Entry  Mon Mar 25 02:04:05 2013, Koji, General, General, OMC building plan / procedure ~ WB18 
    Reply  Mon Mar 25 18:34:25 2013, Koji, General, General, OMC building plan / procedure ~ Mar 25 Mon 
       Reply  Wed Mar 27 20:54:45 2013, Koji, General, General, OMC building plan / procedure ~ Mar 26 Mon 
          Reply  Wed Mar 27 20:54:54 2013, Koji, General, General, OMC building plan / procedure ~ Mar 27 Wed 
             Reply  Wed Mar 27 20:55:10 2013, Koji, General, General, OMC building plan / procedure ~ Mar 28 Thu 
Message ID: 85     Entry time: Wed Mar 27 20:55:10 2013     In reply to: 84
Author: Koji 
Type: General 
Category: General 
Subject: OMC building plan / procedure ~ Mar 28 Thu 

28 March (Thu):

  • Rebuild the bottom template in the lab
  • Place the bottom template on the OMC
  • Glue the PZTs on the mounting prisms (x2)
  • Glue the curved mirrors on the PZTs (x2)
  • R&T measurement
  • Placing optics on the OMC breadboard
     
  • Better coupling to the fiber
  • Matching to the OMC cavity

 

29 March (Fri):

Start gluing bottom side: Set 4 cavity mirrors and 1 HR mirror
   and try to resonate beam.  Glue when OK.


Place BS and DCPD mounting brackets.  Glue when OK.
Friday: Place QPDs and rest of optics.  Glue when OK.

WB 1 April

  • Testing at CIT
    • Transmission / Coupling / Loss
    • FSR / TMS
    • Power dependence
    • PZT position dependence
    • Back scattering
    • Openloop TF
    • PZT TF
    • Noise measurement
  • Epoxy cure bake at CIT
  • Retest at CIT
    • ditto

WB 8 April or after

  • Packing
  • Shipping - Shipping box?
  • Optical Testing at LLO (2 days anticipated)