    Reply  Tue Apr 5 11:42:17 2016, gaericqutam, Update, endtable upgrade, TABLE REMOVAL 
There is currently no table at the X end! 

We have moved the vast majority of the optics to a temporary storage breadbord, and moved the end table itself to the workbench at the end. 

Steve says Transportation is coming at 1PM to put the new table in.
    Reply  Wed Apr 6 17:52:21 2016, gautam, Update, endtable upgrade, First contact cleaning commenced 
I've begun cleaning the optics that will eventually go back onto the newly installed X-endtable. We decided that First Contact was the way to go
(as opposed to methanol drag wiping). Koji demonstrated the application of the (red) First Contact solution onto a 2" mirror - I then proceeded to
work on the rest of the optics. We are broadly following the procedure in E1000079 - first one coat of First Contact solution is applied, then a small
    Reply  Thu Apr 7 12:51:24 2016, gautam, Update, endtable upgrade, Beam height differences 
Steve has finished installing the enclosure on the new endtable. So Eric and I decided to try and lock the X arm and measure the beam height of the transmitted
IR beam relative to the endtable. We initially thought of using POX DC as a the LSC trigger but this did not work as there was no significant change in
it when the arm was flashing. Eric then tried misaligning the ITM and using AS110 as a trigger - this worked. We then recompiled the ASS model to take
    Reply  Thu Apr 7 14:30:58 2016, Steve, Update, endtable upgrade, ETMX table height ETMXbrs.pngETMX.jpgIMG_0618.JPGETMX.jpgETMXwc.jpg
 




Quote:



Steve has finished installing
    Reply  Fri Apr 8 09:13:20 2016, Steve, Update, endtable upgrade, ETMX-T beam height ETMXalignedT.pngETMXF.jpg
X arm resonating after alignment, beam height on ETMX optical table ~4.75"

 
Entry  Wed Apr 13 00:56:07 2016, gautam, Update, endtable upgrade, X endtable repopulation 
Over the last couple of days, I've been working on restoring the optical layout on the X-endtable. Some notes about the status as of today:

Lightwave NPRO output power

The output power from the lightwave NPRO is about 210mW (as measured with the calorimeter). This is significantly lower than the value of ~300mW
    Reply  Wed Apr 13 11:00:28 2016, Steve, Update, endtable upgrade, X endtable repopulation 
ETMX optical table is grounded to ETMX chamber through 1 Mohms

The doubling oven temp controller is installed to reach its cable.

 
    Reply  Wed Apr 13 18:25:07 2016, gautam, Update, endtable upgrade, Lightwave health check 
[Koji,gautam]

Lightwave NPRO information:

Model: 126-1064-700
    Reply  Fri Apr 15 18:38:12 2016, gautam, Update, endtable upgrade, Lightwave health check - NO IMPROVEMENT 
I re-measured the power levels today.

We have ~205mW out of the NPRO, and ~190mW after the Faraday. It doesn't look like the situation is going to improve dramatically. I'm
going to work on a revised layout with the Innolight as soon as I've profiled the beam from it, and hopefully, by Monday, we can decide that we are
    Reply  Tue Apr 19 18:37:29 2016, gautam, Update, endtable upgrade, Laser swap + optical layout IR_modematch_19April2016_2.pdf
Summary of work done over the last two days


Lightwave NPRO + controller moved to PSL table


​​The interlock is not connected
to the controller
Controller is not powered


Innolight NPRO + controller installed at endtable

​​​​Interlock
    Reply  Thu Apr 21 14:25:52 2016, gautam, Update, endtable upgrade, Green light recovered IMG_6567.JPGIMG_6568.JPGCVI_reflectivity.jpeg
I've made progress on the new layout up to the doubling oven. After doing the coarse alignment with the diode current to the NPRO at ~1A, I turned
it back up to the nominal 2A. I then rotated the HWP before the IR Faraday such that only ~470mW of IR
power is going into the doubler (the rest is being dumped on razor beam dumps). After tuning the alignment of the IR into the doubling oven using the steering
    Reply  Tue Apr 26 15:22:35 2016, Steve, Update, endtable upgrade, Cleaning ETMX vacuum dirty window ETMX-Tvp.jpgETMX-TvpDetail.jpg
Gautom is progressing with the layout nicely. The X-arm transmission window have not seen cleaning for decades. This should be the time to do it. Here
is picture of dirtiness.

It is not that simple... How much effort should we put in it? The hole table with 1W inno laser plus... set up now about ~500 lbs  We can
    Reply  Tue Apr 26 23:19:42 2016, gautam, Update, endtable upgrade, Green aligned to arm - high order mode flashes seen IMG_2219.JPGIMG_2220.JPG
Attachment #1

Layout as of today. Most of the green path is done. The Green REFL PD + PZT mirrors have not been hooked up to their respective power sources
yet (I wonder if it's okay to start laying cables through the feedthroughs on either end of the table already, or
    Reply  Wed Apr 27 15:04:47 2016, Steve, Update, endtable upgrade, Cleaning ETMX vacuum dirty window 1cETMX-Tcmp.jpg
It looks very promising.

 
    Reply  Thu Apr 28 00:41:08 2016, gautam, Update, endtable upgrade, more progress - Transmon PD installed 
The IR Transmon system is almost completely laid out, only the QPD remains to be installed. Some notes:


The "problem" with excessive green power reflected from the harmonic separator has been resolved. It is just very sensitive
to the angle of incidence. In the present configuration, there is ~10uW of green power reflected from either side, which shouldn't be too worrisome.
    Reply  Fri Apr 29 00:55:46 2016, gautam, Update, endtable upgrade, green PDH locked to Xarm 
Using the modulation frequency suggested here, I hooked up the PDH setup at the X-end and
succeeded in locking the green to the X arm. I then rotated the HWP after the green Faraday to maximize TRX output, which after a cursory alignment optimization
is ~0.2 (I believe we were used to seeing ~0.3 before the end laser went wonky). Obviously much optimization/characterization remains to be done. But for
    Reply  Fri Apr 29 16:05:23 2016, gautam, Update, endtable upgrade, Cleaning ETMX vacuum dirty window IMG_0755.JPG
After a second round of F.C. application, I think the window is clean enough and there are no residual F.C. pieces anywhere near the central parts of
the window (indeed I think we got most of it off). So I am going to go ahead and install the Oplev. 




    Reply  Mon May 2 19:14:18 2016, gautam, Update, endtable upgrade, Optical layout almost complete ETMX_wedge.pdf
With Steve's help, I installed the Oplev earlier today. I adjusted the positions of the two lenses until I deemed the spot size on the QPD satisfactory
by eye. As a quick check, I verified using the DTT template that the UGF is ~5Hz for both pitch and yaw. There is ~300uW of power incident on the QPD (out
of ~2mW from the HeNe). In terms of ADC counts, this is ~13,000 counts which is about what we had prior to taking the endtable apart. There are a couple
    Reply  Thu May 5 03:05:37 2016, gautam, Update, endtable upgrade, ALS status update ALS_noiseSpec_5May2016_2.pdfCoherence_5May2016.pdfimage.jpeg
[ericQ, gautam]

Today we spent some time looking into the PDH situation at the X end. A summary of our findings.


There is something that I don't understand with regards to the modulation signal being sent to the laser PZT via the sum+HPF pomona
    Reply  Thu May 5 14:05:01 2016, rana, Update, endtable upgrade, ALS status update 
All seems very fishy. Its not good to put attenuators and filters in nilly-willy.


Once the post-PD bandpass has been designed and constructed, you should be able to use whatever PD gain setting gives you the best SNR.
There's no need to use more PD gain than necessary; it just reduces the PD bandwidth. What is the input referred current noise of the PD at the different
    Reply  Thu May 5 21:28:44 2016, gautam, Update, endtable upgrade, Innolight PZT capacitance 
I suggested in an earlier elog that after the repair of the NPRO, the PZT capacitance
may have changed dramatically. This seems unlikely - I measured the PZT capacitance with the BK Precision LCR meter and found it to be 2.62
nF, which is in excellent agreement with the numbers from elogs 
    Reply  Thu May 19 16:29:20 2016, Steve, Update, endtable upgrade, Optical layout almost complete ETMX_4x3_closed.jpgsealedETMXenclosure.jpg
 

 
    Reply  Fri Sep 30 19:53:07 2016, gautam, Update, endtable upgrade, X end IR pickoff fiber coupled 
[johannes, gautam]

Today we re-installed the fiber coupler on the X-endtable to couple some of the PSL light into a fiber that runs to the PSL table, where it is
combined with a similar PSL pickoff to make an IR beat between the EX AUX laser and the PSL. The main motivation behind this was to make the process of
    Reply  Wed Oct 5 16:28:10 2016, gautam, Update, endtable upgrade, EX laser power monitor PD installed 
I installed a 10% BS to pick off some of the light going to the IR fiber, and have added a Thorlabs PDA55 PD to the EX table setup. The idea is to be
able to monitor the power output of the EX NPRO over long time scales, and also to serve as an additional diagnostic tool for when ALS gets glitchy etc.
There is about 0.4mW of IR power incident on the PD (as measured with the Ophir power meter), which translates to ~2500 ADC counts (~1.67V as measured
Entry  Tue Apr 22 22:19:02 2008, rob, Metaphysics, lore, jiggling sliders 

In the interests of tacit communication of scientific knowledge, I here reveal a nugget of knowledge which may or may not prove useful to new LIGOites:
sometimes when front-end machines are rebooted, the hardware they control can wind up in a state which is not accurately represented by the EPICS values
Entry  Sun Nov 2 20:21:58 2008, rana, Configuration, lore, HP 5550dtn (Grazia) set up on allegra 
I set up printing to grazia from allegra. The CUPS interface was not as straightforward as Tobin had made it seem in the Wiki. I had to type in the IP address
and port number by hand.
    Reply  Thu Jan 8 16:49:37 2009, rana, Configuration, lore, HP 5550dtn (Grazia) set up on allegra 
[quote]I set up printing to grazia from allegra. The CUPS interface was not as straightforward as Tobin had made it seem in the Wiki. I had to type in the
IP address and port number by hand.
Entry  Wed May 13 02:53:12 2009, rob, Summary, lore, Channel Hopping: That ancient enemy (MC problems) 
We were stymied tonight by a problem which began late this afternoon.  The MC would periodically go angularly unstable, breaking lock and tripping
the MC2 watchdogs.  Suspicion fell naturally upon McWFS.
Eventually I traced the problem to the MC3 SIDE damping, which appeared to not work--it wouldn't actually damp, and the Vmon values did not correspond
    Reply  Wed May 13 14:43:29 2009, rob, Summary, lore, Channel Hopping: That ancient enemy (MC problems) MC3sidemon.png


    
        
            Quote:
        
        
            
            We were stymied tonight by a problem which began late this afternoon.  The MC would periodically go angularly
Entry  Fri Oct 23 15:02:00 2009, rob, Update, lore, marconi phase 
So, it appears that one doesn't even have to change the Marconi set frequency to alter the phase of the output signal.  It appears that other front
panel actions (turning external modulations on/off, changing the modulation type) can do it as well.  At least that's what I conclude from earlier
this morning, when after setting up the f2 Marconi (166MHz) for external AM, the double-demod handoff in the DRMI no longer worked.  Luckily this
    Reply  Sat Oct 24 04:57:33 2009, rana, Update, lore, marconi phase 


    
        
            Quote:
        
        
            
            So, it appears that one doesn't even have to change the Marconi set frequency to alter the phase of the output signal. 
Entry  Mon Dec 14 15:18:18 2009, Jenne, Update, lore, armLoss script ran....results confidential 
I ran the armLoss script for both Xarm and Yarm.  The results are confidential, pending the completion of Alberto's cavity pole/finesse measurement
due to the 'bet' as to what the new losses are after the drag wiping.
If you're the kind of person who likes to look at their Chrismas presents, the log files with the results are in the usual place for this script:
    Reply  Wed Feb 3 09:01:42 2010, rob, Update, lore, IFO isn't playing nice tonight 


    
        
            Quote:
        
        
            
            I checked the situation from my home and the problem was solved.
Entry  Fri Feb 12 14:19:28 2010, rana, steve, HowTo, lore, International Fax 
Steve showed me how to send an international fax today:

    Load paper.
    Dial:   011 - (country code) - number
    Press START (either the black or color
option)
    wait for the screaming fax noise
    Done

 
Entry  Wed Oct 6 14:49:54 2010, rana, Summary, lore, Steve on the sea jacques.jpg
 
Entry  Mon Jul 11 14:03:37 2011, steve, HowTo, lore, how to visit your old lab P1080069.JPG
Alberto is visiting us from Australia. He brought some terrific presents. It is going to be very demanding task to wait for the rest of the 40m team
to return from Wales to taste coffee:  PNG Peaberry of Wagonga, Monsooned Malabar of Jindebah and Signature Blue Blend of Cosmorex.
Entry  Sun May 27 17:19:27 2012, rana, Summary, lore, Strawberries 20120527_145826.jpg
 We have placed some sweet giant strawberries in the fridge; free for eating for anyone working in the lab today or tomorrow:
Entry  Mon Jul 22 03:10:41 2013, rana, Summary, lore, Angel of the Y End Table? asdasd.jpg
 Trying to take an image or movie of the ETMY Transmon cam, we got instead this attached image.
I think it is just some scattered green light, but others in the control room think that it is a message from somewhere or someone...
    Reply  Mon Jul 22 06:58:17 2013, Lisa, Summary, lore, Angel of the Y End Table? image.jpg


    
        
            Quote:
        
        
            

            Trying to take an image or movie of the ETMY Transmon cam, we got instead this attached image.
Entry  Fri May 16 20:55:18 2014, Jamie, Frogs, lore, un-full-screening Ubuntu windows with F11 
Last week Rana and I struggled to figure out how to un-full-screen windows on the Ubuntu workstations that appeared to be stuck in some sort of full
screen mode such that the "Titlebar" was not on the screen.  Nothing seemed to work.  We were in despair.
Well, there is now hope: it appears that this really is a "fullscreen" mode that can be activated by hitting F11.  
Entry  Wed Mar 29 09:24:28 2017, Steve, Update, lore, summery pages 
The summery pages are working at a slow motion speed. It's response time 12 minutes.
Entry  Thu Oct 2 16:44:28 2008, steve, Summary, oplevs, optical levers 
The idea is to push the  UGF to 10 Hz of the TM oplev servos with quiet HeNe laser.
We measured good intensity noise of JDS 1103P in May 2007 and converted most of the TM oplevs to it.
The ITMs still have the noisy 670nm , 1 mW, diode lasers to begin with.
Entry  Thu Jan 22 12:08:59 2009, pete, Update, oplevs, oplev calibration 
Following the procedure described in Royal Reinecke's 2006 SURF report, I've calibrated the ETMY yaw oplev DOF.  The idea is to sweep the mirror tilt, measuring
the transmitted cavity power and the oplev error signal.  The cavity power can be related to the mirror tilt in radians following D. Anderson APPLIED OPTICS,
Vol. 23, No. 17, 1984.  
Entry  Thu Jan 22 23:36:50 2009, pete, HowTo, oplevs, arm cavity oplev calibration ETMYpitpower.pngETMYpitcal.png
calibrated the y-arm oplevs.  the procedure is contained in a matlab script.  the whereabouts of this script will be revealed in a future log entry.

ITMYpit  140 microrad/ct
    Reply  Fri Jan 23 12:48:12 2009, Kakeru, Update, oplevs, arm cavity oplev calibration ITMX_pitch.png
I calibrated optlevs of x and y arm cavity, indipendently from Peter's work.

ITMX pit: 77 microrad/ct
Entry  Fri Jan 23 16:33:27 2009, pete, Update, oplevs, x-arm oplev calibrations 
ITMXpit 71 microrad/ct
ITMXyaw 77 microrad/ct
ETMXpit 430 microrad/ct
    Reply  Thu Jan 29 17:24:41 2009, Kakeru, Update, oplevs, arm cavity oplev calibration 
I calibrated optlevs again. My previous work has a lot of mistakes, so ignore it.

ITMX pit: 195 microrad/ct
Entry  Mon Mar 9 17:11:38 2009, Alberto, Configuration, oplevs, optical levers centering 
Yoichi, Alberto
this afternoon we centered the optical levers for all the optics.
To do that we first ran the alignment scripts for all the cavities.
    Reply  Sat Mar 14 22:53:12 2009, Kakeru, Update, oplevs, arm cavity oplev calibration oplev.pdf
I finished a calibration of optical levers.

To calibrate oplevs, I locked appropriate cavity and tilted a mirror.
    Reply  Fri Mar 20 15:37:58 2009, Kakeru, Update, oplevs, arm cavity oplev calibration 

I calibrated several oplevs with OSEM signal as a confirmation of my fitting method the method is: