beam dump. The angle was determined
so that the main transmission goes through
 PXL_20230127_052955482.jpgPXL_20230127_052949869.jpg 
  478   Sat Jan 28 00:38:56 2023 KojiMechanicsGeneralOMC #1 cable bracket replacement / OMC #1 repair completedThe AL metal bracket was replaced with
a PEEK version.

Attachments 1/2: Before the replacement.
 PXL_20230128_011405446.jpgPXL_20230128_011401778.jpgPXL_20230128_013509885.jpgPXL_20230128_014001006.jpgPXL_20230128_014035044.jpg 
  479   Sat Jan 28 00:46:21 2023 KojiMechanicsGeneralOMC #4: Replaced the locks of the transport fixture Yesterday, we noticed that we could not
close the transport fixture for OMC #4. We
could not fully rotate the knobs of the locks.
 PXL_20230128_022952669.jpg 
  480   Wed Feb 1 01:33:03 2023 KojiMechanicsGeneral5th OMC Transport FixtureThe transport fixture was brought to the
40m clean room to use as an assembly reference.
 PXL_20230201_005912224.jpg 
  481   Wed Feb 1 01:39:41 2023 KojiMechanicsGeneralDCPD housing / QPD housingInserted 4-40 and 2-56 helicoils into the
DCPD/QPD housings for the 4th OMC. The retainer
caps were also fastened to the housings.
 PXL_20230201_021505299.jpgPXL_20230201_021455728.jpg 
  482   Wed Feb 1 01:44:14 2023 KojiGeneralGeneralOMC (004) plan2/1 2:30PM~ Bonding reinforcement (Last
EP30-2 gluing)

2/2 1:00PM~ Peripheral attachment
  
  483   Thu Feb 2 03:09:41 2023 KojiOpticsGeneralOMC #4: One Invar block bonded with tilt[Camille, Thejas, Koji]

We added a reinforcement bar at
the back of the invar block which had the
 PXL_20230202_003156761.jpgPXL_20230202_003204058.jpg 
  484   Sat Feb 4 03:16:10 2023 KojiOpticsGeneralOMC #4: One Invar block bonded with tiltThe attached photo shows the resulting
bond spread.

 
 PXL_20230202_213114009.jpg 
  485   Sat Feb 4 03:22:46 2023 KojiFacilityGeneralReady for the HEPA enclosure expansionHEPA is quite low for a tall person and
also the curtain on the back of us is always
heavy. It's very tough for anyone to
 PXL_20230202_002014960.MP.jpgPXL_20230203_011618168.MP.jpgPXL_20230203_011633873.jpg 
  486   Sat Feb 4 03:30:02 2023 KojiElectronicsGeneralOMC cables #4 arrived The OMC cables #4 arrived on Feb 3rd. (See
Attachment)

This shipment included two DCPD
 PXL_20230202_210750100.jpg 
  487   Sat Feb 4 03:33:22 2023 KojiGeneralGeneralOMC Lab InventoryAttachment 1: North Cabinet 2nd from the
left

Attachment 2: North Cabinet 3rd
 PXL_20230204_072749311.jpgPXL_20230204_072744686.MP.jpgPXL_20230204_073603041.MP.jpg 
  248   Fri Dec 18 15:33:24 2015 KojiGeneralLoan / LendingLoan from RichLoan Record: I borrowed a PD can opener
from Rich => Antonio Returned Sep
9, 2016
  
  250   Thu Feb 18 21:08:32 2016 KojiGeneralLoan / Lending(all returned) Antonio loanAntonio borrowed: Rich's PD cutter
(returned), Ohir power meter(returned),
Thorlabs power meter head, Chopper
  
  258   Tue Apr 5 18:14:55 2016 KojiGeneralLoan / LendingQPD Lending CrackleXiaoyue

QPD head
X-Z stage
  
  293   Thu May 3 21:45:58 2018 awadeGeneralLoan / LendingBorrowed toaster ovenI’ve borrowed the black and decker
toaster oven to dry some sonicated parts.
It is temporarly located in the QIL lab. 
 9CE80545-7A58-4236-B7E3-1EE6C4042DAA.jpeg 
  385   Tue Oct 22 15:54:59 2019 KojiElectronicsLoan / LendingBorrowed LB1005 from Cryo CavFrom Cryo Cav setup

Borrowed LB1005 Servo box ->
OMC
  
  391   Mon Aug 10 15:34:04 2020 KojiFacilityLoan / LendingGlue bake ovenBlack and Decker Glue Baking Oven came
back to the OMC lab on Aug 10, 2020, Georgia
had lent the unit for the SAMS assembly/testing.
  
ELOG V3.1.3-