40m QIL Cryo_Lab CTN SUS_Lab TCS_Lab OMC_Lab CRIME_Lab FEA ENG_Labs OptContFac Mariner WBEEShop
  40m Log, Page 36 of 172  Not logged in ELOG logo
Entry  Mon Jun 20 16:33:09 2016, Varun, Update, Electronics, Anti-Aliasing Filter circuit schematic 8x
    Reply  Wed Jun 22 14:03:42 2016, Varun, Update, Electronics, Anti-Aliasing Filter circuit schematic io.pdfAA.JPGratios_v2.pdf
Entry  Tue Jun 21 04:01:09 2016, ericq, Update, LSC, Y arm @ 30kHz UGF w/POY, AO inloop_outloop.pdfxarm.pdfyolg.png
    Reply  Wed Jun 22 08:40:42 2016, rana, Update, LSC, Y arm @ 30kHz UGF w/POY, AO 
Entry  Tue Jun 21 11:26:42 2016, varun, Frogs, CDS, medm command not working 
    Reply  Tue Jun 21 11:49:29 2016, ericq, Frogs, CDS, medm command not working 
Entry  Wed Jun 8 13:50:39 2016, jamie, Configuration, CDS, Spectracom IRIG-B card installed on fb1 
    Reply  Thu Jun 9 13:28:07 2016, jamie, Configuration, CDS, Spectracom IRIG-B card installed on fb1 
       Reply  Fri Jun 10 12:09:01 2016, jamie, Configuration, CDS, IRIG-B debugging 
          Reply  Fri Jun 10 12:21:54 2016, jamie, Configuration, CDS, GPS receiver not resetting properly 
             Reply  Mon Jun 20 11:11:20 2016, Steve, Configuration, CDS, GPS receiver not resetting properly 
                Reply  Mon Jun 20 11:19:41 2016, jamie, Configuration, CDS, GPS receiver not resetting properly 
                   Reply  Mon Jun 20 14:03:04 2016, jamie, Configuration, CDS, EndRun GPS receiver upgraded, fixed GPSreceiverWorking.jpg
          Reply  Wed Jun 15 10:19:10 2016, Steve, Configuration, CDS, GPS antennas... debugging 6x
Entry  Mon Feb 15 12:28:03 2016, gautam, Update, General, Something has gone wrong - was there a power outage? Vac_15Feb2016.png
    Reply  Mon Feb 15 13:09:33 2016, Koji, Update, General, Something has gone wrong - was there a power outage? 
       Reply  Tue Feb 16 09:13:39 2016, Steve, Update, General, there was a power outage & EQ 20160215_power_outage.png
          Reply  Tue Feb 16 15:02:19 2016, ericq, Update, General, Power Glitch recovery 
             Reply  Tue Feb 16 23:42:22 2016, gautam, Update, General, Power Glitch recovery - arms recovered 
                Reply  Wed Feb 17 13:45:15 2016, ericq, Update, General, No monit on frontends 
             Reply  Thu Feb 25 11:02:36 2016, Steve, Update, General, Power Glitch again powerGlitch.png
                Reply  Thu Feb 25 11:32:04 2016, gautam, Update, General, Power Glitch again 
          Reply  Mon Feb 22 08:45:46 2016, Steve, Update, SUS, EQ 4.3 grabs ITMX-UL magnet EQ4.3LucerneV.pngITMX-UL.png
             Reply  Mon Feb 22 23:00:21 2016, ericq, Update, SUS, ITMX free, green is flashing 
                Reply  Tue Feb 23 09:51:34 2016, Steve, Update, SUS, ITMX free ITMX_FREED.pngITMX_FREE.png
                   Reply  Tue Feb 23 17:46:09 2016, gautam, Update, SUS, EQ  SUS_Summary_23Feb.png
             Reply  Tue Apr 5 08:55:51 2016, Steve, Update, SUS, local EQ 3.1m eq3.1Valencia.png
                Reply  Wed May 25 08:32:55 2016, Steve, Update, SUS, local EQ 3.5m 3.5Cucam.pnglocal3.5cucam.png
                   Reply  Fri Jun 3 14:24:13 2016, Steve, Update, SUS, local EQ 3.1 m eq3.1mMuscoyCa.png
                      Reply  Fri Jun 10 09:52:51 2016, Steve, Update, SUS, EQ 5.2 mag Borego Spring 5.2mBoregoSpring.pngeqBSs.png
                         Reply  Mon Jun 20 09:36:10 2016, Steve, Update, SUS, EQ 3.1 m Big Bear Lake, CA eq3.1BigBearLakeCA.png
Entry  Thu Jun 16 18:08:57 2016, Johannes, Update, PSL, Before the AOM installation IMG_20160615_154556392e.jpg
    Reply  Fri Jun 17 22:36:11 2016, Johannes, Update, PSL, AOM installation aom_new_mount.jpgaom_beam_split.jpgaom_dump_IR.jpg
       Reply  Mon Jun 20 08:26:56 2016, Steve, Update, PSL, AOM pictures AOMinplace.jpginplaceAOM.jpgAOMin.png
Entry  Tue Jun 14 19:37:40 2016, jamie, Update, CDS, Overnight daqd test underway 
    Reply  Wed Jun 15 09:52:02 2016, jamie, Update, CDS, Very encouraging results from overnight split daqd test 
       Reply  Wed Jun 15 11:21:51 2016, jamie, Update, CDS, still work to do to transition to new configuration/code 
          Reply  Thu Jun 16 16:11:11 2016, jamie, Update, CDS, upgrade aborted for now 
Entry  Thu Jun 16 12:06:59 2016, ericq, Update, LSC, RF Amp installed at POY11 RF output IMG_3426.jpg
Entry  Thu Jun 16 11:25:00 2016, Johannes, Update, LSC, Y-Arm round-trip loss measurement with ALS T_vs_steps.pdff_vs_steps.pdf
Entry  Thu Jun 16 08:52:14 2016, Steve, Update, General, illuminators turned off 
Entry  Mon Jun 13 19:30:58 2016, Aakash, Update, General, EPICS Installation | SURF 2016 
    Reply  Tue Jun 14 11:52:08 2016, Johannes, Update, General, EPICS Installation | SURF 2016 
Entry  Tue Jun 14 11:29:25 2016, Johannes, Summary, ASC, YArm OpLev Calibration CavityCoupling.pdf
Entry  Thu Jun 9 19:08:58 2016, Varun, Update, Electronics, Anti-Aliasing Filter update 32to65.jpg65to98.png
Entry  Thu Jun 9 18:54:40 2016, Aakash, Update, General, About Acromag | SURF 2016 
Entry  Thu Jun 9 15:14:46 2016, jamie, Update, CDS, old fb restarted, test of new daqdon fb1 aborted for time being Jamie.jpg
Entry  Thu Jun 9 09:57:06 2016, Aakash, Update, General, Seismometer Enclosure Development 
Entry  Fri Jun 3 17:56:14 2016, Varun, Update, General, DAFI update 
    Reply  Tue Jun 7 18:20:18 2016, Varun, Update, General, DAFI update 
       Reply  Wed Jun 8 16:12:38 2016, Varun, Update, General, DAFI update dafi.pngagcin.pdfagcout.pdf
Entry  Mon Jun 6 16:41:36 2016, ericq, Update, CDS, FB upgrade work 
    Reply  Tue Jun 7 11:12:47 2016, jamie, Update, CDS, DAQD UPGRADE WORK UNDERWAY 
       Reply  Tue Jun 7 20:49:50 2016, jamie, Update, CDS, DAQD work ongoing 
          Reply  Wed Jun 8 08:34:55 2016, jamie, Update, CDS, DAQD work ongoing 
Entry  Tue Jun 7 17:21:13 2016, Aakash, Update, General, SURF 2016 
Entry  Fri Jun 3 13:05:18 2016, ericq, Update, CDS, CDS Notes 
Entry  Wed Jun 1 16:28:28 2016, ericq, Update, Electronics, Common board Op amp input offsets 
    Reply  Fri Jun 3 12:53:44 2016, ericq, Update, Electronics, Common board Op amp input offsets CMboard_offsets.png
Entry  Wed Jun 1 11:19:14 2016, Varun, Update, General, Update of work till now 
Entry  Fri May 20 17:36:06 2016, gautam, Update, LSC, New stands for TransMon/Oplev QPDs 
    Reply  Wed Jun 1 09:06:38 2016, Steve, Update, LSC, New stands for TransMon/Oplev QPDs pdIb.PDFpdstand.pdf
Entry  Mon May 30 18:19:50 2016, Johannes, Update, CDS, ASS medm screen update 
Entry  Fri May 27 11:54:22 2016, Varun, Update, General, Package delivery 
Entry  Fri May 27 02:52:53 2016, ericq, Update, LSC, Restoring high BW single arm control 
Entry  Wed May 25 14:21:29 2016, Max Isi, Update, General, Summary page configuration 
Entry  Wed May 25 02:54:09 2016, ericq, Update, General, Odds and ends 
Entry  Tue May 24 17:55:17 2016, Varun, Update, Electronics, Using Altium 
Entry  Tue May 10 03:44:59 2016, ericq, Update, LSC, Relocked 2016-05-10_DARMcoherence.pdf
Entry  Thu Apr 28 15:23:11 2016, ericq, Update, LSC, Green PDH demod lowpass 
    Reply  Thu Apr 28 18:53:05 2016, rana, Update, LSC, Green PDH demod lowpass 
       Reply  Fri Apr 29 16:13:36 2016, ericq, Update, LSC, Green PDH demod lowpass IMG_3186.jpgpdh_lpf.pngelp_liso.zip
          Reply  Fri May 6 16:42:12 2016, ericq, Update, LSC, Green PDH demod lowpass pdh_lpf.pngAUX_X_PDH_OLG_May6.png
             Reply  Fri May 6 19:08:52 2016, rana, Update, LSC, Green PDH demod lowpass 
                Reply  Sat May 7 09:40:40 2016, ericq, Update, LSC, Green PDH demod lowpass 
                   Reply  Sun May 8 08:39:21 2016, rana, Update, LSC, Green PDH demod lowpass 
Entry  Mon May 2 17:06:58 2016, rana, Summary, COC, G&H optics to Fullerton/HWS for anneal testing 20160427_182305.jpg
Entry  Thu Apr 28 08:49:47 2016, Steve, Update, PEM, possible noise sources schedule Campus_B&W_Map-2.pdf
Entry  Wed Apr 27 14:06:31 2016, rana, Summary, General, meeting notes 
Entry  Mon Apr 25 11:07:06 2016, Steve, Update, SUS, spare SOS tower ETMXreplacment.jpg
    Reply  Wed Apr 27 09:45:56 2016, rana, Update, SUS, spare SOS tower 
Entry  Wed Apr 27 09:05:10 2016, Steve, Update, General, AP viewport APg.jpgAP.jpgAPspiderWebs.jpg
Entry  Fri Mar 11 16:52:53 2016, Steve, Update, PEM, leaky roof leakyRoof.jpgleakyRoofA.jpg
    Reply  Fri Apr 22 13:58:13 2016, Steve, Update, PEM, leaky roof is fixed leakyRoof_(2).jpg
Entry  Thu Apr 14 17:30:18 2016, ericq, Update, General, PLL measurement ongoing 
    Reply  Fri Apr 15 03:02:44 2016, ericq, Update, General, New AUX laser measurements aux_innolight_freqPSD.pdfaux_innolight_AMPM.pdfaux_innolight_data.zip
       Reply  Fri Apr 15 18:35:57 2016, gautam, Update, General, New AUX laser measurements PSL_AUX_TEMP_SCAN.pdfPSL_AUX_TEMP_SCAN.mat
          Reply  Fri Apr 15 23:11:49 2016, gautam, Update, General, Innolight 1W moved to SP table 
             Reply  Mon Apr 18 00:29:00 2016, gautam, Update, General, Beam profiling + injection current scan 6x
Entry  Tue Mar 22 21:30:15 2016, Koji, Update, IOO, PMCIMC aligned, WFS offset adjusted 08.png
    Reply  Tue Apr 12 22:41:00 2016, Koji, Update, IOO, PMC/IMC aligned, WFS offset adjusted 
Entry  Tue Jan 26 17:50:22 2016, gautam, Update, Green Locking, Lightwave frequency noise measurement 
    Reply  Wed Jan 27 18:19:45 2016, gautam, Update, Green Locking, Lightwave frequency noise measurement 
       Reply  Thu Jan 28 00:29:30 2016, gautam, Update, Green Locking, Lightwave frequency noise measurement PLL_OLG.pdfFreq_noise_comparison.pdf
          Reply  Mon Feb 1 18:11:25 2016, gautam, Update, Green Locking, Lightwave frequency noise measurement Free_running_frequency_noise_comparison.pdf
       Reply  Fri Jan 29 14:43:47 2016, Steve, Update, Green Locking, Innolight laser is 10 years old inno1W.pdf
          Reply  Fri Jan 29 16:55:27 2016, rana, Update, Green Locking, Innolight laser is 10 years old 
             Reply  Sat Jan 30 00:12:22 2016, gautam, Update, Green Locking, Innolight laser is 10 years old RIN_comparison.pdf
                Reply  Sat Jan 30 09:56:24 2016, Koji, Update, Green Locking, Innolight laser is 10 years old 
                   Reply  Mon Feb 1 15:16:28 2016, gautam, Update, Green Locking, Innolight laser is 10 years old 
                      Reply  Mon Feb 1 15:43:18 2016, Koji, Update, Green Locking, Innolight laser is 10 years old 
                         Reply  Fri Feb 5 15:02:13 2016, gautam, Update, Green Locking, X-end NE cable 
          Reply  Fri Feb 12 11:10:49 2016, Steve, Update, Green Locking, Innolight laser is 10 years old inno1W.jpg
          Reply  Mon Mar 21 14:29:32 2016, Steve, Update, Calibration-Repair, 1W Innolight laser repair diagnoses 
             Reply  Thu Mar 24 07:56:09 2016, Steve, Update, Calibration-Repair, NO Noise Eater for 1W Innolight 
                Reply  Mon Apr 11 17:03:41 2016, Steve, Update, Calibration-Repair, 1W Innolight repair completed 
Entry  Tue Mar 29 03:16:21 2016, ericq, Update, LSC, DRFPMI Locked Once More 2016-03-29_calibdarm.pdf2016-03-29_DRFPMI_errctrl.pdfDRFPMI_DTT.zip
    Reply  Wed Mar 30 16:40:24 2016, ericq, Update, LSC, 2016 vs 2010 2016_vs_2010.png
    Reply  Mon Apr 11 16:06:30 2016, ericq, Update, LSC, DRFPMI Data Archived 
Entry  Thu Mar 10 16:29:32 2016, gautam, Update, endtable upgrade, Inventory check Inventory_check.pdfDoubler_comparison.pdf
    Reply  Thu Mar 10 16:32:45 2016, rana, Update, endtable upgrade, Inventory check 
       Reply  Mon Mar 14 22:42:23 2016, gautam, Update, endtable upgrade, Inventory check 
       Reply  Mon Mar 28 10:43:18 2016, Steve, Update, endtable upgrade, ETMX 4'x2' optical table pictures ETMX4x2Layout.jpgETMX_4x2.JPGETMXopt_4x2.JPG
          Reply  Wed Mar 30 17:38:52 2016, gautam, Update, endtable upgrade, X end table proposed layout  ETMX_3x2.JPGlayout_details_20160328.pdfETMX_proposed_layout.pdf
             Reply  Thu Mar 31 09:38:41 2016, Steve, Update, endtable upgrade, Y end 4x3 existing layout ETMY4x3layout.jpg
                Reply  Thu Mar 31 19:49:31 2016, gautam, Update, endtable upgrade, proposed layout v2 ETMX_proposed_layout_v2.pdf
                   Reply  Mon Apr 4 10:59:12 2016, gautam, Update, endtable upgrade, proposed layout v3 ETMX_proposed_layout_v3.pdfIR_modematch.pdfGreen_modematch.pdfXendALaMode.zipETMX_proposed_layout_dimensions.dwg
                      Reply  Mon Apr 4 15:04:14 2016, gautam, Update, endtable upgrade, COMPONENT REMOVAL 
                         Reply  Tue Apr 5 11:42:17 2016, gaericqutam, Update, endtable upgrade, TABLE REMOVAL 
                            Reply  Wed Apr 6 17:52:21 2016, gautam, Update, endtable upgrade, First contact cleaning commenced 
                               Reply  Thu Apr 7 12:51:24 2016, gautam, Update, endtable upgrade, Beam height differences 
                                  Reply  Thu Apr 7 14:30:58 2016, Steve, Update, endtable upgrade, ETMX table height ETMXbrs.pngETMX.jpgIMG_0618.JPGETMX.jpgETMXwc.jpg
                                     Reply  Fri Apr 8 09:13:20 2016, Steve, Update, endtable upgrade, ETMX-T beam height ETMXalignedT.pngETMXF.jpg
Entry  Fri Apr 1 13:11:26 2016, ericq, Update, WienerFiltering, Bilinear Noise Testing bilinear_drive.pdf40m_bilin.pdf
Entry  Mon Sep 29 11:17:14 2008, steve, Update, SAFETY, horizontal viewports are protected with lexan 
    Reply  Wed Mar 30 11:35:24 2016, steve, Update, safety, BS visitor's viewport is protected with lexan 
Entry  Mon Mar 28 08:30:09 2016, Steve, Update, SUS, PRM damping restored shaking.png
Entry  Sat Mar 26 18:28:24 2016, Koji, Update, elog, elogd flakiness 
Entry  Mon Mar 11 10:20:36 2013, Max Horton, Summary, Computers, Attempted Smart UPS 2200 Battery Replacement upsB.jpgupsBa.jpg
    Reply  Thu Jun 6 15:46:10 2013, Max Horton, Summary, General, Smart UPS 2200 Batteries Replaced 
    Reply  Wed Mar 23 11:55:47 2016, Steve, Update, General, Smart UPS 2200 Battery Replaced 
Entry  Tue Mar 15 10:31:58 2016, Steve, Update, IOO, Laser is turned back on 2WlaserOff-On.png
    Reply  Tue Mar 22 14:12:18 2016, Steve, Update, IOO, Laser is turned back on off-onAgain.png
Entry  Mon Mar 21 10:07:45 2016, Steve, Update, SUS, ETMX enclosure update ETMXenclosure.jpg
Entry  Fri Mar 18 11:04:56 2016, Steve, Update, SUS, inverted pendulum invPeng.jpg
ELOG V3.1.3-