40m QIL Cryo_Lab CTN SUS_Lab TCS_Lab OMC_Lab CRIME_Lab FEA ENG_Labs OptContFac Mariner WBEEShop
  40m Log, Page 341 of 344  Not logged in ELOG logo
New entries since:Wed Dec 31 16:00:00 1969
    Reply  Tue Nov 27 17:06:51 2018, Steve, Configuration, VAC, Agilent 84FS turbo installed as TP2 
Chub & Steve,

We swapped in our  replacement of Varian V70D "bear-can" turbo as factory clean.

The new
Entry  Thu Jan 3 21:17:49 2019, rana, Configuration, Computers, Workstation Upgrade: Donatella -> Scientific Linux 7.2 IMG_20190103_205158.jpg
donatella was one of our last workstations running ubuntu12. we installed SL7 on there today


had to use a DVD; wouldn't boot from USB stick
made sure to use userID=1001 and groupID=1001 at the initial install part
went
to the Keith Thorne LLO wiki on SL7
The 'yum update' command failed due to a gstreamer conflict. I did "yum
Entry  Mon Jan 7 11:54:12 2019, Jon, Configuration, Computer Scripts / Programs, Vac system shutdown 
I'm making a controlled shutdown of the vac controls to add new ADC channels. Will advise when it's back up.
    Reply  Mon Jan 7 19:21:45 2019, Jon, Configuration, Computer Scripts / Programs, Vac system shutdown 
ADC work finished for the day. The vac controls are back up, with all valves CLOSED and all pumps OFF.




Quote:



I'm making a controlled shutdown of the vac controls to add new ADC channels. Will advise when it's back
Entry  Fri Mar 8 08:40:26 2019, Anjali, Configuration, , Frequency stabilization of 1 micron source Homodyne_setup.png
The schematic of the homodyne configuration is shown below.

Following are the list of components




Item
Quantity
Availability
Part
Entry  Tue Jun 11 19:25:58 2019, aaron, Configuration, BHD, Reviving the single OMC BHD design? singleOMC.pdf
I drew out some idea of how we might use a single OMC to clean both paths of the BHD after mixing, without being susceptible to polarization-dependent
effects within the OMC. Basically, can we send the two legs of the BHD into the OMC counterpropagating. I've attached a diagram.

I think one issue would be scattered light, since any backscatter directly couples into the counterpropagating mode, and thus directly to
Entry  Thu Jun 13 22:21:44 2019, Koji, Configuration, CDS, Paola wireless connected to martian 
SURFs had trouble connecting paola to martian via wireless.
Of course, it requires a fixed IP but it had not it yet. So I went to chiara and gave 192.168.113.110 as "paolawl". Note that the wired
connection has .111 and it is "paola".
    Reply  Fri Jun 21 19:22:40 2019, Koji, Configuration, BHD, Reviving the single OMC BHD design? 
I think a Faraday rotator rotates the polarizations in a same way for both forward and backward beam, and it's not like in this figure.
And the transmission through multiple faradays will also be a big issue.
Entry  Mon Jun 24 13:48:36 2019, Kruthi, Configuration, CDS, Giada wireless connection 
[Gautam, Kruthi]

This afternoon, Gautam helped me setup Giada to access the GigE installed for MC2. Unlike Paola, which was being used earlier, Giada has a better
battery life and doesn't shutdown when the charger is unplugged. Gautam configured Giada to enable its wireless connection to Martian, just like Koji
Entry  Wed Jul 17 17:56:18 2019, Koji, Configuration, Computers, Gave resolv.conf to giada 
Kruthi noticed that she could not login to rossa from giada.

I checked /etc/resolv.conf and it was

nameserver 127.0.0.1
    Reply  Thu Jul 25 14:28:03 2019, gautam, Configuration, Computers, firewalld disabled for EPICS CA donatellaCommissioning.png
I think rana did some more changes to this workstation to make it useful for commissioning activities - but the MEDM screens were still white blanks.
The problem was that the firewalld wasn't disabled (last two steps of the KThorne
setup wiki). I disabled it. Now donatella can run MEDM, ndscope and StripTool. DTT doesn't work to get online data because of a "Synchronization
Entry  Sun Dec 8 20:48:29 2019, rana, Configuration, Computers, Megatron: starts up grade 
I noticed recently that Megatron was running Ubuntu 12, so I've started its OS upgrade.


Unlocked the IMC + disabled the autolocker from the LockMC screen + closed the PSL shutter (IMC REFL shutter doesn't seem to do anythin)
Disabled
the "FSS" slow servo on the FSS screen
did sudo apt-get update, sudo apt-get upgrade, and then sudo apt-get do-release-upgrade which
    Reply  Wed Dec 11 22:01:24 2019, rana, Configuration, Computers, Megatron: starts up grade 
Megatron is now running Ubuntu 18.04 LTS.

We should probably be able to load all the LSC software on there by adding the appropriate Debian repos.

I have re-enabled the cron jobs in the crontab.
Entry  Mon Jan 13 15:47:37 2020, shruti, Configuration, Computer Scripts / Programs, c1psl burt restore 
[Yehonathan, Jon, Shruti]

Since the PMC would not lock, we initially burt-restored the c1psl machine to the last available shapshot (Dec 10th 2019), but it still would
not lock.
Entry  Wed Jan 15 14:10:28 2020, Jon, Configuration, PSL, New EPICS database for C1PSL + C1IOO 
Summary

I have completed the new EPICS channel database for the c1psl and c1ioo channels
(now combined into the new c1psl Acromag machine). I've tested a small subset of channels on the electronics bench to confirm that the addressing and
analog channel calibrations are correct in a general sense. At this point, we are handing the chassis off to Chub to complete the wiring of the Acromag terminals
    Reply  Wed Jan 22 19:17:20 2020, gautam, Configuration, Computers, Megatron: starts up grade 
upgrade was done

cronjob testing wasn't one by one 😢 

burt snapshots were gone
    Reply  Thu Jan 23 15:32:42 2020, gautam, Configuration, Computers, Megatron: starts up grade 
The burt snapshotting is still not so reliable - for whatever reason, the number of snapshot files that actually get written looks random. For example,
the 14:19 backup today got all the snaps, but 15:19 did not. There are no obvious red flags in either the cron job logs or the autoburt log files. I also
don't see any clues when I run the script in a shell. It'll be good if someone can take a look at this.
Entry  Thu Jan 23 23:07:04 2020, Jon, Configuration, PSL, c1psl breakout board wiring c1psl_feedthrough_wiring.pdf
To facilitate wiring the c1psl chassis and scripting loopback tests, I've compiled a distilled spreadsheet with the Acromag-to-breakout board
wiring, broken down by connector. This information is extractable from the master
spreadsheet, but not easily. There were also a few apparent typos which are fixed here.
Entry  Mon Jan 27 14:01:01 2020, Jordan, Configuration, General, Repurposed Sorenson Power Supply  
The 24 V Sorenson (2nd from bottom) in the small rack west of 1x2 was repurposed to 12V 600 mA, and was run to a terminal block on the north side of
1X1. Cables were routed underneath 1X1 and 1X2 to the terminal blocks. 12V was then routed to the PSL table and banana clip terminals were added.
    Reply  Mon Jan 27 18:16:30 2020, gautam, Configuration, Computers, Sluggish megatron? 
I've also been noticing that the IMC Autolocker scripts are running rather sluggishly on Megatron recently. Some evidence - on Feb 11 2019, the time
between the mcup script starting and finishing is ~10 seconds (I don't post the raw log output here to keep the elog short). However, post upgrade,
the mean time is more like ~45-50 seconds. Rana mentioned he didn't install any of the modern LIGO software tools post upgrade, so maybe we are using
    Reply  Tue Jan 28 15:39:04 2020, gautam, Configuration, Computers, Sluggish megatron? 
There were a bunch of medm processes stalled on megatron (connected with screenshot taking). To see if they were interfering with the other scripts,
I killed all of the medm processes, and commented out the line in the crontab that runs the screenshots every 10 mins. Let's see if this improves stability.
    Reply  Tue Jan 28 17:36:45 2020, gautam, Configuration, Computers, Local EPICS7.0 installed on megatron 
[Jon, gautam]

We found that the caput commands were taking much longer to execute
on megatron than on pianosa (for example). Suspecting that this had something to do with the fact that megatron was using EPICS binaries from the shared
Entry  Tue Jan 28 19:12:30 2020, Jon, Configuration, PSL, Spare channels added to c1psl chassis c1psl_feedthrough_wiring_v2.pdf
After some discussion with Gautam, I decided to build more spare channels into the new c1psl machine. This is anticipation of adding new laser and ISS
channels in the near future, to avoid having to disconnect the installed chassis and pull it out of the rack. The spare channels will be wired to DB37M
feedthroughs on the front side of the chassis, with enough wire length to be able to pull the breakout boards out of the front to reconfigure their wiring
Entry  Mon Jun 22 10:43:25 2020, Jon, Configuration, VAC, Vac maintenance at 11 am 
The vac system is going down at 11 am today for planned maintenance:


Re-install the repaired TP2 and TP3 dry pumps [ELOG 15417]
Incorporate
an auto-mailer and flag channel into the controls code for signaling tripped interlocks [ELOG 15413]


We
    Reply  Mon Jun 22 20:06:06 2020, Jon, Configuration, VAC, Vac maintenance complete Pumpdown-6-22-20.png
This work is finally complete. The dry pump replacement was finished quickly but the controls updates required some substantial debugging.

For one, the mailer code I had been given to install would not run against Python 3.4 on c1vac, the version run by the vac controls since about
a year ago. There were some missing dependencies that proved difficult to install (related to Debian Jessie becoming unsupported). I ultimately solved
    Reply  Tue Jun 23 17:54:56 2020, rana, Configuration, VAC, Vac maintenance complete 
I propose we go for all CAPS for all channel names. The lower case names is just a holdover from Steve/Alan from the 90's. All other systems are
all CAPS.

It avoids us having to force them all to UPPER in the scripts and channel lists.
Entry  Wed Jul 1 18:03:04 2020, Jon, Configuration, VAC, UPS replacements 
​I looked into how the new UPS devices suggested by Chub would communicate with the vac interlocks. There are several possible ways, listed in
order of preference:


Python interlock service directly queries the UPS via a USB link using the (unofficial) tripplite
    Reply  Thu Jul 9 18:00:35 2020, Jon, Configuration, VAC, UPS replacements 
Chub has placed the order for two new UPS units (115V for TP2/3 and a 220V version for TP1).

Tripp Lite SMX1000RT2U: https://www.grainger.com/product/TRIPP-LITE-UPS-System-36HW20

Tripp
Lite Smart1000LCD: https://www.grainger.com/product/TRIPP-LITE-Smart-UPS-1AYA6

They
Entry  Sat Aug 8 07:36:52 2020, Sanika Khadkikar, Configuration, Calibration-Repair, BS Seismometer - Multi-channel calibration BS_X-EY_X.pngBS_Y-EY_Y.pngBS_Z-EY_Z.pngtimeseries.png
Summary : 

I have been working on analyzing the seismic data obtained from the 3 seismometers present in the lab. I noticed while looking at the combined
time series and the gain plots of the 3 seismometers that there is some error in the calibration of the BS seismometer. The EX and the EY seismometers
Entry  Fri Aug 14 10:10:56 2020, Jon, Configuration, VAC, Vacuum repairs today 
The vac system is going down now for planned repairs [ELOG 15499]. It will likely take
most of the day. Will advise when it's back up.
    Reply  Sat Aug 15 02:02:13 2020, Jon, Configuration, VAC, Vacuum repairs today 
Vacuum work is completed. The TP2 and TP3 interlocks have been overhauled as proposed in ELOG
15499 and seem to be performing reliably. We're now back in the nominal system state, with TP2 again backing for TP1 and TP3 pumping
the annuli. I'll post the full implementation details in the morning.
    Reply  Sat Aug 15 15:12:22 2020, Jon, Configuration, VAC, Overhaul of small turbo pump interlocks small_tp_signal_routing.pngsmall_tp_interlock_signal.pngsmall_tp_signal_routing.pngmedm_screen.png
Summary

Yesterday I completed the switchover of small turbo pump interlocks as proposed in ELOG
15499. This overhaul altogether eliminates the dependency on RS232 readbacks, which had become unreliable (glitchy) in both controllers.
In their place, the V4(5) valve-close interlocks are now predicated on an analog controller output whose voltage goes high when the rotation
Entry  Fri Dec 18 22:59:12 2020, Jon, Configuration, CDS, Updated CDS upgrade plan CDS_2020_Dec.pdfCDS_2020_Dec.graffle
Attached is the layout for the "intermediate" CDS upgrade option, as was discussed on Wednesday. Under this plan:



Existing FEs stay where they are (they are not moved to a single rack)


Dolphin IPC remains PCIe Gen 1
    Reply  Mon Dec 21 09:28:50 2020, Jamie, Configuration, CDS, Updated CDS upgrade plan 



Quote:



Attached is the layout for the "intermediate" CDS upgrade option, as was discussed on Wednesday.
Under this plan:
    Reply  Wed Dec 23 23:06:45 2020, gautam, Configuration, CDS, Updated CDS upgrade plan 

The diagram should clearly show the host machines and the expansion chassis and the interconnects between them.
We no longer have
any Gentoo bootserver or diskless FEs.
The "c1lsc" host is in 1X4 not 1Y3.
The connection between c1lsc and Dolphin switch
is copper not fiber. I don't know how many Gbps it is. But if the switch is 10 Gbps, are they really selling interface cables that have lower speed?
    Reply  Tue Jan 19 14:05:25 2021, Jon, Configuration, CDS, Updated CDS upgrade plan 40m_CDS_Network_-_Planned.pdf40m_CDS_Network_-_Current.pdf
I've produced updated diagrams of the CDS layout, taking the comments in 15476 into
account. I've also converted the 40m's diagrams from Omnigraffle ($150/license) to the free, cloud-based platform draw.io.
I had never heard of draw.io, but I found that it has most all the same functionality. It also integrates nicely with Google Drive.
    Reply  Tue Jan 19 15:43:24 2021, gautam, Configuration, CDS, Updated CDS upgrade plan 
Not sure if 1Y1 can accommodate both c1sus2 and c1bhd as well as the various electronics chassis that will have to be installed. There may need to be
some distribution between 1Y1 and 1Y3. Does Koji's new wiring also specify which racks hold which chassis?

Some minor improvements to the diagram:
    Reply  Mon Mar 15 20:40:01 2021, rana, Configuration, Computers, installed QTgrace on donatella for dataviewer cutiegrace.png
I installed QTgrace using yum on donatella. Both Grace and XMgrace are broken due to some boring fight between the Fedora package maintainers and the (non existent) Grace
support team. So I have symlinked it:
Entry  Wed Mar 17 09:05:01 2021, Paco, Anchal, Configuration, Computers, 40m Control Room Changes 

Switched positions of allegra and donatella.
While doing so, the hdmi cable previously used by donatella snapped. We replaced this
cable by another unused cable we found connected only on one end to rossa. We should get more HDMI cables if that cable was in use for some other purpose.
Paco
bought a bluetooth speaker/mic that is placed infront of allegra and it's usb adapter is connected to iMac's keyboard in the bottom. With the new
    Reply  Wed Apr 14 13:16:20 2021, Anchal, Configuration, Computers, 40m Control Room Changes 

I have confirmed that the old two monitors' backlighting is not working. One can see the impression of the display without any brightness
on them. Both old monitors are on the shelf behind.
Today we got a monitor and mouse from Mike. I had to change /etc/default/grub GRUB_GFXMODE
to 1920x1200@30 on allegra for it to work with the(any) monitor.
Allegra is Debian 10 with latest cds-workstation installed on it. It is a good
Entry  Wed May 26 11:45:57 2021, Anchal, Paco, Configuration, IMC, MC2 analog camera 
[Anchal, Paco]

We went near the MC2 area and opened the lid to inspect the GigE and analog video monitors for MC2. Looked like whatever image is coming through
the viewport is split into the GigE (for beam tracking) and the analog monitor. We hooked the monitor found on the floor nearby and tweaked the analog
Entry  Thu Aug 26 10:30:14 2021, Jamie, Configuration, CDS, front end time synchronization fixed? 
I've been looking at why the front end NTP time synchronization did not seem to be working.  I think it might not have been working because
the NTP server the front ends were point to, fb1, was not actually responding to synchronization requests.

I cleaned up some things on fb1 and the front ends, which I think unstuck things.
Entry  Mon Jan 24 12:33:41 2022, rana, Configuration, Wiki, AIC Wiki: txz files allowed 
I updated the mime.local.conf file for the AIC Wiki so as to allow attachments with the .txz
format. THis should be persistent over upgrades, since its a local file.
Entry  Wed May 25 16:56:44 2022, Paco, Configuration, BHD, IFO recovery - IMC alignment 
[Yuta, Paco]

We aligned IMC to recover the IFO progressively. First step was to center the MC REFL beamspot on the camera as well as the WFS DC. Then slide
MC2 and MC3 together. Below are the alignment slider positions before/after.
    Reply  Wed May 25 17:34:47 2022, yuta, Configuration, BHD, IFO recovery - IFO alignment Screenshot_2022-05-25_17-47-57.png
IFO aligned to maximize flashings, except for GRY and LO-AS.

What we did:
    Reply  Thu May 26 19:55:43 2022, yuta, Configuration, BHD, Oplevs centered, BHD DCPDs are now online elog_1Y2.JPGelog_BHD.JPGelog_box.JPGScreenshot_2022-05-26_17-37-27_IFOaligned_OplevCentered.pngScreenshot_2022-05-26_20-35-02.png
[Paco, Yuta]

We have aligned the IFO (except for LO-AS and GRY), and centered all the oplevs.
We have also restored Gautam's in-air BHD DCPD setup and placed it to ITMY table.
    Reply  Fri May 27 17:45:53 2022, yuta, Configuration, BHD, BHD camera installed, GRY aligned 
[JC, Paco, Yuta]

After the IFO recovery (elog 40m/16881), we installed an analog camera for BHD fringe
    Reply  Thu Jun 2 20:05:37 2022, yuta, Configuration, PSL, IMC input power recovered to 1W, some alignment works Before.JPGAfter.JPG
[Paco, Yuta]

We have increased the output power from the PSL table to 951 mW (it was 96.7 mW).
    Reply  Fri Jun 3 12:13:58 2022, Paco, Configuration, CDS, Fix RFM channels  SoGreen.png
[Paco, Yuta]

We tried fixing the issue of LSC_TRY and LSC_TRX channels not working. We first did some investigation, and just like previously
reported by Chris, narrowed down the issue to the RFM channels coming from c1iscex/c1iscey.
Entry  Mon Jun 6 16:09:23 2022, rana, Configuration, DetChar, Summary Pages: seis BLRMS 
I updated the config file c1pem.ini in /users/public_html/detcharsummary/ConfigFiles, and commited it so I hope it works, but I did not have git push
permissions. Does anyone know what is the idea here? Should we do our own personal git clone and modify that way or shoudl we do it with the control account.

Wiki needs to clear out all the outdated information on this workflow.
ELOG V3.1.3-