Thu Nov 1 08:48:42 2012, steve, Update, Alignment, progress, then setback - trend of BS table shift  
| +
Fri Dec 14 09:05:04 2012, steve, Update, PEM, TT after eq 6.1
| +
Wed Mar 6 11:33:09 2013, steve, Update, SAFETY, safety audit 2013
| +
Wed Mar 13 16:04:24 2013, steve, Update, SAFETY, laser safety glasses checked
| +
Tue Mar 19 10:30:00 2013, steve, Update, SAFETY, crane inspection 2013 
| +
Fri May 31 10:25:17 2013, steve, Update, safety, first aid kits refilled
| +
Thu Jun 6 16:33:19 2013, steve, Update, safety, updated laser inventory
| +
Fri Aug 30 08:08:29 2013, steve, Update, safety, fire horns-flashers tested OK
| +
Wed Feb 19 08:07:01 2014, steve, Update, safety, annual laser safety glasses check 
| +
Tue Feb 25 16:54:57 2014, steve, Update, safety, safety audit 2014
| +
Thu Feb 27 13:11:13 2014, steve, Update, safety, safety audit correction 
|
Thu Mar 6 11:43:17 2014, steve, Update, General, Guralp control unit 
| +
Fri Mar 7 16:56:17 2014, steve, Update, IOO, IOO qpds centered
| +
Mon Mar 10 09:28:48 2014, steve, Update, IOO, IOO pointing 2 days 
| +
Thu Mar 13 16:05:48 2014, steve, Update, safety, safety audit 2014
| +
Mon Mar 17 10:50:58 2014, steve, Update, safety, 2014 annual crane certification
|
Fri Mar 21 14:59:44 2014, steve, Update, PEM, controling dust
| +
Mon Mar 24 22:13:37 2014, steve, Update, General, Power Failure
| +
Tue Mar 25 14:52:57 2014, steve, Update, VAC, vacuum is recovered
| +
Fri Mar 28 16:26:20 2014, steve, Update, VAC, RGA scan after power failure
| +
Fri Apr 11 14:57:53 2014, steve, Update, LSC, congratulation 
| +
Mon Apr 28 17:27:29 2014, steve, Update, safety, safety audit 2014
| +
Tue Apr 29 00:11:03 2014, steve, Update, safety, safety audit 2014
| +
Thu May 1 17:14:36 2014, steve, Update, PSL, thin window AR measured
| +
Fri May 2 08:15:54 2014, steve, Update, safety, safety audit 2014
| +
Fri May 2 10:38:29 2014, steve, Update, PSL, thin window AR measured
|
Tue May 6 09:46:50 2014, steve, Update, PEM, cleaning day
| +
Tue May 6 10:22:28 2014, steve, Update, CDS, c1ioo dolphin fiber
| +
Tue May 6 18:32:14 2014, steve, Update, LSC, TRY 60Hz noise hunt
| +
Wed May 7 14:01:36 2014, steve, Update, LSC, TRY 60Hz noise hunt
| +
Thu May 8 17:25:17 2014, steve, Update, LSC, TRY 60Hz noise hunt
| +
Fri May 9 11:23:11 2014, steve, Update, Green Locking, decreased X green light power
| +
Mon May 12 14:42:25 2014, steve, Update, endtable upgrade, optical table enclosure wall proposal and table at ETMY  
| +
Fri May 16 16:08:12 2014, steve, Update, LSC, Isolating base plates
| +
Mon Jun 9 09:41:06 2014, steve, Update, safety, safety training
| +
Thu Jun 19 10:39:22 2014, steve, Update, safety, surf safety training
| +
Thu Jun 19 14:12:45 2014, steve, Update, safety, optical table scans
| +
Thu Jun 19 17:11:52 2014, steve, Update, PEM, it is warmer today
|
Fri Jun 20 14:42:57 2014, steve, Update, SUS, vac illuminators turned off
|
Mon Jul 7 08:13:41 2014, steve, Update, General, yes,there was firework
| +
Fri Aug 8 11:22:35 2014, steve, Summary, SUS, oplev laser summary
| +
Mon Aug 11 10:23:39 2014, steve, Summary, SUS, oplev laser summary updated
| +
Thu Sep 18 10:08:07 2014, steve, Summary, SUS, oplev laser summary updated
| +
Mon Sep 22 10:18:58 2014, steve, Update, PEM, lab temperatures
| +
Thu Oct 2 14:36:52 2014, steve, Update, PEM, oil drops on vertex crane
| +
Tue Nov 4 10:40:46 2014, steve, Update, PEM, lab temperatures and particle counts
| +
Mon Dec 8 09:03:49 2014, steve, Update, PEM, air cond maintenance tomorrow morning
| +
Wed Dec 10 14:26:13 2014, steve, Update, PEM, air cond maintenance and particle plot
|
Fri Feb 27 10:25:24 2015, steve, Update, Cameras, quad picture problem
| +
Thu Mar 19 17:11:32 2015, steve, Summary, SUS, oplev laser summary updated
|
|