Message ID: 34     Entry time: Wed Nov 7 20:44:11 2012
Author: Koji 
Type: General 
Category: General 
Subject: Plan Update: November [!] 

Completed work of the previous months: [Jul] [Aug] [Sep] [Oct] [Nov] [Dec]


  • Work done
    • Wedge measurement (1st trial) [ELOG]
    • RoC measurement [ELOG]
  • Work in progress
    • R&T measurement
    • Wedge measurement
  • Work to be done
    • QPD/PD pre-selections (QE/noise)
    •  
    •  
    •  
    • Misc. / Beaurocracy?
      • Continuous monitoring of the particle level
      • Replacing a file cabinet next to the south wall by a lockable cabinet
      • Ion gun safety issues: https://dcc.ligo.org/cgi-bin/private/DocDB/ShowDocument?docid=88631
      • Laser SOP / HV use? / UV?
  • Things delivered
  • Things ordered
    • Power strips Tripp Lite PS3612 (Ordered Nov. 8, Delivered Nov. 12)
    • Kapton tapes (1in x 6, 1/2in x 12 Delivered Nov. 15)
    • Sticky Mats (VWR 18888-216 Delivered Nov. 12 and 21992-042)
    • Duck tape (PK3) (Delivered Nov. 12)
    • Wipers 12"x12" 2ply x 119 pairs x case15 (Delivered Nov. 12)
    • Syringes (1mL&2mL) & Needles (20G x dozen)
    • Stainless trays with cover (Steve Delivered Nov. 12)
    • Gold Plated allen keys (Steve Delivered Nov. 12)
    • Forceps (Delivered Nov. 12) / Tweezers / Scissors (Delivered Nov. 12)
  • Things to buy / get
    • OMC testing optics / opto-mechanics
    • Black Glass / Black Glass holder / AR ==> Some at the 40m, some from LLO
    • Ionized air blow
      • N2 or Air cylinder: 4N - UHP or 5N - Research Grade.  (... steal from Downs)
    • Clean tools, tray, storage
    • Supply
      • Additional clean supplies ~ glove 8.5,9,9.5
      • Stainless bats / Pure solvents (Metha / Aceton / Iso) / Syringes / Lint free cloth / Paper lens tissue
      • Lab coats
    • ATF
      • Tefron tape
      • Thorlabs 8-32 screw kit / Thorlabs HW-KIT1
      • Pedestal Shims - Newport
  • Things to be done
    • Cavity ref/trans/finesse
    • PD Q.E. & Reflectivity measurement vs incident angle
    • Functionality test of QPD/PD (PeterK) /PZT
       
  • Procedures to be decided
    • PZT alignment
    • UV glue? (heat) / gluing test
    • Balance
    • N2 cylinder/lines/filter
    • Shipping procedure: New shipping cage design on going (Jeff) => Plastic box similar to COC
  • Design
    • Solidworks raytracing model
    • Mode design for HAM6 layout
       
  • Things to be decided / confirmed
    • How to handle optics / assemblies (Talk to the prev people)
    • First contact? (Margot: applicable to a short Rc of ~2.5m)
    • Gluing templates to be designed (how to handle it?)
  • Jitter noise?
  • How to align the cavity mirrors, input mirrors, QPDs, PDs, beam dumps.

Electronics ==> Rich

Attachment 1: OMC_Project_Schedule.pdf  273 kB  Uploaded Wed Nov 7 21:57:20 2012  | Hide | Hide all
OMC_Project_Schedule.pdf