Mon Mar 25 02:04:05 2013, Koji, General, General, OMC building plan / procedure ~ WB18
|
Mon Mar 25 18:34:25 2013, Koji, General, General, OMC building plan / procedure ~ Mar 25 Mon
|
Wed Mar 27 20:54:45 2013, Koji, General, General, OMC building plan / procedure ~ Mar 26 Mon
|
Wed Mar 27 20:54:54 2013, Koji, General, General, OMC building plan / procedure ~ Mar 27 Wed
|
Wed Mar 27 20:55:10 2013, Koji, General, General, OMC building plan / procedure ~ Mar 28 Thu
|
|
Message ID: 85
Entry time: Wed Mar 27 20:55:10 2013
In reply to: 84
|
Author: |
Koji |
Type: |
General |
Category: |
General |
Subject: |
OMC building plan / procedure ~ Mar 28 Thu |
|
|
28 March (Thu):
- Rebuild the bottom template in the lab
- Place the bottom template on the OMC
- Glue the PZTs on the mounting prisms (x2)
- Glue the curved mirrors on the PZTs (x2)
- R&T measurement
- Placing optics on the OMC breadboard
- Better coupling to the fiber
- Matching to the OMC cavity
29 March (Fri):
Start gluing bottom side: Set 4 cavity mirrors and 1 HR mirror
and try to resonate beam. Glue when OK.
Place BS and DCPD mounting brackets. Glue when OK.
Friday: Place QPDs and rest of optics. Glue when OK.
WB 1 April
- Testing at CIT
- Transmission / Coupling / Loss
- FSR / TMS
- Power dependence
- PZT position dependence
- Back scattering
- Openloop TF
- PZT TF
- Noise measurement
- Epoxy cure bake at CIT
- Retest at CIT
WB 8 April or after
- Packing
- Shipping - Shipping box?
- Optical Testing at LLO (2 days anticipated)
|