  448   Fri Aug 26 22:29:02 2022 KojiGeneralGeneralTool Shipping PrepShipping preparation for the LLO
trip

Started
July 15, 2022 and finished Aug 30. So it
 PXL_20220831_025623318.jpgPXL_20220831_024518032.jpgPXL_20220831_030234581.jpg 
  449   Tue Sep 20 08:54:33 2022 KojiGeneralGeneralPD cage arrangementUpon the LLO work, the current PD arrangement
in the cages are:
CAGE B
  
  450   Mon Sep 26 14:27:49 2022 KojiGeneralGeneralLLO OMC ICS workOMC
#001


ICS Link: https://ics.ligo-la.caltech.edu/JIRA/browse/ASSY-D1201439-1
Already
  
  453   Fri Nov 11 19:07:48 2022 KojiSupplyGeneralSupply OrderClean Supply Ordered


TexWipe TX8410 AlphaSat
Vectra Alpha 10 50 sheets x 12 pk  (VWR
  
  456   Tue Nov 15 07:46:58 2022 Camille MakaremOpticsGeneralcleaning OMC #1Monday, November 14, 2022

Camille and Koji did a "deep
cleaning" of OMC#1:
  
  457   Tue Nov 15 10:58:53 2022 KojiOpticsGeneralOMC #1 damaged black glass removal[Camille, Koji]

The damaged black glass was removed
from the OMC breadboard leaving the glass
 PXL_20221114_222641455.jpgPXL_20221114_222544330.jpgPXL_20221114_222555849.jpgPXL_20221114_233748631.jpg 
  458   Tue Nov 15 11:12:24 2022 KojiOpticsGeneralOMC #1 fogging on the AR side of BS1 cleaned[Camille, Koji]

Photo of the BS1 AR cleaning process

Attachment 1: Before cleaning.
 PXL_20221114_225338114.jpgPXL_20221114_232824245.jpgPXL_20221114_233714774.jpgPXL_20221114_233748631.jpg 
  459   Thu Nov 17 18:56:22 2022 KojiOpticsGeneral Transmission measurements of OMC #1 after deep cleaning[Camille, Koji]

- Removed the first contact we
left on Monday.
 PXL_20221117_232145418.jpgScreen_Shot_2022-11-17_at_19.02.31.png 
  461   Fri Nov 18 18:41:05 2022 Camille MakaremGeneralGeneral2nd deep cleaning of OMC #1The four cavity mirrors in OMC #1 were
each scrubbed using acetone and a cotton
swab.
 PXL_20221118_213955948.jpg 
  462   Mon Nov 21 19:13:35 2022 KojiGeneralGeneralTransmission measurement (2nd deep cleaning of OMC #1)OMC Transmission measurement after
the 2nd deep cleaning

The 2nd deep cleaning didn't
 PXL_20221122_030736513.jpgOMC_loss.pdf 
  467   Mon Dec 5 20:09:39 2022 KojiOpticsGeneral(re)starting the OMC #4 build[Camille Koji]

We started buikding the
OMC #4. 
 PXL_20221205_233712211.jpg 
  471   Thu Jan 19 23:45:44 2023 KojiOpticsGeneralOMC #4: cavity mirror bonding[Koji, Camille]

We worked on the bonding of the
flat mirrors for the OMC cavity with UV epoxy.
  
  472   Mon Jan 23 19:51:20 2023 KojiOpticsGeneralOMC #4: cavity mirror bonding[Camille, Koji]

We continued to bond two CM mirrors
and the other two steering mirrors for QPD2.
 HOM_plot_PZT0_0.pdfPXL_20230124_032358482.MP.jpgPXL_20230124_032452805.MP.jpgPXL_20230124_032425638.jpg 
  473   Wed Jan 25 23:51:04 2023 KojiGeneralGeneralThe items packed for DownsQty1 1/2 mounts
Qty2 prism mounts
Qty6 gluing fixures
 PXL_20230127_055920944.jpg 
  474   Thu Jan 26 22:57:19 2023 KojiOpticsGeneralOMC #4: One Invar block bonded with tilt[Camille, Koji]

The bottom side template was separated
into two pieces and successfully removed
 PXL_20230126_221425695.jpgPXL_20230126_221522416.jpg 
  475   Thu Jan 26 23:07:14 2023 KojiOpticsGeneralOMC #4: Input beam dump bonding[Camille, Koji]

During the second UV epoxy session,
we did not bond the input beam dump. This
 PXL_20230126_221556977.jpg 
  477   Thu Jan 26 23:46:13 2023 KojiOpticsGeneralOMC #1 input beam dump bondingA beam dump was stacked on the base of
the previous beam dump. The angle was determined
so that the main transmission goes through
 PXL_20230127_052955482.jpgPXL_20230127_052949869.jpg 
  478   Sat Jan 28 00:38:56 2023 KojiMechanicsGeneralOMC #1 cable bracket replacement / OMC #1 repair completedThe AL metal bracket was replaced with
a PEEK version.

Attachments 1/2: Before the replacement.
 PXL_20230128_011405446.jpgPXL_20230128_011401778.jpgPXL_20230128_013509885.jpgPXL_20230128_014001006.jpgPXL_20230128_014035044.jpg 
  479   Sat Jan 28 00:46:21 2023 KojiMechanicsGeneralOMC #4: Replaced the locks of the transport fixture Yesterday, we noticed that we could not
close the transport fixture for OMC #4. We
could not fully rotate the knobs of the locks.
 PXL_20230128_022952669.jpg 
  480   Wed Feb 1 01:33:03 2023 KojiMechanicsGeneral5th OMC Transport FixtureThe transport fixture was brought to the
40m clean room to use as an assembly reference.
 PXL_20230201_005912224.jpg 
  481   Wed Feb 1 01:39:41 2023 KojiMechanicsGeneralDCPD housing / QPD housingInserted 4-40 and 2-56 helicoils into the
DCPD/QPD housings for the 4th OMC. The retainer
caps were also fastened to the housings.
 PXL_20230201_021505299.jpgPXL_20230201_021455728.jpg 
  482   Wed Feb 1 01:44:14 2023 KojiGeneralGeneralOMC (004) plan2/1 2:30PM~ Bonding reinforcement (Last
EP30-2 gluing)

2/2 1:00PM~ Peripheral attachment
  
  483   Thu Feb 2 03:09:41 2023 KojiOpticsGeneralOMC #4: One Invar block bonded with tilt[Camille, Thejas, Koji]

We added a reinforcement bar at
the back of the invar block which had the
 PXL_20230202_003156761.jpgPXL_20230202_003204058.jpg 
  484   Sat Feb 4 03:16:10 2023 KojiOpticsGeneralOMC #4: One Invar block bonded with tiltThe attached photo shows the resulting
bond spread.

 
 PXL_20230202_213114009.jpg 
  485   Sat Feb 4 03:22:46 2023 KojiFacilityGeneralReady for the HEPA enclosure expansionHEPA is quite low for a tall person and
also the curtain on the back of us is always
heavy. It's very tough for anyone to
 PXL_20230202_002014960.MP.jpgPXL_20230203_011618168.MP.jpgPXL_20230203_011633873.jpg 
  486   Sat Feb 4 03:30:02 2023 KojiElectronicsGeneralOMC cables #4 arrived The OMC cables #4 arrived on Feb 3rd. (See
Attachment)

This shipment included two DCPD
 PXL_20230202_210750100.jpg 
  487   Sat Feb 4 03:33:22 2023 KojiGeneralGeneralOMC Lab InventoryAttachment 1: North Cabinet 2nd from the
left

Attachment 2: North Cabinet 3rd
 PXL_20230204_072749311.jpgPXL_20230204_072744686.MP.jpgPXL_20230204_073603041.MP.jpg 
  493   Wed Feb 15 16:00:46 2023 StephenElectronicsGeneralOMC cables #4 inspectedInspection

Updated ICS (Shipment-12578) and
moved those parts to Storage-9482.
 cable_residue_OMC_Lab_493_20230215_145127.jpg 
  500   Mon Mar 6 12:25:08 2023 KojiFacilityGeneralHEPA Enclosure improvementChub, JC, and co worked on the HEPA enclosure
improvement.
 20230306_081449.jpg20230306_081518.jpg 
  501   Mon Mar 6 16:02:56 2023 Thejas OpticsGeneralOMC test setup locking On Feb 16, Camille and I attampted at locking
the OMC cavity. It was quick to re-align
the beam to the cavity (by using only the
  
  519   Wed Apr 5 22:09:30 2023 KojiFacilityGeneralHEPA Enclosure extensionChub finished the HEPA enclosure extension
project.
 20230405_120322.jpg20230405_120308.jpg20230405_120033.jpg 
  525   Tue Apr 18 07:59:46 2023 Madeline LesovskyGeneralGeneralTest Cure Bake - Curved Mirror Subassembly BondingThis is a test bake conducted in Air Bake
Oven A (ABO-A) held in the 40m Clean and
Bake facility. The overall objective is to
 6x 
  530   Fri Apr 28 13:25:40 2023 Thejas OpticsGeneralaLIGO OMC Unit-4[Camille, Koji, Thejas]

Yesterday, we cleaned the cavity
optics with first contact, aligned the input
 image.jpegPXL_20230428_010507088.png 
  543   Fri May 19 16:09:31 2023 StephenGeneralGeneralA+ OMC Build Progress, Week of 2023.05.15A+ OMC Build efforts ongoing or completed
this week:


 PZT lead onboard
  
  546   Fri Jun 2 17:15:44 2023 StephenGeneralGeneralA+ OMC Build Progress, Weeks of 2023.05.22 and 2023.05.29A+ OMC Build efforts ongoing or completed
in the last two weeks:


 PZT lead onboard
  
  248   Fri Dec 18 15:33:24 2015 KojiGeneralLoan / LendingLoan from RichLoan Record: I borrowed a PD can opener
from Rich => Antonio Returned Sep
9, 2016
  
  250   Thu Feb 18 21:08:32 2016 KojiGeneralLoan / Lending(all returned) Antonio loanAntonio borrowed: Rich's PD cutter
(returned), Ohir power meter(returned),
Thorlabs power meter head, Chopper
  
  258   Tue Apr 5 18:14:55 2016 KojiGeneralLoan / LendingQPD Lending CrackleXiaoyue

QPD head
X-Z stage
  
  293   Thu May 3 21:45:58 2018 awadeGeneralLoan / LendingBorrowed toaster ovenI’ve borrowed the black and decker
toaster oven to dry some sonicated parts.
It is temporarly located in the QIL lab. 
 9CE80545-7A58-4236-B7E3-1EE6C4042DAA.jpeg 
  385   Tue Oct 22 15:54:59 2019 KojiElectronicsLoan / LendingBorrowed LB1005 from Cryo CavFrom Cryo Cav setup

Borrowed LB1005 Servo box ->
OMC
  
  391   Mon Aug 10 15:34:04 2020 KojiFacilityLoan / LendingGlue bake ovenBlack and Decker Glue Baking Oven came
back to the OMC lab on Aug 10, 2020, Georgia
had lent the unit for the SAMS assembly/testing.
  
  518   Tue Apr 4 16:14:06 2023 KojiOpticsLoan / LendingC7 mirror to DownsI handed Camille the C7 mirror for the
cross-calibration of the ROC characterization
techniques.
  
  529   Wed Apr 26 14:43:44 2023 StephenGeneralLoan / LendingBorrowed Items for PZT DC Response Shadow Sensor SetupBorrowed for PZT DC Response Shadow Sensor
Setup (see Attachment 1):


Thorlabs PDA100A Photodiode
 PXL_20230426_185227710.jpg 
  538   Fri May 12 10:00:06 2023 Camille MakaremGeneralLoan / LendingBorrowed Items for PZT DC Response Shadow Sensor SetupThe ThorLabs MDT694B piezo driver was returned
to the OMC lab.

 PXL_20230511_201545235.jpg 