- The wrong Mighty Mouse connectors for the PZT wires were prepared. The correct ones are in the vacuum oven till Tuesday morning.
- The thread holes for the cable pegs are 1/4-20 rather than 10-24. This requires re-machining of the cable pegs & the C&B.
- We are waiting for the fast shipment of the from LHO
May
Thu 23rd Diode mount adjustment / Optical tests
Fri 24th Optical tests
Tue 28th Mighty mouse connector available / Diode mounting finalization
Wed 29th final check
Thu 30th shipment
Fri 31th
June
Mon 3rd ? Arrival to LLO / Koji fly to LLO
Tue 4th Suspension test done? |