Message ID: 153     Entry time: Fri Aug 16 17:21:38 2013
Author: Koji 
Type: General 
Category: General 
Subject: [OMC002] Build started 

[Jeff Koji]

The breadboard (SN2) was loaded on the transportation fixture.

The laser side template was installed and the cavity mirrors were placed.

The laser beam will be resonated in the cavity next week.