Message ID: 7     Entry time: Sat Jul 14 02:16:07 2012
Author: Koji 
Type: General 
Category: General 
Subject: Plan Update: July 

Facility/Supplies

  • Work in progress
    • Floor cleaning
    • Plug slits on the roof of the HEPA booth - blanking panels have been ordered (Peter)
    • Install laser safety barrier (Peter is working on this)
    • Place a sticky mat
       
  • Work to be done
    • Replacing a file cabinet next to the south wall by a lockable cabinet
    • Replacing a lab desk at the west side of the room. (Vladimir's)
    • Replacing Vladimir's rack with nicer one.
    • Laser sign
    • Safety glass holder
    • Prepare clean supplies (Shoes/Coverall/Hats/Gloves) => go to VWR stock room
      • glove 8.5,9,9.5
         
    • Label maker (P-Touch) & Tape
        
  • Design
    • Optical layout - Laser SOP
    • Additional HEPA stage
       
  • Test
    • Confirm particle level
       
  • Note: Optical Table W96" x D48" x H27"

Beaurocracy

  • Laser SOP
  • HV use?
  • UV?

Mechanics

  • Ongoing Work 
    • Cone-shaped wire clamp design (at the OMC end) - Jeff
       
  • Design
    • Wire preparation fixture - Jeff
    • How do we hold the PDs, QPDs, and black glass - we put 2 PDs and 2 QPDs on the PD mounting blacket. - Jeff
    • Integrated solidwork model - Sam
      • Q: How the wires are clamped at the top side?
      • Q: How much the length of the wire should be?
      • Q: Locations of the wire mounts on the plate
    • Cabling investigation:
      • Where do the cables from the feed-thrus anchored? - Sam
      • List of the current internal cables and their lengths - Sam
      • List of the required internal cables and their lengths
      • Can we route the intermediate stage of the suspension? Do we need new cables?
    • Dummy intermediate stage structure
       
    • Metal templates
      • First, decide an optical design
      • takes at least a month
         
    • Weights how heavy / how many
       
  • Test
    • Cone-shaped wire clamp test - Jeff/Koji 
    • Balancing the plates
      • The Faraday isolator cage isn't clean
    • Dummy metal payload test at the sites???
       
  • Procedures to be decided
    • PZT alignment
    • Prototyping with metal parts?
    • UV glue? (heat) / gluing test
    • Balance

Optics

  • Ongoing Work 
    • Mirrors to be delivered ~Aug
       
    • Design down select - Between "Single output & BS" vs "Two outputs & no BS"
    • Down selecting procedure:
      1. Assume ELIGO beam component
      2. Assume amount of 9MHz / 45MHz sidebands at the OMC input
      3. Calculate transmitted power
      4. Require HOM to be smaller than the TEM00 offset 
         
    • UV cured epoxy (Quate obtained)
  • Design
    • Mode design for HAM6 layout
    • Finalization of scattering paths
       
  • Tests
    • Measurement of PD angles
    • R&T of each mirror
    • Curvature of the curved mirrors
    • Cavity ref/trans/finesse
    • PD Q.E. & Reflectivity measurement vs incident angle
       
  • Things to be decided / confirmed
    • How to handle optics / assemblies (Talk to the prev people)
    • First contact? (Margot: applicable to a short Rc of ~2.5m)
    • Gluing templates to be designed (how to handle it?)
       
  • PDs
  • Misc
    • CCD beam analyzer (Zach: It is fixed.)
    • Are two PZTs used?
      • YES, for redundancy, range, upconversion tests.
         
  • Things to buy
  • Need to buy a fiber for mode cleaning?
  • Mode content of the ELIGO dark beam?
  • Jitter noise?
  • How to determine the design?
  • Why Fused Silica? (How much is the temp fluctuation in the chamber?)
  • How to align the cavity mirrors, input mirrors, QPDs, PDs, beam dumps.
     

Electronics

  • Thorough scrutinization of cabling / wiring / electronics
  • Electronics / CDS electronics / software
  • Things to be tested
    • QPD/PD pre-selections (QE/noise)
    • Functionality test of QPD/PD/PZT

Shipping, storage etc


Jun/July
    - Lab renovtion
    - Mechanics design
    - Glue training
Aug
    - Mirror delivery
    - Basic optics test
Sept
    - Cavity test
    - Suspending test
NOV~DEC
    - Shipping to LLO

Open questions
    Two optical designs
    Procedure
    Modeling
    Clamp design / stencil design
    gluing-installation procedure

 


July:Facility/Supplies