  456   Tue Nov 15 07:46:58 2022 Camille MakaremOpticsGeneralcleaning OMC #1

Monday, November 14, 2022

Camille and Koji did a "deep cleaning" of OMC#1:
1) Applied First Contact to the mirror surfaces. Removed first contact after ~10 minutes.
2) Acetone scrub of the mirror surfaces with a cotton swab.
3) Applied First Contact again. Removed after ~10 minutes. We left the FC paint on for the work on Thu.

The foggy spot on the input mirror was unchanged after the first round of First Contact. But the foggy spot came off during the acetone scrub.

  457   Tue Nov 15 10:58:53 2022 KojiOpticsGeneralOMC #1 damaged black glass removal

[Camille, Koji]

The damaged black glass was removed from the OMC breadboard leaving the glass base.
The black glass pieces were bonded very tightly on the FS base with EP30-2. The apparent amount of the bond was not so much but it was such hard that removal by hand was not possible.
We decided to give drips of Acetone on the base hoping the gradual dissolving of EP30-2. Using a knife edge, the "filets" of the bonds were removed, but the BD was still tight.

By wedging the black glass-black glass bonding with the nife edge, the left side (the directly damaged one) was taken off from the structure leaving a tiny fragment of the glass on the base.

The remaining one was even stronger. We patiently kept dripping Acetone on the base and finally, the black glass piece was knocked off and removed from the base.

Attachment 1: The base right after the black glass removal.

Attachment 2: The black glass pieces were stored in a container with Al foil + clean cloth bed. The damaged and fogged surfaces faced up.

Attachment 3: The zoom-in shot of the black glass pieces.

Attachment 4: The base was wiped with Acetone and cleaned with FC. We will bond another BD assembly on the base, presumably using the UV epoxy.

  458   Tue Nov 15 11:12:24 2022 KojiOpticsGeneralOMC #1 fogging on the AR side of BS1 cleaned

[Camille, Koji]

Photo of the BS1 AR cleaning process

Attachment 1: Before cleaning. Foggy surface is visible.

Attachment 2: After FC cleaning. The structure of the deposited material is still quite visible.

Attachment 3: Acetone scrubbing. Cotton Q-tip was used so that the stick does not melt with acetone.

Attachment 4: After acetone scrubbing. Nicely clean!

Acetone scrubbing was applied to HR/AR of BS1, FM1, FM2, BS2, and HR of CM1 and CM2. (total 10 surfaces)
Then final FC paint was applied to these 10 surfaces.

We'll come back to the setup on Thu for FC peeling and loss measurement.

  459   Thu Nov 17 18:56:22 2022 KojiOpticsGeneral Transmission measurements of OMC #1 after deep cleaning

[Camille, Koji]

- Removed the first contact we left on Monday.

- Measured transmission (Set1) Very high loss! Total optical loss of 18.5%! Observation with the IR viewer indicated that CM1 has bright scattering. We suspencted a remnant of FC.

- Applied the second FC on the four cavity mirrors. This made the CM1 sport darker.

- Measured the transmission (Set1~Set3). We had consistent loss of 4.2~5.0%. We concluded that this is the limitation of this OMC even with the cleaning.

  461   Fri Nov 18 18:41:05 2022 Camille MakaremGeneralGeneral2nd deep cleaning of OMC #1

The four cavity mirrors in OMC #1 were each scrubbed using acetone and a cotton swab.
Then, the four mirrors were painted with First Contact (picture attached). The First Contact was allowed to dry for 20 minutes, then removed while using the top gun.

  462   Mon Nov 21 19:13:35 2022 KojiGeneralGeneralTransmission measurement (2nd deep cleaning of OMC #1)

OMC Transmission measurement after the 2nd deep cleaning

The 2nd deep cleaning didn't improve the transmission. (See Attachment 2)
The measured loss was 0.044+/-0.002

 

  248   Fri Dec 18 15:33:24 2015 KojiGeneralLoan / LendingLoan from Rich

Loan Record: I borrowed a PD can opener from Rich => Antonio Returned Sep 9, 2016

Tungsten Carbide Engraver (permanently given to the OMC lab)

KEITHLEY SOURCE METER + Laptop

  250   Thu Feb 18 21:08:32 2016 KojiGeneralLoan / Lending(all returned) Antonio loan

Antonio borrowed: Rich's PD cutter (returned), Ohir power meter(returned), Thorlabs power meter head, Chopper

  258   Tue Apr 5 18:14:55 2016 KojiGeneralLoan / LendingQPD Lending Crackle

Xiaoyue

QPD head
X-Z stage
Mounting brackets
DB15 cable
QPD matrix circuit
+/-18V power supply cable

  293   Thu May 3 21:45:58 2018 awadeGeneralLoan / LendingBorrowed toaster oven

I’ve borrowed the black and decker toaster oven to dry some sonicated parts. It is temporarly located in the QIL lab. 

  385   Tue Oct 22 15:54:59 2019 KojiElectronicsLoan / LendingBorrowed LB1005 from Cryo Cav

From Cryo Cav setup

Borrowed LB1005 Servo box -> OMC

 

  391   Mon Aug 10 15:34:04 2020 KojiFacilityLoan / LendingGlue bake oven

Black and Decker Glue Baking Oven came back to the OMC lab on Aug 10, 2020, Georgia had lent the unit for the SAMS assembly/testing.